Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
An improvement project currently under way in the town of Culpeper, Va., will improve Route 229 (North Main Street) from two to four lanes.
Tue August 09, 2016 - Northeast Edition
An improvement project currently under way in the town of Culpeper, Va., will improve Route 229 (North Main Street) from two to four lanes.
Construction began on Jan. 11, 2016, and the project is currently on schedule for a completion date of Aug. 2, 2017.
The full project cost is $14.1 million, broken out as follows: $3.1 million preliminary engineering; $2.5 million right of way acquisition and utility relocation; and $8.5 million construction. The value of the construction contract is $6.65 million. The remainder of the construction funds are reportedly budgeted on inspection services, materials testing for concrete and asphalt quality, engineering fees and contingencies.
Funding is 80 percent federal funds; 18 percent state; and 2 percent local.
The prime contractor is Fielder's Choice Enterprises Inc. of Charlottesville, Va. Will Ashwell is the project manager, and Wade Shifflett is the project superintendent.
The project will widen a 0.8-mi. (1.3 km) segment of Route 229 from two to four lanes, with left- and right-turn lanes where warranted. It involves grading, storm sewer pipe installation, paving and construction of sidewalks and a 10 ft. (3 m) wide shared-use path, as well as replacement of traffic signals and an emergency actuator signal near the county rescue squad building.
Several challenges were noted by Stacy Londrey, communications manager of VDOT's Culpeper District.
“The project is being built in a tight urban-like area, which requires extra attention to detail like curb and gutter, bicycle/pedestrian access, a storm sewer system and maintenance of traffic through a tight work zone,” he said. “With two schools in very close proximity, we also have to accommodate the increase in traffic during drop-off and pickup times, as well as confine most work to times when construction noise will not affect the residents living along this route.”
Londrey noted that the project will complete the widening of Route 229 between the Culpeper downtown area and its northern terminus, and will greatly improve mobility for commuters who travel north to Warrenton and other parts of northern Virginia.
“In terms of construction, the relocation of utilities — including several deep sanitary sewer lines — has been extensive,” he said. “Since the work is occurring in the front yards of 48 single-family homes along Route 229, maintaining services like water and sewer presents another unique challenge.”
This project originated in 1997 and at that time included the intersection improvement that later became the Route 229 roundabout project, completed in July 2015. The projects were split in 2008 at the request of the town of Culpeper.
The entire project includes 37,415 cu. yds. (28,606 cu m) of earth moved, 5,866 ft. (1,788 m) of storm sewer pipe, and 0.8 mi. of roadway.
Subcontractors include A-Team of Stanley, Va., water-line and sewer-line installation; F.W. Cardozo Concrete of Dale City, Va., concrete entrance and curb and gutter installation; Eastern Clearing of Bealeton, Va., clearing and grubbing; and B&B Signal Company of Manassas, Va., signal installation.
The extensive list of equipment used on the job includes Case, GMC, International and Mack dump trucks; Kobelco, Kubota, Case, John Deere and Caterpillar excavators; a Terex backhoe; a Kawasaki front end loader; John Deere, Case and Takeuchi skid steers; Caterpillar track loaders; and Caterpillar dozers.
Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.
Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.
Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.