Broadway Curve Project Reaches Halfway Milestone

Tue December 12, 2023 - West Edition #26
ADOT


The project has been broken down into three segments: West segment, Central segment and the East segment. Crews wrapped up the second phase of the project and now the third phase is under way.
(ADOT photo)
The project has been broken down into three segments: West segment, Central segment and the East segment. Crews wrapped up the second phase of the project and now the third phase is under way. (ADOT photo)
The project has been broken down into three segments: West segment, Central segment and the East segment. Crews wrapped up the second phase of the project and now the third phase is under way.
(ADOT photo) ADOT opted to utilize the public-private partnership (P3) statute to procure, design and build this project, which makes it possible to deliver much needed transportation projects in a timely manner, often years before the projects could be delivered using traditional project-delivery methods.
(ADOT photo) Contractors will focus on widening roads and bridges and rebuilding ramps on 32nd Street. Other work includes drainage and bridgework and finishing the Collector-Distributor (CD) roads.
(ADOT photo) Broadway Curve Constructors — a joint venture of Pulice Construction Inc., FNF Construction Inc. and Flatiron Constructors Inc. — are halfway home to completing the $776 million Broadway Curve Project in Phoenix.
(ADOT photo) During the last phase, crews removed and replaced the 48th Street and Broadway Road bridges. They also constructed new walls and began building Collector-Distributor (CD) roads, which are meant to separate through-traffic from entering and exiting vehicles.
(ADOT photo)

Phoenix, America's fifth-largest city, is being transformed by the Broadway Curve project, which is now halfway complete, according to an update from the Arizona Department of Transportation.

The project began in spring 2021 and is expected to be completed in late 2024.

The project developer, Broadway Curve Constructors — a joint venture of Pulice Construction Inc., FNF Construction Inc. and Flatiron Constructors Inc. — has broken down the project into three segments:

  • West segment: East and westbound I-10 from 24th Street to the east of 40th Street and will include the I-10 bridges over the Salt River;
  • Central segment: East and westbound I-10 east of 40th Street and Broadway; and 1 mi. of Route 143 in both directions between I-10 and the Salt River;
  • East segment: East and westbound I-10 between Broadway and Ray roads and including 1 mi. of U.S. 60 in both directions between I-10 and Hardy Drive.

This complicated undertaking will cost $776 million.

Crews recently wrapped phase two and now the third phase is beginning.

During the last phase, crews removed and replaced the 48th Street and Broadway Road bridges. They also constructed new walls and began building Collector-Distributor (CD) roads, which are meant to separate through-traffic from entering and exiting vehicles.

ADOT estimates the third phase to last through late summer 2024.

From now until then, crews will widen roads and bridges and rebuild ramps on 32nd Street. Other work includes drainage and bridgework and finishing the CD roads.

"This project is our largest urban freeway reconstruction project to date," said Marcy McMacken, spokesperson of the Arizona Department of Transportation (ADOT).

This project also will prepare the region for future growth projections, which indicate a 25 percent increase in traffic through the Broadway Curve area by 2040. Currently, more than 300,000 vehicles pass through the Broadway Curve area on an average weekday.

ADOT opted to utilize the public-private partnership (P3) statute to procure, design and build this project. A public-private partnership design-build makes it possible to deliver much needed transportation projects in a timely manner, often years before the projects could be delivered using traditional project-delivery methods.

"Opening the new eastbound travel lanes early in the life of this massive project provided tremendous value to thousands of motorists," said ADOT Director John Halikowski. "We are delighted we could make it happen and improve the afternoon and evening commute home for so many of our customers in Guadalupe, Tempe, Chandler and other areas of the Southeast Valley. We know this project is influential in other areas of I-10, the U.S. 60 and State Route 143. Opening up new travel lanes is one way we're striving to reduce the project's impacts for at least some motorists in the project area."

McMacken also sees a big impact to travelers in the Broadway Curve and throughout Phoenix.

"Once completed, motorists will notice reduced travel time during peak hours and improved access to and from Phoenix Sky Harbor International Airport," McMacken said. "They also will have improved access to the over 4,600 businesses within the project area, improved safety by reducing lane changes and ‘weaving' on Interstate 10 in the Broadway Curve area and on State Route 143 at University Drive."

Challenges

"In May, the team needed to close I-10 in both directions and detour motorists to westbound U.S. 60," McMacken said. "However, a water main broke under U.S. 60, creating extensive flooding and damaging the U.S. 60 road surface. U.S. 60 was closed for repairs for several days. Without a viable detour available, crews again pivoted and rescheduled work, exhibiting the ability to modify their construction work plans."

ADOT is using new outreach tools, in addition to the traditional methods, to create awareness about this massive project.

"We launched ADOT's first project-specific, bilingual paid advertising campaign in the summer of 2021," said McMacken. "The campaign includes billboards as well as TV, radio, online, social media and paid search. Also, visitors who pass through Phoenix Sky Harbor International Airport will see project-related ads, so they are aware of the project construction taking place around the airport, which is in the heart of the busiest section of the project."

Green Construction

Planners and workers have given special emphasis to environmental responsibility. Recycling used construction materials has been made a priority.

"We reuse as much as we can, so nothing goes to waste," Kole Dea, senior resident engineer of the Broadway Curve Project, said. "If something can't go back into the project, then it's recycled."

Some 1.3 million sq. yds. of millings are being used as the base layer for temporary haul roads in the project area. Millings provide a strong base for trucks and equipment to drive on and they help reduce dust.

Throughout the project, walls and other concrete structures are being taken down and reduced to pieces no larger than 24 in. Once broken down to the appropriate size, the concrete is used as fill to build up approaches for new bridges, fill up holes or help support unstable materials throughout the project area. The contractor sends unused metal and steel to a recycling factory.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\