Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Thu May 09, 2019 - Northeast Edition #10
The Maine Department of Transportation is conducting road reconstruction and bridge replacement work along Route 302 in Fryeburg. The work begins at the New Hampshire state line and runs for more than four miles along Route 302, skipping a mile and a half of Fryeburg's downtown business district.
The work began in April.
Reed & Reed of Woolwich, Maine, is the lead contractor for the bridge replacement and AJ Coleman of Rochester, N.H., is the lead contractor on the Route 302 road work.
Reed & Reed is reconstructing the Eddy Flats and Short Ridge bridges, which both run over Route 302.
Jim Wentworth, Reed & Reed's project manager on the Fryeburg job, said the company is using a Manitowoc 10000 90-ton crawler crane and other large cranes on the job.
"We're in phase one construction and will construct one half of each bridge at a time," he said. "We're currently doing roadway work, clearing trees and utility lines have been moved. We expect the job to be complete by the end of the summer."
The job has a completion date of August 2020 but Wentworth said it will be completed early to accommodate the Fryeburg Fair in October.
"Two lanes of traffic are needed in and out of town for the fair and there is only one lane of traffic during construction," Wentworth said.
Patrick Holland, vice president of construction operations of AJ Coleman, said, "We're rebuilding and widening Route 302 to widen the canopy and allow more room for drainage. We using recycled asphalt and blending it with the gravel below and paving with new concrete on top of that."
Construction equipment to be used includes feller bunchers, skid steers and bucket trucks.
The company also performed earth work early in the job and utilized excavators and bulldozers, Holland said. Caterpillar equipment is being used.
The company will meet the August 2020 deadline and not complete all work this year. "The injection process is time dependent and we can't inject after Sept. 15, so we will be injecting and paving next season," Holland said.
Ernest Martin, a Maine DOT spokesperson, said the budget for the project is $15.4 million, with 80 percent funded by the federal government and 20 percent paid by the state.
Mark Debowski, project manager of Stantec of Auburn, N.H., the design firm on the project, said Northeast Extreme Tee (NEXT) beams were used on the bridges, which offers improved durability and design flexibility. Both bridges were expanded to 34-ft. width and 58-ft. span to match the width of the paved shoulders on Route 302. He said Route 302 is being widened to add paved shoulders on both sides and 2,300 ft. of sidewalk is being added on sections of the highway.
"The existing bridges were 31 feet and the new bridges will be 34 feet," Wentworth said. "We're gaining almost five feet of roadway width. They were designed for the amount of traffic. The Saco River runs through it and the new bridges will be set back from the river and further up the banks of the river instead of on the edge of the river."
The Route 302 road reconstruction proceeds from the New Hampshire state line east 1.16 mi. to Elm Street and from Recreational Complex Road east 3.22 mi. to the bridge over Osgood Brook.
"The decision was made to do the construction three or four years ago. The road was in bad shape from Bridgton to the state line and needs to be completely reconstructed and widened," said Sharon Jackson, Fryeburg town manager.
CEG