List Your Equipment For Free  /  Seller Login

CTDOT's $34.8M Bridgeport Route 8/25 Project Reaches Important Milestone

The Connecticut Department of Transportation's (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point.

Wed February 24, 2016 - Northeast Edition
Irwin Rapoport


Manafort Brothers Incorporated photo.
The Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working ha
Manafort Brothers Incorporated photo. The Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working ha
Manafort Brothers Incorporated photo.
The Connecticut Department of Transportation’s (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working ha Manafort Brothers Incorporated photo.
The four bridges being rehabilitated carry an average of 88,000 cars over Capital Avenue, Lindley Street and a large parking lot.
 Manafort Brothers Incorporated photo.
The bridges will be demolished and rebuilt in a different configuration using accelerated bridge construction techniques. 
 Manafort Brothers Incorporated photo.
The Lindley Street Bridges will be reduced to two spans each by filling in five of the seven spans on each bridge. Manafort Brothers Incorporated photo. CTDOT noted that work will continue on the construction of PBUs in the construction area along Route 8 NB at Exit 5 and that in early summer, these PBUs will be transported to the Lindley Street and Capital Avenue sit

The Connecticut Department of Transportation's (CTDOT) $34.8 million project to replace the Route 8/25 bridges in Bridgeport has exceeded the half-way point as crews from Manafort Brothers Incorporated are working hard to meet the September delivery date.

The four bridges being rehabilitated carry an average of 88,000 cars over Capital Avenue, Lindley Street and a large parking lot. The Lindley Street Bridge consists of seven, 82 ft. (25 m) long spans with four 12-ft. (3.6 m) lanes and two shoulders in each direction. The project will reduce the bridge to two spans while keeping the same lane and shoulder capacity.

The Capital Avenue Bridge, consisting of a single span with four 12-ft. lanes and two shoulders in each direction will be replaced with a similar structure. The work also includes the construction of a large retaining wall to support 425 ft. (130 m) of new highway, the rehabilitation of the metal bin-wall retaining wall which is currently supporting Route 8 southbound, south of Capital Avenue and capacity improvements to two intersections on Lindley Street adjacent to Route 8 northbound.

The bridges will be demolished and rebuilt in a different configuration using accelerated bridge construction techniques. The new superstructures will consist of prefabricated bridge units (PBUs), which consists of two steel beams fabricated with an integral concrete deck to form a double tee section. The PBUs will be connected in the field with narrow longitudinal closure pours.

The Lindley Street Bridges will be reduced to two spans each by filling in five of the seven spans on each bridge. The pier to the north of the second span will be converted to an abutment by constructing a retaining wall behind the existing pier. The substructures to the north of the final two span structures will be left in place and buried. The area under the spans to be removed will be filled. The fill will be retained by concrete retaining walls built outboard of the existing bridge limits.

Federal highway funds cover 85 percent of the cost, with the remaining 15 percent from the state. The existing bridges, nearly 2 mi. (3.2 km) north of Interstate 95, were built in 1973 and according to CTDOT, have reached the “excessive deterioration” point and cannot be repaired.

“The bridges are part of CTDOT's bridge program which prioritizes work based on a continuous assessment of the remaining useful life of bridges and their need to be replaced or rehabilitated,” stated the project Web site. “CTDOT has determined that the bridges involved are reaching the end of their useful life and warrant rehabilitation.”

“The existing precast concrete beams supporting the roadway are experiencing what is called an Alkali-Silica Reaction, where, due to a chemical reaction within the concrete, the concrete literally self-destructs,” said Scott Adkins, project engineer of CTDOT. “While the bridges are currently structurally safe, there is no way to repair the beams, and therefore the entire superstructure must be replaced. In the 1970s, ASR was a common problem. Fortunately, advances in concrete construction have significantly reduced the occurrence of ASR.

“Lane closure and stage construction periods that would impact the travel lanes on Route 8/25 have been reduced from two years to two periods of approximately 14 days each,” said Adkins. “The ability to reduce the impact on the traveling public is very important to the department and played a central role in the design of the project and is part of the ‘get in and get out' policy put forward by CTDOT.”

Commenting on additional construction methods, which will reduce the long-term maintenance costs, Adkins said, “The new bridges, which have been designed to have a lifespan of nearly 75 years, are being built with what is referred to as ‘weathering steel' beams. Weathering steel has been used for more than 50 years and is a great alternative, as it does not require painting. In addition, five of the seven Lindley Street spans will be eliminated. The anticipated maintenance savings during the lifetime of the bridge is in excess of a million dollars.”

According to the Web site, “When the Lindley Street Bridge was built, the land adjacent to the Lindley Street Bridge was a parking lot for the Bridgeport Machine Company. Closure of the parking lot would have left the site with virtually no parking. The state decided at that time to build over the parking lot instead of displacing the company that was a significant part of the Bridgeport industrial community. Unfortunately the company no longer exists on the site so the state was able to work to secure the land beneath the bridge to allow the elimination of the spans.”

