List Your Equipment For Free  /  Seller Login

Honolulu Airport Receives $2.7B Makeover, New Name

The modernization project is expected to be ongoing through 2021.

Wed October 11, 2017 - West Edition #21
Lori Tobias


Construction work continues on several major projects throughout the terminal of the newly-named Daniel K. Inouye International Airport.
(Hawaii Department of Transportation photo)
Construction work continues on several major projects throughout the terminal of the newly-named Daniel K. Inouye International Airport. (Hawaii Department of Transportation photo)
Construction work continues on several major projects throughout the terminal of the newly-named Daniel K. Inouye International Airport.
(Hawaii Department of Transportation photo) Hawaii’s largest and most active airport is undergoing a $2.7 billion modernization project.
(Hawaii Department of Transportation photo) The modernization project is expected to be ongoing through 2021.
(Hawaii Department of Transportation photo) Much of the work on the tall structure is being handled by large cranes.
(Hawaii Department of Transportation photo)

Hawaii's largest and most active airport was recently given a new name — an apt change, perhaps, to go along with the $2.7 billion modernization project that also will undoubtedly give it a new look. The former Honolulu International Airport was rechristened earlier this year the Daniel K. Inouye International Airport as construction work continues on several major projects throughout the terminal.

The project, as described on a website dedicated to the Hawaii Airports Modernization Program, “… consists of a multi-year effort to transform HNL into a distinctive, functional airport, worthy of a first-class visitor destination and to meet the growing needs of residents and visitors alike.”

The major components include a new concourse, terminal and car rental facility.”

“The challenge is we are landlocked,” said Ford Fuchigami, director of transportation for the Hawaii Department of Transportation. “There is no room to do expansion. Everything needs to be sequenced and needs to be sequenced very carefully. We can't afford to shut down gates. We have to do the operation keeping in mind the 18 million passengers a year enplaning and deplaning while doing all these different projects. That's one of our major challenges. The unique thing about the Honolulu airport is we have three different concourses. Diamond Head, on the east; central, which is right in the middle and Eba, located on the west side. Those are three different areas where people flow through and we try to coordinate that so we have equal passenger flow.”

Work is under way on the new $240 million, LEED Silver-certified Mauka Concourse. It will give HNL additional gate capacity during peak hours as well as new gates capable of handling larger widebody aircraft such as the Airbus A-350.

“It will be the first major concourse expansion at Daniel K. Inouye International Airport in almost 20 years,” Fuchigami said.

The Airbus A-350, operated by Nippon (Ana) Airways, also will require the construction of a third loading bridge, which also will mean renovations to existing loading bridges and significant runway work.

According to the website, “The L-shaped concourse will be connected to the Interisland Terminal and will include new aircraft gates, passenger holding rooms, security screening lanes, jet bridges, and public amenities, such as concessions, restrooms, and information kiosks.

The new concourse will provide six new gatehouses, each with two passenger loading bridges, with an overall capability of accommodating six widebody aircraft parking positions or 11 narrowbody aircraft parking positions.”

Also, currently under construction and about 10 percent complete is the $340 million LEED Silver-certified Consolidated Car Rental Facilities.

“It is five stories and will house five of the car rental families,” Fuchigami said. “It has a quick turn-around area, car wash and parking stalls for cars being stored.”

Much of the work on the tall structure is being handled by large cranes.

“You also have backhoes and dozers, but we see a lot of cranes, big cranes,” Fuchigami said. “The cranes are necessary to drive the piles into the ground and for lifting certain slabs to certain floors. It's a five-story building and a matter of getting things from point a to point b.”

The rental facility is set for completion in 2020.

There also is a $70 million renovation project in the concessionaire area.

“It's been a huge upgrade to the appearance of the airport,” Fuchigami said. “We were able to get the concessionaires to fund it. It is on the second level and they cantilevered it over the first floor to create another 10,000 square feet. We're very proud of that.”

The modernization project has come under some criticism for taking too long to complete, with some components under way for more than a decade. The criticism helped spark a move to pass the airport corporation bill, which would have moved the project out of the state's hands and put it under the direction of an independent board.

The bill, SB658, however, did not survive the legislative session.

“An airport corporation would have added efficiency and reduced redundancy, which would have helped construction projects finish faster,” said Fuchigami. “Airport management does not have control over the decision making that would deliver first class airports. Without systematic changes the public should not expect significant changes at our airports. That said, we will continue to manage with the resources we have available for the 34 million passengers who fly to and from Hawaii's 15 airports each year. We thank Attorney General Doug Chin for working with us and we will continue to work with the Legislature to address any concerns on the issue. We will not give up on making a difference.”

Chin commended Fuchigami for “thinking outside the box” in trying to solve the airport related issues.

“Taking the State out of airport management is a complex idea with a variety of factors. It is not uncommon for huge changes like this to take time before gaining final approval,” said Chin.

The modernization project is expected to be ongoing through 2021.

CEG

This story also appears on Crane Equipment Guide.


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025