Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Construction of the future 630-foot high observation wheel has hit what appears to be a potential snag.
Thu June 15, 2017 - Northeast Edition
STATEN ISLAND, N.Y. -- While the city Buildings Department has reported a minor issue with the legs of the NY Wheel, a source says the problem can potentially hinder the project.
Construction of the future 630-foot high observation wheel in St. George has hit what appears to be a potential snag because some of the "welds are bad" on the NY Wheel legs that were crafted in Italy, according to a construction source with knowledge of the project.
"I know they were supposed to be putting those legs up already and they aren't," the source said. "It sounds like just from following what's going on that they are going to be three months behind."
However, a NY Wheel spokesperson said the construction glitch will not delay the Wheel's target opening date.
'Minor Problem'
The legs, which arrived at Brooklyn Marine terminal last fall, are the next step in erecting the giant wheel, according to information previously provided to the Advance by the NY Wheel.
The city Buildings Department said the minor problem with the welds was uncovered by a special Buildings Department inspector, whose job it is to make sure all the parts of the project are tested and up to code.
The issue involved less than 10 welds, of which the largest was a few inches long, according to the Buildings Department. The legs consist of thousands of welds.
The department issued the following statement:
"DOB (Department of Buildings) requires special inspections for the Wheel and other large, metal-frame structures under construction. The special inspector identified a minor problem with a weld that the Wheel properly reported to DOB and is in the process of fixing. It's not uncommon for special inspectors to spot small issues like this and it demonstrates that the city's quality-control process for construction projects is working exactly as it should."
The cost for the legs and installation was previously calculated to be roughly $15 million of the $580 million project, which is scheduled to open in April 2018.
When asked about the weld issue and how it may hinder construction, a NY Wheel spokesperson said:
"All welds in any construction project are fully inspected as required by the New York City Buildings Department. As is the normal course following these inspections, minor remediation to a component is not atypical in this sort of construction project and construction is proceeding."
Most Recent Site Work
Recent work at the site has involved the terminal building, where ticketing, photos, merchandise and concessions will be housed, said a spokeswoman.
Crews most recently installed a curtain wall, which will have a terracotta-like exterior to keep rain out, elevators and plumbing, she said.
In addition, crews completed the foundation for the outdoor beer garden and the green roof, said the NY Wheel spokeswoman.
(Source: silive.com — http://www.silive.com/news/2017/06/sources_faulty_parts_may_hinde.html)