Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
It is expected that the reconstruction of the transmission line will provide for an end of May re-energization.
Thu January 18, 2018 - National Edition
AEP Texas announced it will expedite the rebuilding of a vital power line in the Coastal Bend area that was devastated by Hurricane Harvey.
The Aransas Pass – Port Aransas Transmission Line Rebuild Project components include:
Right-of-way agents and crews have been performing preconstruction activities in the area and have begun contacting affected landowners and businesses to notify them of additional field work and construction activities as reconstruction of the line is undertaken. It is expected that the reconstruction of the transmission line will provide for an end of May re-energization.
“AEP Texas continues to work to improve and upgrade the initial repairs following the storm,” said AEP Texas External Affairs Manager Patrick King. “That's why we are rebuilding the damaged local electric transmission lines and equipment to strengthen the transmission grid and storm-harden the existing infrastructure.
By Sept. 9, AEP Texas, along with thousands of workers from American Electric Power, contractors and other utilities helped to restore power to over 96 percent of the customers who could still take power following the storm, which made landfall on the evening of Aug. 25.
“Transmission projects such as the Aransas Pass – Port Aransas Transmission Line Rebuild Project are critical to the electric system,” King continued. “AEP Texas realizes that construction projects may inconvenience landowners and the public and is committed to working with the community to minimize any impact.”
AEP Texas serves nearly one million electric meters in the deregulated Texas marketplace. As an energy delivery (wires) company, AEP Texas delivers electricity safely and reliably to homes, businesses and industry across its nearly 100,000-sq.-mi. service territory in south and west Texas. AEP Texas also builds new power lines, restores service following outages and reads the meters via advanced meter technology for retail electric providers (REPs) throughout its service territory. The company also connects or disconnects service upon the orders of the REPs.