Crews will soon begin work to improve mobility and save lives along I-25, one of the most heavily traveled corridors in Colorado. On Aug. 30, Colorado Gov. John Hickenlooper led a groundbreaking ceremony for the I-25 South Gap project, officially kicking off construction on the 18-mi. project between Monument and Castle Rock.
Joining Gov. Hickenlooper and CDOT were representatives from Colorado State Patrol (CSP), the Federal Highway Administration (FHWA), Douglas County, El Paso County, the Pikes Peak Rural Transportation Authority and several elected officials who played major roles in getting the project from the study phase to construction.
“Getting this project to construction would not have been possible without the leadership of many of our elected officials along the corridor at the federal, state and local levels,” Gov. Hickenlooper said. “It's an example of great collaboration that will go a long way in saving lives, reducing congestion and providing reliable travel options.”
The I-25 South Gap is a four-lane section of I-25 connecting Colorado's two largest cities, Denver and Colorado Springs. Over the years, congestion, crashes and delays have grown, along with Colorado's population. Safety along this vital transportation corridor has been a key concern.
“Our trooper family knows too well the hazards of this corridor,” said CSP Chief Col. Matthew Packard. “The I-25 South Gap is a tough place to work. We're thankful to all the partners that came together to accelerate this project for everyone's safety.”
The I-25 South Gap project will:
Throughout the project, drivers can expect:
Road work will begin in early September on the northern portion of the project near Castle Rock. Overnight lane closures will be ongoing along I-25 between Plum Creek Parkway and Sky View Lane as crews begin restriping I-25 and installing concrete barrier to make room for work in the median, where the new Express Lane and inside shoulder will be constructed.
Putting all four lanes of traffic in this new, temporary alignment will occur over several weeks, but drivers could see new traffic patterns along this stretch as soon as Friday, Sept. 7. Traffic will be pushed to the far outside shoulders. Two lanes of traffic will be maintained during daytime hours throughout the duration of construction.
Most of the initial traffic impacts will be focused in the northern section. Still, motorists will see some construction activity corridor-wide where crews are relocating the fiber optic lines east of I-25.
Work in additional areas along the corridor will begin in phases. By summer 2019, the entire 18-mi. stretch will be experiencing active construction. Substantial construction completion is planned for late 2021, with tolling to begin in 2022.