The bridges were designed by WSP/Parsons Brinckerhoff.

“The biggest challenge during the design of the project was finding a way to reduce the impact to the traveling public,” said Adkins. “We knew that a project that did not employ accelerated bridge construction methods would create long term impacts on the public. A great example of the success of ABC is the I-84 bridge replacement project in Southington, where the contactor replaced the superstructures over the course of a weekend.”

The construction schedule is based on two phases — two bridges per-phase. During two short term construction windows, one side of Route 8/25 will be closed for approximately two weeks. Traffic will be detoured across the median to the opposite side of the highway. Opposing traffic will be separated by concrete barriers for safety. There will be minor closures of Lindley Street and Capital Avenue during these periods to allow for the rapid construction. Minor local road detours will be used to accommodate local traffic.

The footprint of Route 8/25 will remain unchanged in the final configuration of the new highway infrastructure.

“The expressway has ample room for current traffic and future traffic increases,” stated the Web page. “There are also no safety concerns with the current alignment of the roadways, so re-alignments are not required. Minor changes are proposed for the northbound exit ramp at Lindley Street. An additional lane will be added to the end of the ramp to make more room for turning vehicles onto Lindley Street. The intersection at the Lindley Street ramp will be upgraded along with the intersection of Lindley Street and Route 1 (North Avenue).”

CTDOT noted that work will continue on the construction of PBUs in the construction area along Route 8 NB at Exit 5 and that in early summer, these PBUs will be transported to the Lindley Street and Capital Avenue sites to be set in place once the existing structures have been removed.

Justin Gill, Manafort's heavy highway department manager, takes nothing for granted in terms of working conditions.

“With last winter still fresh in our minds,” he said, “we planned for the additional effort required to place PBU concrete during the cold weather months. Fortunately, the reality was unseasonably warm weather for late fall and early winter. This allowed us to place most of the concrete in quite favorable temps. All of the PBU concrete was placed prior to the first large snow storm of the season.”

This also is CTDOT's first design-build project and Gill is confident that Manafort has a thorough knowledge of the work, especially the upcoming bridge reconstruction.

“Construction of each stage will be limited to 14 consecutive calendar days for each stage,” he said. “During each 14-day period, one side of the expressway will be completed, including construction of two bridges and the final filling of the spans under the Lindley Street Bridge.

“Offline improvements consist of rehabilitation of an approximately 600 foot long metal bin retaining wall and intersection improvements in the vicinity of the Lindley Street Route 8 northbound exit ramp,” he added. “This metal bin retaining wall will be rehabilitated with precast concrete panels and soil nails extending under Route 8 southbound. The intersection work involves the widening of Lindley Street and the Route 8/25 northbound exit ramp at Lindley Street and replacement of the traffic control signal. This work also includes operational improvements at the North Avenue and Lindley Street intersection to the east. Offline work shall be completed prior to the construction of the Route 8/25 bridges in order to facilitate maintenance of traffic.”

The final construction stage involves a full width of asphalt overlay for the entire length of the project — approximately 1,600 ft. (487.68 m).

The work will see the removal of 15,000 cu. yds. (11,468 cu m) of excavation; 60,000 cu. yds. (45,873 cu m) of material fill, structural backfill and road base; and 4,000 cu. yds. (3,058 cu m) of light-weight fill. This is bolstered by 6,000 cu. yds. (4,587 cu m) of structural concrete, 950,000 lbs. (430,912 kg) of rebar, 150,000 lbs. (68,039 kg) of miscellaneous metals, 1 million lbs. (453,592 kg) of structural steel and 14,000 tons (12,700 t) of asphalt.

On a daily basis there are between 35 to 45 people on site doing regular extended shifts and second shifts, and with two-week closure period this summer, crews will be working round-the-clock. The key subcontractors are Hartland Building and Restoration; Santoro, Inc.; A&J Paving; Ducci Electrical Contractors; and Underground Builders.

Equipment being used includes Volvo 360, Volvo 480, JD 450, JD 750 excavators with demolition attachments; Cat D4, Cat D6, JD 550 bulldozers; Schwing 42M, Schwing 32M concrete pump trucks; Grove RT600 hydraulic cranes; and earth moving equipment such as Bobcat 550 skid steers and Ingersoll Rand SD50 and SD100 small rollers that were required to place fill under the existing bridge structures.

Manafort will rent self-propelled modular transporters (SPMTs) to move the PBUs on site. These machines will be rented from Marino Crane of Middletown, Mass. Large hydraulic cranes will be rented to hoist and set the heavy PBU sections. For these picks Manafort also will rent the cranes from Marino Crane.

Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.96118 \\ -82.99879 \\ Columbus \\ OH