List Your Equipment For Free  /  Seller Login

Beck and Bellucci Leads Way on Bridge Work in Peterborough

Wed September 09, 2020 - Northeast Edition #19
Ken Liebeskind -CEG Correspondent


The replacement of the Main Street Bridge in Peterborough, N.H., is the main element of a construction project that started this summer and also includes work on Route 202, which intersects with Main Street.
The replacement of the Main Street Bridge in Peterborough, N.H., is the main element of a construction project that started this summer and also includes work on Route 202, which intersects with Main Street.
The replacement of the Main Street Bridge in Peterborough, N.H., is the main element of a construction project that started this summer and also includes work on Route 202, which intersects with Main Street. Beck and Bellucci constructed a prefabricated truss-type pedestrian bridge to replace the sidewalk on the north side of the bridge. Improvements to the current bridge were planned to address the deteriorating condition of the bridge with a rigid frame that shows evidence of heavy leakage, minor to moderate cracking in the frame and a surface cracked with random potholes. The budget for the job is $14.7 million, with the state paying for 80 percent and the town 20 percent. Construction equipment in use on the job includes a Link-Belt RTC80110 110-ton rough-terrain crane, a Link-Belt RTC 8050 50-ton rough-terrain crane and a Link-Belt LS 108 50-ton lattice boom crane. The Main Street Bridge over the Contoocook River in the center of Peterborough is a 75-ft.-long rigid frame structure that was constructed in 1940 to replace a two-span structure that was lost to flooding during the hurricane of 1938. The existing Main Street Bridge will be replaced with a cast-in-place concrete frame bridge on spread cast-in-place concrete footings, according to the NHDOT report. The replacement bridge will be wider, measuring 47 ft., 7 in. to allow for the widening of traffic lanes to improve vehicle movement and safety over the bridge and through the Main Street/Route 202 intersection.

The replacement of the Main Street Bridge in Peterborough, N.H., is the main element of a construction project that started this summer and also includes work on Route 202, which intersects with Main Street.

Aaron Lachance, a project manager and structural engineer of Hoyle, Tanner and Associates, Manchester, N.H., the design firm on the job, said, "It's five projects rolled into one," with the bridge replacement joining a list that also includes structural work on Route 202.

Chris Schroeder, engineer/estimator of Beck and Bellucci, Franklin, N.H., the lead contractor on the job, said, "The scope of the work is to demolish and replace the existing concrete rigid frame arch bridge on Main Street and replace the decorative masonry stones salvaged from the existing bridge on the new bridge.

"We will rehabilitate several hundred feet of existing stone retaining wall along Route 202 injecting grout to stabilize existing dry-laid boulder masonry," he added. "We will replace 175 feet of existing stone retaining wall with a new ‘King Pile' wall system. The King Pile wall consists of drilled shafts with embedded vertical beams, with sheet piles spanning between the beams. We will also realign Route 202 near the Main Street intersection."

As for the sequence of construction events in the project, Schroder said, "We are currently installing temporary retaining walls to allow for construction of an access road at the existing Route 202 retaining wall and beginning demolition of the concrete bridge. We are also removing the existing bridge masonry, with stones being labeled and stored for re-use on the new structure. This fall and winter we will complete demolition of the bridge and construct new concrete footings and the king pile wall should also be installed. In spring 2021 we will install EFCO concrete formwork, place the arch superstructure and begin rehab work on the Route 202 retaining wall. By fall 2021 we should be complete with the new bridge and retaining wall work and the new bridge will open by spring 2022."

Schroeder noted the construction equipment in use on the job includes a Link-Belt RTC80110 110-ton rough-terrain crane, a Link-Belt RTC 8050 50-ton rough-terrain crane, a Link-Belt LS 108 50-ton lattice boom crane and Caterpillar 300-class excavators, skid steer and dozer.

The Main Street Bridge over the Contoocook River in the center of Peterborough is a 75-ft.-long rigid frame structure that was constructed in 1940 to replace a two-span structure that was lost to flooding during the hurricane of 1938. It is one of the state's red-list bridges, which means it has one or more major structural elements in poor condition.

Improvements to the current bridge were planned to address the deteriorating condition of the bridge with a rigid frame that shows evidence of heavy leakage, minor to moderate cracking in the frame and a surface cracked with random potholes.

The goal according to a NHDOT report "is to provide a low maintenance bridge that meets NHDOT requirements while minimizing cost and construction duration."

Beck and Bellucci won the job with a low bid.

The existing Main Street Bridge will be replaced with a cast-in-place concrete frame bridge on spread cast-in-place concrete footings, according to the NHDOT report. The replacement bridge will be wider, measuring 47 ft., 7 in. to allow for the widening of traffic lanes to improve vehicle movement and safety over the bridge and through the Main Street/Route 202 intersection. The lane widths of the bridge of 10 ft., 10 ft. and 10 ft. will be replaced by widths of 12 ft., 7.5 in., 11 ft. and 10 ft., 7.5 in. from the north side of the bridge to the south.

A portion of the existing mortar rubble masonry ashlar retaining wall adjacent to the bridge and northern portion of the boulder wall will be replaced with a sheeting and king pile retaining wall system with stone facing that will retain the existing wall's character. The southern portion of the boulder wall will be retained and stabilized with micropiles and ground injection. Approximately 75 ft. of the northern portion of the cast-in-place retaining wall will be removed and the adjacent roadway embankments will be regraded to accommodate the lack of retaining wall. The southern portion of the cast-in-place retaining wall will be retained and rehabilitated, as needed.

The budget for the job is $14.7 million, with the state paying for 80 percent and the town 20 percent. Ninety percent of the state's share is paid by the Federal Highway Administration and the Municipal Off-System Bridge Rehabilitation and Rehabilitation Program. In January, Peterborough residents voted to approve an additional $1.4 million for bridge repair.

Prior to beginning work on the bridge and Route 202, Beck and Bellucci constructed a prefabricated truss-type pedestrian bridge to replace the sidewalk on the north side of the bridge. The bridge is 105 ft. in span and was erected to accommodate pedestrian traffic across the river during construction of the vehicular bridge. The pedestrian bridge will be removed after the new bridge is opened.

Kayla Hampe, a structural engineer of Hoyle, Tanner & Associates, said, "The original intent was to have a permanent pedestrian bridge, but the design was revised to eliminate the pedestrian bridge and widen the vehicular bridge to accommodate a sidewalk on the downstream side, in addition to the sidewalk on the upstream side."

The Main Street Bridge was closed to traffic on April 13 and will not reopen until the project is complete. CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\