List Your Equipment For Free  /  Seller Login

Building Golden Gate Bridge Safety Net Will Cost $400M

Wed January 11, 2023 - West Edition #2
Associated Press


SAN FRANCISCO (AP) A prevention net on San Francisco's Golden Gate Bridge that is already years behind schedule will cost about $400 million, more than double its original price, because of problems sparked by the government agency that manages the span, the lead contractors allege.

The allegations filed in state court by two construction companies said that changes to and flaws in the net design and the lack of transparency about the deterioration of the bridge's maintenance platforms have raised the construction price from $142 million to at least $398 million.

"We were alarmed to discover the district concealed significant information during the proposal phase of the project, including extensive deterioration in certain areas of the bridge," the contractor said in a statement.

The project aims to add 20-ft.-wide stainless steel mesh nets on both sides of the 1.7-mi. bridge and replace maintenance platforms used by bridge workers that were built in the 1950s. Work on the net began in 2018 and was set to be completed by January 2021 but has been repeatedly delayed.

Bridge officials in 2008 voted to move forward with the net, meant to deter those looking to jump to their deaths and catch those who do. Paul Muller, president of the Bridge Rail Foundation, a nonprofit created to end suicides on the bridge, said the span with sweeping views of the Pacific Ocean and San Francisco bay has been the site of nearly 2,000 suicides since it opened in 1937, including 25 last year alone.

According to the joint venture, the deterioration is mainly in the maintenance platforms — U-shaped structures known as travelers that are powered by diesel engines and hug the bridge on both sides and bottom to give workers access to the bridge's underside and hard-to-reach areas.

The alleged problem with the platforms remains unclear because the information was redacted from the court documents. A spokesperson for Shimmick said that was done for security reasons and that it will be up to the judge to make the information public.

The joint venture has completed approximately 47 percent of the net and expects to finish it by December 2023, nearly four years behind schedule. Adding the net requires the maintenance platforms to be reconfigured. The upgraded platforms are not expected to be completed until January 2026.

The contractors claim bridge officials also changed the design of the net when the project was already underway and imposed unnecessary requirements on the contractors that drove costs higher and caused delays. They cited a scaffolding standard not required by the California Occupational Safety and Health Standards Board and said the district failed to obtain a waiver until this February for the federal requirement to buy the steel needed in the U.S.

"Rather than acknowledge its own mistakes, the district seeks to hold SDJV hostage and have it complete the work with no adjustment in price," the contractors said in court documents. "In other words, the district wants to pay only $142 million for a project that will cost well over $398 million because of the district's mistakes."

Suicide prevention advocates said they are frustrated by the delays because they are costing lives.

Muller said that even though part of the net has been built, suicides are happening at the usual rate of about two or three per month.

"This has been a life-and-death matter for 85 years," Muller said.




Today's top stories

Pacific Coast Highway Drainage Infrastructure, Bridge Construction Proceed

Explore St. Louis: Gateway to Experiences at World of Asphalt 2025

AUSA Unveils Its Next-Generation of Compact Dumpers

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

HIPOWER HS Stationary Product Line

Appalachian State University in Boone, N.C., to Build $29M Indoor Athletic Practice Facility

Tennessee DOT Wants $308M in Funding to Deal With Backlog of Projects Amid Flat Revenues


 







\\ \\ \\