List Your Equipment For Free  /  Seller Login

Kriger Finishes Project Nobody Else Wanted to Tackle

Mon February 15, 2010 - Northeast Edition
Construction Equipment Guide


Kriger Construction Inc., based out of Dickson City, Pa., was the only contractor to bid on a Luzerne County project to build a new park with boat and kayak ramps/launches along the Susquehanna River. The Susquehanna River is notorious for its rapidly rising and falling water levels. The first 40 ft. (12.2 m) of the two new ramps would be built below the water level. It was a challenge most contractors were afraid of tackling.

The ramps, themselves, would be 40 ft. wide, 110 ft. (33.5 m) long, and built on a 10 percent slope as required by the Pennsylvania Fish and Boat Commission.

“While researching the project, we spoke with several people in the industry about the best way of finishing the ramps and they all recommended GOMACO,” James Marzolino, general superintendent of Kriger Construction, said. “We chose the C-450 because of the width and the thickness of the concrete being placed and the grade it was being placed at. We felt a cylinder finisher would give us the quality we wanted and a better end-product.”

Work on the project was planned around the river. When the water level was at its lowest, Kriger Construction moved its crews in and worked double shifts to complete the project. The first phase involved building the coffer dam to hold the water back. Sheets of PZ-27 piling were driven into the river bed at approximately 25 to 30 ft. (7.6 to 9.1 m) deep, or 2.5 times the depth of the water, to form the coffer dam.

After the dam was built, grade was prepared and two mats of heavy gauge wire mesh was placed on grade. Rails for the C-450 were set and the finisher was placed on the rails. Two GOMACO service representatives were onsite assisting with set-up of the C-450, training and guidance on the first pours.

“The service reps were a big help, because we didn’t have any experience with the GOMACO product,” Marzolino said. “We spent some time with them just going over the machine, learning about it, what precautions to take, and just general operation of the machine. They were a big help.”

Kriger Construction completed each ramp in two pours, 55 ft. (16.8 m) long, 40 ft. wide, and 8 in. (20 cm) thick. The concrete and concrete pump were supplied locally by Pocono Transcrete. The mix was a 4000 psi (27.6 MPa) design with a 4 in. (10 cm) slump for pumping.

To help accommodate the steep 10 percent slope of the ramps, Kriger Construction outfitted its C-450 with an all-wheel drive system and 36 in. (91 cm) bogies with cupped wheels. Then, as an added safety precaution, the C-450 was attached to a winch and a D5 dozer. Kriger never had to utilize the extra precaution.

The C-450 is equipped with double-drum cylinders and misting spray bar to provide the ultimate finish. The C-450’s automatic advance moved the machine forward 12 in. (30 cm) automatically on each pass.

“We were dealing with some pretty tight finishing tolerances,” Marzolino said. “It had to be under 0.25 inch over a 10 foot distance. The C-450 easily accomplished that requirement.”

Each of the two pours was accomplished in less than five hours, from start to finish. Specifications required a heavy broom finish on the new ramp, and joints were saw cut on 10 ft. (3 m) centers the day after the pours. Twenty-eight days after the final pour, the ramps were opened up to the awaiting public.

The ramps are part of the public boat launches on the North Branch of the Susquehanna River for the city of Wilkes-Barre and the surrounding communities. The project included not only the ramps/launches, but also a 2 acre (0.8 ha) parking area, a bioretention garden and 1,800 sq. yds. (1,505 sq m) of earthwork.

Kriger Construction has more work planned for its new C-450. Its next project is finishing two bridge decks in Luzerne County, Pa.

Alfred Kriger is the president of Kriger Construction. For more information, call Kriger Construction at 570/383-2042 or e-mail [email protected]. Kriger Construction is located 7 Oakwood Dr in Dickson City, Pa.




Today's top stories

SEPTA Builds Major Transportation Center

National Equipment League — Heavy Equipment Operation as a Professional Sport — Launches Season Two

Washington Bridge in Providence, R.I., Undergoes Demolition

Construction Industry Optimistically Preparing for New Year Ahead

Capital Express Central Project Ramps Up in Texas

Nevada DOT Awards $54M Contract for U.S. 50 Renovation in Ely

Construction Set for $37M Wildlife Crossing in Wyoming

PCL Construction's Special Projects Division Sets 2024 Record With Nearly 270 New Projects









39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085