List Your Equipment For Free  /  Seller Login

Construction Crews Rebuilding Three Bridges on I-35

Tue May 19, 2020 - West Edition #11
Irwin Rapoport – CEG Correspondent


TxDOT’s $78.8 million I-35 from Stassney Lane to William Cannon Drive project will improve safety and mobility in south Austin.
TxDOT’s $78.8 million I-35 from Stassney Lane to William Cannon Drive project will improve safety and mobility in south Austin.
TxDOT’s $78.8 million I-35 from Stassney Lane to William Cannon Drive project will improve safety and mobility in south Austin.
 Placing concrete for Stassney Lane bridge deck – a variety of equipment was key to pouring the new bridge decks.  A Kobelco SK07 excavator performs work at the job site. Demolition, which was done at night, required the use of several excavators, including those manufactured by Doosan and Link-Belt. OHL setting beams for span 2 of the Stassney Bridge.

Crews from OHL USA Inc. started work on the Texas Department of Transportation's (TxDOT) $78.8 million I-35 from Stassney Lane to William Cannon Drive project to improve safety and mobility in south Austin in July 2016, and they are expected to deliver the new and updated structure this summer.

The project is reconstructing the bridge structures at Stassney Lane and William Cannon Drive and the frontage road bridge over Williamson Creek, adding new U-turns at Stassney and William Cannon, widening 3.2 miles of mainlanes to incorporate shoulders and extended entrance/exit lanes, reconfiguring entrance and exit ramps, installing some drainage infrastructure, improving bicycle and pedestrian accommodations, and adding new safety and high mast lighting.

The work schedule was divided into three phases. Thus far, the tasks that have been completed include: paving the inside median area of the project limits, modifying and constructing entrance/exit ramps, constructing/widening the outside mainlanes and frontage roads, constructing U-turn bridges in both directions at William Cannon and Stassney, and reconstructing a new widened bridge at William Cannon Drive.

Construction Phases

Reconstruction of the bridge structures at William Cannon Drive and Stassney Lane were done in several phases in a logical progression.

"The demolition and reconstruction of the bridges at Stassney Lane and William Cannon Drive under live traffic was challenging," said said Oscar Salazar-Bueno, Construction Enterprises, Inc.'s (CEI) project manager for the I-35 Stassney Lane to William Cannon project. "Our project team implemented a detailed action plan to accomplish that work, including performing several traffic switches and completing the work in phases in order to minimize the impact to the traveling public."

For the William Cannon Drive bridge, a total of 32 massive beams, each spanning nearly 95 ft. and weighing over 90,000 lbs. — the equivalent to the height of about five giraffes and the weight of seven adult elephants — were set over four evenings as crews worked overnight, diverting alternating north and southbound I-35 mainlane traffic to frontage roads.

To place the beams, crews operated two cranes in tandem and field staff worked to ensure proper placement, all while monitoring safety and efficiency. The William Cannon Drive bridge has 30,405 sq. ft. of reinforced concrete slab, 1,450.59 linear feet of prestressed concrete box beam (4B34), and 4,779.49 linear feet of prestressed concrete box beam (SB34).

"On average, each bridge beam was set in 11.3 minutes, which is an impressive feat, to say the least," Salazar-Bueno said.

For the Stassney Lane bridge, 44 beams were set. The new bridge has 20,731 sq. ft. of reinforced concrete slab, 1,375.21 linear ft. of prestressed concrete box beam (4B40), and 2,946.89 linear ft. of prestressed concrete box beam (SB40).

Current Status

Currently, crews are reconstructing a new widened bridge at Stassney Lane (from two lanes in each direction to three), with two through lanes and one dedicated left-turn lane in each direction, working on ramp modifications, and finishing up pedestrian enhancements. Once this work is complete, crews will perform final paving operations for the entire 3.2 miles.

The final roadway configuration includes three mainlanes in each direction with extended entrance/exit lanes for the entire length of the project.

"The final configuration includes the same number of mainlanes, but will now have extended entrance/exit lanes in both directions to facilitate better merging and traffic flow," said Wheelis. "There will be three frontage road lanes in each direction, whereas the existing configuration only had two lanes in each direction."

Crews have put in many nights shifts as some work, including demolition could only be done at night when lane closure were possible.

The project, as noted, covered many aspects and overcame some challenges along the way.

"The project included upgrading some existing City of Austin water and wastewater lines, as well as the relocation of existing structures like manholes, drainage inlets, and water valves," said Salazar-Bueno. "The contractor, city inspector, TxDOT, and the CEI team worked jointly to accommodate the relocations within the limited right-of-way to keep the project going."

Project Timeline

The road work, as noted covered many aspects and was done in several phases in a logical progression. The paving operations for the mainline lanes are expected to start in a few months.

Drainage, grading, electrical, and illumination work, such as installing intelligent traffic signals along the frontage roads, continues throughout the project limits. Construction is expected to be complete later this summer.

Peak days have had 50 plus OHL and subcontractor employees on-site. The subcontractors include: Austin Underground, The Levy Company, Earth Reinforcing Systems, JC Communications, AWP, RSI, Aaron Concrete, C2 Concrete, and Austin Materials.

The amounts of materials that have been excavated and demolished – concrete, asphalt, rebar and steel, and earth and rock are still being finalized. Some of this material has been recycled on-site, while some has been taken to recycling centers for processing. Materials for the new road construction are being updated as work proceeds.

Equipment-wise, OHL is using cranes from Liebheer and other manufacturers, excavators: Doosan, Liebherr, CAT, and others; and various dozers, loaders, pavers, rollers, generators, and other heavy standard construction equipment.

The project was designed in-house by TxDOT.

Project development was funded by TxDOT and the construction ($79 million) is being funded by Proposition 1, which dedicates a portion of oil and gas tax revenue to the state highway fund, and by the Capital Area Metropolitan Planning Organization, and TxDOT.

"Lane weaving on the north and southbound I-35 mainlanes from Stassney Lane to William Cannon Drive can lead to reduced mobility for motorists," said Brad Wheelis, public information officer for TxDOT's Austin District. "The slowing and stopping of traffic on the mainlanes can also lead to traffic delays at area intersections. With more than 200,000 vehicles a day traveling on this segment of I-35 each day, this project will improve mobility, safety, and connectivity for all modes of transportation along and across I-35."

Lauded as a "soaring symphony of engineering," I-35 has been a backbone of Texas travel since it opened in1962. Planning for the Strassney Lane initiative began several years ago, with a public open house held in December 2013. Plans, Specifications and Estimates, schematics, and environmental documentation were prepared in 2014-15, and the project went out to bid (letting) in November 2015.

"I-35 through Central Texas is one of the most congested highways in Texas," said Wheelis. "Improvements to this 50-year-old interstate are required to address the increased congestion and travel-time delay due to population and employment growth."

The project team has informed impacted motorists about all construction-related lane closures and detours with directional signage, smart work zone display boards, and flaggers, as well as by www.my35construction.org, a construction hotline, and email.

"Safety during construction is our top priority," said Wheelis, who noted that the project team worked with businesses to provide access and minimize impacts whenever possible. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Crews Work to Complete Metro Atlanta Project

ABC: Nonresidential Construction Adds 17,100 Jobs in May

DEVELON Introduces Its Smallest Mini Excavator Yet

Highway Crews in Minnesota See End in Sight

John Deere Debuts New P-Tier Skid Steer, Compact Track Loader Models, Attachments

Charles Blalock & Sons Work On TDOT Project

Hultdins New Design SG260S, New Model SG310S Grapples

Liebherr Spotlights Trina Baughman, Digital Products Product Manager


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA