Harbor Bridge Project


Flatiron, Dragados JV Set to Finish Major Job in Corpus Christi

With work now in its final phase, the countdown is on for completing one of Corpus Christi's most anticipated construction projects. After years of research, public input and collaboration, the new U.S....


Harbor Bridge Project Pushing for 2025 Finish

The Flatiron/Dragados LLC (FDLLC) joint-venture constructing the Texas Department of Transportation's (TxDOT) design-build, $1.2 billion U.S. 181 Harbor Bridge Project (HBP) in Corpus Christi is pressing forward and making considerable strides for an initiative that not only improves traffic flow and enhances commercial activity, but is improving life for area residents....


TxDOT, Contractor Agree to Resume Harbor Bridge Project

The Texas Department of Transportation (TxDOT) has reached an agreement with the developer of the New Harbor Bridge Project, Flatiron/Dragados LLC (FDLLC), that settles all outstanding disputes and damage claims....


TxDOT, Contractor Take Steps to Resume Harbor Bridge

TxDOT and Flatiron Dragados LLC (FDLLC) have executed a signed letter agreement that establishes the legal framework for resolving the safety issues identified in the design of the New Harbor Bridge Project....


Contractor, TxDOT Work to Continue Harbor Project

TxDOT has recently had productive communications with Flatiron Dragados LLC (FDLLC) and its parent company, ACS Group, regarding concerns over the construction on the Texas Harbor Bridge project. Those discussions have taken a new direction and tone since TxDOT issued a notice of default on Aug....


Harbor Bridge Project Crews Have Productive Summer

The summer months were an incredibly productive time for construction progress around the South Interchange or future tie-in point for IH 37, SH 286 (Crosstown Expressway) and US 181. Despite initial rain delays, roadworks and structure crews met several goals to accomplish major upcoming traffic shifts, connector switches and demolition of existing ramps around the IH 37 and SH 286 Interchange....


CCHB Crew Pours Concrete

Over the past month, crews on the south side of the Harbor Bridge project in Corpus Christi achieved a major milestone with the completion of the largest concrete pour to-date on the project. The pour was part of the construction of the footing for the south pylon and included 3,100 cu....


First Pre-Cast Segment Reaches Corpus Christi Harbor Bridge Work Site

On Sept. 4, the Corpus Christi Harbor Bridge project reached a major milestone when the first pre-cast segment was delivered to its North Approach. The segment weighs 135 tons and is the first of about 2,600....


Harbor Bridge Crews Achieve Project Milestone

Harbor Bridge Project (HBP) crews have reached another milestone with the completion of 40 drilled shafts on both the north and south side of the project. The 40 drilled shafts will make up the foundations of the two bridge pylons....


HBP Crews Provide Recovery Assistance in Wake of Storm

Heavy equipment operators, superintendents, field crew members, subcontractors and employees from all different backgrounds and specialties joined forces to assist with clean-up efforts for those hardest hit by Hurricane Harvey....


Today's Top Stories

  1. Traffic Could Begin Moving Across Tampa Bay's Howard Frankland Bridge in Early 2025  →
  2. Blanchard Holds First Used Equipment Yellow Tag Sale in West Columbia, S.C.  →
  3. Georgia Is Moving Ahead to Enhance Highway Networks  →
  4. Iowa DOT's I-35 Project Includes New Bridges  →
  5. ROMCO Equipment Co., SMT Acquire Bee Equipment Sales  →
  6. Next Generation Cat D8 Dozer Provides Next-Level Technology  →
  7. Year in Review: Bobcat's Major Moments of 2024  →
  8. Des Moines Airport Works With Weitz/Turner On Expansion  →
  9. Touro University Building First Dental School in New Mexico  →
  10. CFX Oversees $412M SR429 Expansion in Florida  →
  11. Lake Perris Emergency Release Facility Project Under Way  →
  12. Kobelco Announces RTL Equipment as New Authorized Excavator Dealer  →
  13. New York State Court Ruling Could Impact How Cities Report Road Damage, Conditions  →
  14. California Coastal Commission OKs Plan for $175M Seawall  →
  15. DEVELON Set to Exhibit at ARA Show 2025  →
  16. Amtrak Completes Important Early Construction Activity for Susquehanna River Bridge Project  →
  17. Liebherr Announces West Coast Container Crane Contract  →
  18. MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs  →
  19. Two Repaired Road Bridges in Stamford, Conn., Reopened, Three More Still Need Work  →
  20. VIDEO: Construction Progressing On New Arena for UGA's Ice Dawgs Hockey Team  →
  21. VIDEO: Electric Demolition Excavator Gives Robles1 New Edge  →