List Your Equipment For Free  /  Seller Login

El Centro's Imperial Improvement

Tue August 25, 2020 - West Edition #18
Irwin Rapoport – CEG Correspondent


Two Volvo EC480E excavators, a Cat 345B excavator and a Link-Belt 470X excavator – with 1,100 FTP breakers – perform demo work on the $44 million Interstate 8/Imperial Avenue 
Interchange project.
Two Volvo EC480E excavators, a Cat 345B excavator and a Link-Belt 470X excavator – with 1,100 FTP breakers – perform demo work on the $44 million Interstate 8/Imperial Avenue Interchange project.
Two Volvo EC480E excavators, a Cat 345B excavator and a Link-Belt 470X excavator – with 1,100 FTP breakers – perform demo work on the $44 million Interstate 8/Imperial Avenue 
Interchange project. Looking southbound as the crew begin to demolish the existing bridge structure. Aerial view looking west at the SW quadrant of the project during construction of the EB I-8 off and on ramps at Imperial Ave. Belly dump trucks delivering imported borrow material while a water pull waters the material and a Cat 824G tractor spreads and compacts. The demolition and excavation operations should generate approximately 600 cu. yds. of concrete and 80,000 cu. yds. of native fill material that will be incorporated into the project. 
 New materials are expected to include approximately 238,000 cu. yds. of imported borrow, 4,600 cu. yds. of concrete, 27,000 cu. yds. of aggregate base, 14,000 tons of asphalt and 65,000 lbs. of rebar. 
 Cat 637E scrapers excavate soil from the existing EB on ramp and spread the material on the new EB I-8 on and off ramps, while an 824G tractor spreads and compacts. A water pull and water truck spreads water and a?Cat 143M spreads material.

Granite Construction Inc. is continuing to make progress on the California Department of Transportation's (Caltrans) $44 million, multi-year project to reconstruct the interchange at Imperial Avenue and Interstate 8 (I-8) in the city of El Centro.

The initiative will remove the existing bridge and eastbound on- and off-ramps, then reconstruct the structure and the on- and off-ramps in both directions, construct a new entrance loop ramp from southbound Imperial Avenue to eastbound I-8 and create access to the city's upcoming extension of southbound Imperial Avenue to city areas south of I-8.

The state's Regional Improvement Program is providing $42 million of the cost, with $2 million from the Federal Highway Priority Projects Program.

The project was designed internally by the Caltrans Division of Design in coordination with Project Engineer Dimitar Peev, Design Manager Kazim Mamdani and Edward Mercado (structures division).

Project Progress

On July 6, the eastbound I-8 on and off-ramps at Imperial Avenue were closed for eight-to-10 months for Stage 1 construction as crews worked on the southern portion of the intersection. The traffic plan is based on lane closures (day and night) and detours.

Stage 2 work on the northern portion is anticipated to take four-to-six months to complete and could begin as early as December. During this stage, all I-8/Imperial Avenue on- and off-ramps will be fully closed.

The project will be executed in two phases. The first phase will demolish the existing bridge and construct the new Imperial Avenue Bridge. This phase will include all the work involved on the south side of I-8 and a portion of the north side. This phase began in May and is scheduled to be completed by October of 2021.

The second phase will remove the westbound on/off ramps and is scheduled to begin in January 2021. The entire construction project is scheduled to be completed in October 2021.

During the course of the project, the I-8 freeway will be subjected to full freeway closures. The bridge removal closure has already occurred, but the second full freeway closure is scheduled for January 2021 to install false work for the new bridge. The last closure is set to take place June 2021 to remove falsework.

Crews will install approximately 5,400 linear ft. of a new storm drain system. The first phase will be installed in November 2020 and phase two will be installed in April 2021.

"We anticipate one or two nights for each closure totaling up to five full freeway closures," said Fausto Gonzalez, Granite's project manager. "Additionally, single lane closures will be needed to perform other miscellaneous work such as k-rail installation, freeway striping and bridge column/abutment removals. This work will be scheduled for night operations."

Construction of the new bridge and ramps will begin soon, with a completion goal of October 2021.

"This project was planned in a way that will minimize public inconvenience and still provide us the ability to complete the project on time," said Gonzalez. "The first phase required the closure of the on/off ramps east bound. That allowed us to build the majority of the project, except for the westbound on/off ramps. Starting in January 2021, phase two will overlap with phase one. At this point, all ramps on Imperial Avenue will be closed for the construction of the bridge, including all connectors.

"In order to expedite the project, Granite will be working on different operations simultaneously," said Gonzalez. "This will help us complete the project on time. Our personnel are specialized in this type of work with the support of other subs who are specialized in their respective construction disciplines."

Partnering to Get the Job Done

"We are fortunate to have a team with a strong mindset on partnering," said Gonzalez. "This has allowed the team to come together and work towards a shared goal. I'm confident that together we will overcome any issues and great results will be achieved."

Peak days will have more than 20 Granite and subcontractor employees, with the major subcontractors from ACL Construction for concrete barrier; Alcorn Fence Company for metal beam guardrail; Harbor Companies for bridge removal; Integrity Rebar for rebar; Jilk Heavy Construction for pile driving; Maneri Traffic Control for construction area signs; Mendoza Business Enterprise for electrical; Pacific Restoration of erosion control; Payco Specialties for striping; Statewide Traffic Safety for signage; and Universal Construction Engineering for landscaping.

