List Your Equipment For Free  /  Seller Login

Critical Safety Improvements Part of Bridge Rehabilitation

Derailing trains have hit the bridge four times in the past two years.

Mon May 01, 2017 - West Edition #9
Chuck Harvey


Oklahoma Department of Transportation photo. Pier protection will be part of a nearly $20 million bridge rehabilitation project now under way on the 23rd St. bridge over I-244 in Tulsa, Okla.
Oklahoma Department of Transportation photo. Pier protection will be part of a nearly $20 million bridge rehabilitation project now under way on the 23rd St. bridge over I-244 in Tulsa, Okla.
Oklahoma Department of Transportation photo. Pier protection will be part of a nearly $20 million bridge rehabilitation project now under way on the 23rd St. bridge over I-244 in Tulsa, Okla.   Oklahoma Department of Transportation. Work on the new bridge began in May 2016, with traffic continuing to use the bridge in the narrowed configuration. Oklahoma Department of Transportation photo.  Workers will replace the bridge deck, erect crash walls for each pier, improve the substructure and make critical safety improvements. Oklahoma Department of Transportation photo. Built in 1962, the worn bridge became classified as structurally deficient.

Pier protection will be part of a nearly $20 million bridge rehabilitation project now under way on the 23rd St. bridge over I-244 in Tulsa, Okla.

The work will impact traffic on the 23rd St. bridge until early 2018 and drivers are advised to plan ahead to adjust for slowing. The road on the bridge has been narrowed from two lanes to one as improvements continue.

The 1,000-ft. bridge crosses over both I-244 and an adjacent rail yard. Derailing trains have hit the bridge four times in the past two years. The trains damaged three piers, which were repaired.

Workers will replace the bridge deck, erect crash walls for each pier, improve the substructure and make critical safety improvements.

"The length of the pier protection depends on the length of the pier being protected," said Mark Zishka, construction engineer for Oklahoma Department of Transportation Division 8. "They range from 25 feet to 90 feet in length."

Piers Reconfigured

The project includes reconfiguring piers not only for safety, but also to help the railroad expand operations below the bridge.

Current work includes replacing the bridge deck; repair and painting of the beams; substructure repair; adding pier protection to piers in the rail yard; and replacing spans, beams and piers for rail yard expansion.

Heavy equipment on site includes cranes; backhoes; hydraulic hammers; cement trucks; pavement compactors, rollers and sealers; dump trucks and delivery trucks.

In terms of materials, asphalt for the project is minimal at about 700 tons (635 t). Crews will apply 1,500 cu. yds. (1,147 cu m) for pavement and about 3,900 cu. yds. (2,982 cu m) for the bridge.

Concrete and reinforcing will be used in the bridge deck and piers being replaced. Both steel and lumber forms will be used to construct the new piers and bridge deck.

All steel removed from the project becomes the property of the contractor. The steel may then be recycled or repurposed.

Contractor is Becco Contractors Inc. of Tulsa. It placed the low bid for the project and was approved by the Oklahoma Transportation Commission.

Tetra Tech of Pasadena, Calif. is overseeing the daily construction.

The project has nine subcontractors including Logos Construction Co. of Sapulpa, Okla., for structural repair and Action Safety Supply of Oklahoma City for traffic control. Both Logos Construction and Becco Contractors specialize in bridge construction.

Between 10 and 15 workers are on the job each day.

Existing Bridge Was Structurally Deficient

Built in 1962, the worn bridge became classified as structurally deficient. It has also seen an increase in traffic. The bridge traffic averages about 15,800 vehicles daily.

Work on the new bridge began in May 2016, with traffic continuing to use the bridge in the narrowed configuration. Slower movement of traffic is expected to impact the nearby area during construction, but traffic is not seen as a serious problem at this point.

Numerous businesses and industries depend on the bridge for access. As do students and staff at nearby Eugene Field Elementary School.

"This is one of the few city streets connecting this area to the interstate," Zishka said.

"The bridge is open to traffic, so it is likely near the usual traffic counts at this time. There is no mitigation to other city street traffic."

No Detour Necessary

Because one lane on the bridge remains open, no detour is needed for the 23rd Street crossing. But a detour is currently in place for a closed westbound I-244 off-ramp to 23rd Street.

"Drivers can use either the 17th Street ramp or use I-244 to 57th West Avenue," Zishka said.

He said one of the main challenges of the project has been working over the active BNSF (Burlington Northern Santa Fe) rail yard at the same time rail construction crews are working on a project to expand the rail yard. The rail project is not connected with the bridge project, but requires coordination and planning between the two jobs.

"There are meetings weekly to plan and work out issues," Zishka said.

He added that coordinating the two projects has not slowed progress or added additional costs to the bridge project.

Additional Retaining Wall

A separate $1.7 million project began in May to construct a retaining wall along the adjacent rail yard in the corridor, which also is impacting traffic on westbound I-244.

Drivers can expect delays throughout these projects, especially during peak travel times and should plan ahead for extra travel time or consider an alternate route if possible.

Lane closures will be announced in the Traffic Advisories section of www.odot.org as they are scheduled throughout the project.—CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







39.96118 \\ -82.99879 \\ Columbus \\ OH