List Your Equipment For Free  /  Seller Login

Chicago's $2.1B Chicago Transit Authority Modernization Well Under Way

Wed February 19, 2020 - Midwest Edition #4
Lori Tobias – CEG Correspondent


The Red-Purple Modernization Program will modernize train service on a 9.6-mi. stretch of track by replacing old rails, adding an overhead bypass and rebuilding four stations on the line.
The Red-Purple Modernization Program will modernize train service on a 9.6-mi. stretch of track by replacing old rails, adding an overhead bypass and rebuilding four stations on the line.
The Red-Purple Modernization Program will modernize train service on a 9.6-mi. stretch of track by replacing old rails, adding an overhead bypass and rebuilding four stations on the line.
 Construction crews drilled the first shafts last fall for the $1.2-billion phase one of the Chicago Transit Authority’s $2.1-billion Red-Purple Modernization Program.
 Equipment on site includes a Bauer BG 39 drill rig; a Liebherr LTR 1220, 220-ton telecrawler crane; a Grove RT 765 rough-terrain crane; a Caterpillar 938 loader; and a Caterpillar 308 mini-excavator. The Chicago Transit Authority’s $2.1-billion Red-Purple Modernization Program, the largest capital improvement project in the agency’s history. “The big cranes are used to install the casing and rebar in the shafts,” said Don Henry, construction manager of the Walsh-Fluor Design-Build Team. The shafts recently drilled are for the foundations of the flyover portion of the bridge that will take new track for the Brown line over the existing four tracks. “We started in October about the time we wanted to,” said Don Henry, construction manager of the Walsh-Fluor Design-Build Team. “In April or May we’ll start erecting the structural steel. For the next six months to a year we’ll be building the foundation, superstructure, substructure and tracks,” said Don Henry, construction manager of the Walsh-Fluor Design-Build Team. The track was originally built in 1924 under President Calvin Coolidge and during the era when the Wrigley Building had just been completed.

Construction crews drilled the first shafts last fall for the $1.2 billion phase one of the Chicago Transit Authority's $2.1 billion Red-Purple Modernization Program, the largest capital improvement project in the agency's history. The program will modernize train service on a 9.6-mi. stretch of track by replacing old rails, adding an overhead bypass and rebuilding four stations on the line. The track was originally built in 1924 under President Calvin Coolidge and during the era when the Wrigley Building had just been completed.

"The Red-Purple Bypass Project is a critical part of RPM Phase One that will ensure we can deliver quality, reliable and comfortable rail service to our customers," the CTA said in a project overview. "It benefits riders on the Red Line, our busiest rail line with more than 125,000 riders a day, and other rail lines by addressing chronic overcrowding and delays and modernizing infrastructure that is more than a century old. The Red-Purple Bypass to be built north of Belmont, and reconstruction of Red and Purple Line tracks just to the north of the bypass, will allow us to add trains during our busiest periods while providing a ride that is smoother and more reliable."

The shafts drilled are for the foundations of the flyover portion of the bridge that will take new track for the Brown Line over the existing four tracks. In its current configuration, the Brown Lines intersect with Red and Purple Lines, causing delays when one line is stopped to allow another to pass. The project also will allow CTA to add more trains.

"We started in October about the time we wanted to," said Don Henry, construction manager of the Walsh-Fluor Design-Build Team. "We can drill in the winter, and then we might pour some concrete if the weather cooperates. We will continue the drilled shafts for this stage and after those are poured we will start the substructure of the bypass. That consists of the columns and caps. We will have those complete in March or April. In April or May we'll start erecting the structural steel. For the next six months to a year we'll be building the foundation, superstructure, substructure and tracks. The flyover itself will be put into use in June 2021. Then we've got the existing mainline. We'll demolish the four tracks and rebuild it all. We'll start that June 2021 and we will finish that somewhere around first quarter of 2024."

Equipment on site includes:
  • Bauer BG 39 drill rig
  • Liebherr LTR 1220, 220-ton telecrawler crane
  • Grove RT 765 rough-terrain crane
  • Caterpillar 938 loader
  • Caterpillar 308 mini-excavator

"The big cranes are used to install the casing and rebar in the shafts," Henry said. "The real challenges on the job are the logistics. The footprint is very condensed. There is not a lot of room to store material or for cranes to move around. Also, our windows for working are a little short. The only time the boom can be in the air is 9 a.m. to 3 p.m. Also, our flagging requirements are limited. They don't want any flaggers slowing traffic during rush hour."

The project also will see the Lawrence, Argyle, Berwyn and Bryn Mawr stations completely rebuilt.

"While CTA has made some improvements to these stations in recent years, the main support structures for all four stations were built in the early 1900s," according to the CTA. "All have very narrow station platforms that prevent CTA from adding critical upgrades like elevators. These stations will be completely torn down and rebuilt from the ground up. This will allow CTA to expand and modernize the stations and ensure they are full ADA accessible to customers with disabilities."

Additional amenities at the stations will include:
  • Wider platforms for faster boarding and less crowding;
  • better lighting and customer security features;
  • longer canopies, more benches, and wind screens; and
  • real-time information boards. CEG

Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







\\ \\ \\