The demolition and excavation operations should generate approximately 600 cu. yds. of concrete, 80,000 cu. yds. of native fill material that will be incorporated into the project.

"Granite has always been very environmentally oriented and this project will not be the exception," said Gonzalez. "We will recycle and incorporate into the project all allowable materials generated from the demolitions and roadway excavation."

New materials are expected to include approximately 238,000 cu. yds. of imported borrow, 4,600 cu. yds. of concrete, 27,000 cu. yds. of aggregate base, 14,000 tons of asphalt and 65,000 lbs. of rebar.

"Due to the nature of the project, this project will be equipment intense," said Gonzalez. "Consequently, our ability to complete this project on time will highly depend on our equipment and its ability to run every day. For this reason, we inspect and maintain all equipment prior to the start of shifts to ensure that it's in its best working condition."

Granite is utilizing a Cat 637 scraper to transport loads to the fill area, as well as Cat 824G tractors and Cat 143M road graders equipped with GPS to complete the job.

Granite rents equipment from dealerships such as Elms Equipment Rental and ACME Safety Supply in El Centro, Imperial Valley Aggregate in Ocotillo, Gibson and Schaefer in Heber, and Contera Construction Corporation.

"The local dealerships have been a crucial component for the development of the project," said Gonzalez. "Their commitment and ability to adapt to our needs has been very positive. As a result, we have been able to stay on schedule."

Engineering Challenges

"Some of the design and engineering challenges was the staging of the project in order to minimize the traffic impact of the area," said Daniel Hernandez-Duarte, Caltrans resident engineer. "In order to reduce the construction time and associated traffic congestion, Design proposed to El Centro to close the whole interchange. District 11 Design, El Centro, the county of El Centro and Imperial Irrigation District worked together to reach an agreement to reduce impacts to the public. The life expectancy of the project is governed from the structures. For bridges and retaining walls, that life is 75 years, however in many cases with proper maintenance, we see a much longer time."

Caltrans District Director Gustavo Dallarda emphasized the need for motorists to watch out for and slowing down for construction workers, and to avoid the work zone when possible.

"Their safety is paramount," he said.

Noisy construction work is being scheduled during the day as much as possible, with three months of pile driving expected. Nighttime bridge demolition also will be noisy, but it is only expected to occur one or two nights at a time on a few occasions.

"We work very hard with our contractor to reduce that [noise and dust] to a minimum," said Dallarda.

"The safety of our employees and the public has always been Granite's number one priority," said Gonzalez. "For this reason, Granite, in conjunction with Caltrans, developed a new construction exit on a less traveled road for our trucks and construction equipment, thus providing a safer construction zone. To put it into perspective, this project requires approximately 228,000 cubic yards of imported borrow, which equates to approximately 15,000 truckloads in a lapse of 55 days.

"This means that on average, a truck will merge onto live traffic on the I-8 approximately every two minutes," he added. "From a safety stand point, we saw the need to change the original plan and come up with a solution that could improve safety. To achieve this goal, we had to get the support from the city, Imperial County and other private property owners since the new route required the use of their right-of-way."

Minimizing public inconvenience is a given for Granite, be it large or small projects.

"We constantly plan operations to reduce the number of freeway and lane closures," said Gonzalez. "The majority of the operations will be performed during daytime working hours, except for operations that will require traffic lane closures. Planned nighttime work includes the bridge removal, along with setting up and removing falsework required for bridge construction . As of today, we have not encountered issues that could delay or impede the ability to construct the project. Fortunately, our relationship with Caltrans has been very good and I'm confident that together we will overcome any future issues.

"With the COVID-19 pandemic, keeping our employees safe and healthy has been a constant challenge," he added. "Granite has always been proactive in protecting our people. For this reason, we have implemented additional protective measurements such as social distancing, face mask requirements, using radios to communicate and minimize proximity with other co-workers, and disinfecting equipment/tools that could potentially spread the virus."

Earth work operations began in May and they should be finished in January 2021.

Bridge demolition took place overnight on July 22 during a 12.5- hour full closure of the interchange and main lanes on I-8.

Highway Impact

"Traffic within the project limits is approximately 16,000 to 27,000 vehicles per-day, primarily associated with the growth in international trade and travel between the United States and Mexico, as well as travel onto and from Imperial Avenue from north of Interstate 8," said Cathryne Bruce-Johnson, Caltrans public information officer. "In the next five years, traffic is expected to double. This project will aid in keeping vehicles moving from the international border along State Route 111 to destinations across the states."

The interchange is expected to open to traffic in late 2022, with final delivery in mid-2023.

"Every day, 31,000 motorists and commercial trucks travel through the Imperial Avenue Interchange and this project is key to maintaining the Imperial Valley's economic vitality," said David S. Kim, secretary of California State Transportation Agency.

"It supports economic growth," said Caltrans Director Toks Omishakin. "That means more local jobs. Once it's finished, it will eliminate the need for local motorists and commercial trucks to travel out of their way onto city streets and county roads."

Caltrans is providing real-time traffic information via http://quickmap.dot.ca.gov/, @SDCaltrans on Twitter, and at www.facebook.com/CaltransDistrict11. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.96118 \\ -82.99879 \\ Columbus \\ OH