List Your Equipment For Free  /  Seller Login

ALL Brings Together Two 900-Ton ATs to Replace Downtown Cleveland Railroad Bridge

In downtown Cleveland, two 900-ton cranes were used side by side to replace a railroad bridge section over West Third Street. The unique heavy lift operation involved intricate planning and execution, resulting in the successful replacement within a seven-hour time frame.

Wed August 28, 2024 - Midwest Edition #24
ALL Crane


The two Liebherr LTM 1750-9.1 all terrain cranes were configured with 161 ft. of main boom and maximum counterweight.
Photo courtesy of ALL Crane
The two Liebherr LTM 1750-9.1 all terrain cranes were configured with 161 ft. of main boom and maximum counterweight.
The two Liebherr LTM 1750-9.1 all terrain cranes were configured with 161 ft. of main boom and maximum counterweight.    (Photo courtesy of ALL Crane) “When you’re in the thick of planning the project, you’re thinking about all the little details that lead to a successful lift,” said Zac Kasparek, sales representative of ALL Erection & Crane Rental.   (Photo courtesy of ALL Crane) One crane was set up directly on the street below the span, the other in a neighboring empty lot, with the cranes only approximately 25 ft. apart.   (Photo courtesy of ALL Crane)

The challenge: replace a section of railroad bridge in a close, urban setting — in which you will need to use the remaining tracks to both roll the old bridge section away and roll the replacement section into the work zone.

The solution: a rarely seen heavy lift operation requiring two 900-ton cranes. Plus, they'll be working side-by-side, but won't be performing any dual picks.

"This kind of job only happens once or twice a career," said Chad Rados, project coordinator of ALL Erection & Crane Rental, flagship branch of the ALL Family of Companies, which provided cranes for the job.

The operation happened this summer in Cleveland, Ohio, at the Norfolk Southern railroad bridge over West Third Street near the city's downtown. One crane was set up directly on the street below the span, the other in a neighboring empty lot, with the cranes only approximately 25 ft. apart.

"When you're in the thick of planning the project, you're thinking about all the little details that lead to a successful lift," said Zac Kasparek, sales representative of ALL Erection & Crane Rental.

Photo courtesy of ALL Crane

"Then the day came that we've got two 900-ton cranes set up and ready to work, and it occurred to me … the fact that we have two cranes of that size mobilized in one area, on the same job, is pretty impressive."

Both were Liebherr LTM 1750-9.1 all terrain cranes configured with 161 ft. of main boom and maximum counterweight. The crane on West Third Street, with its boom directly over the replacement area, also was outfitted with Y-guying to bolster boom capacity.

The operation called for the West Third Street crane to single-pick the old bridge section and set it on a flatbed rail car directly east of the now-missing section, on a second set of tracks. A road-rail vehicle (a truck able to drive on train tracks) powered the flatbed to the east, where the second Liebherr LTM 1750 lifted the old section off the flatbed, lowered it to the lot below, then picked up the new replacement bridge section and set it on the flatbed.

The road-rail vehicle next drove the flatbed back to the Third Street crane, which picked it from the railcar and set it into the gap created by the absence of the old bridge section.

In essence, with the flatbed acting as a go-between, the two giant cranes formed an assembly line.

Total elapsed time: about seven hours.

The need to use two 900-ton cranes in this manner was prompted by a variety of factors. The top elevation of the bridge was 55 ft. Because of the size of the bridge section, which measured 90 ft. and weighed 243,000 lbs., rigging required a large spreader beam. The narrowness of West Third Street left no room to lay down the old bridge section or the new one, requiring a shift to the adjacent empty lot.

Photo courtesy of ALL Crane

"This is a classic case of the job picking the cranes," said Rados. "The site logistics told us it was going to have to be two cranes. The limited amount of room and weights of the two pieces made it clear that the two 1750s were the best option."

It's unusual to deploy two cranes with such high capacities on a single job. ALL owns three of the units, and pulled these two from branches in Lima, Ohio, and Atlanta.

It took approximately 40 truckloads to deliver both cranes to the deceptively complex job site, and two to three days total to assemble them before and disassemble them afterward. Meanwhile, crane maneuvers all took place within a single seven-hour period in which rail service to the tracks was shut down.

For more information, visit www.allcrane.com.

This story also appears on Crane Equipment Guide.




Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







\\ \\ \\