List Your Equipment For Free  /  Seller Login

Krome Avenue Project Approaches Completion

Mon July 30, 2018 - Southeast Edition #16
Irwin Rapoport – CEG Correspondent


Odebrecht Construction USA is less than two months away from completing the Florida Department of Transportation’s (FDOT) $59 million project to widen and improve a segment of Krome Avenue.
Odebrecht Construction USA is less than two months away from completing the Florida Department of Transportation’s (FDOT) $59 million project to widen and improve a segment of Krome Avenue.
Odebrecht Construction USA is less than two months away from completing the Florida Department of Transportation’s (FDOT) $59 million project to widen and improve a segment of Krome Avenue. Peak days saw close to 30 construction workers on-site. The existing roadway had cracks and other pavement issues at certain locations. The Krome Avenue section is widening the road from two lanes to four lanes; installing a 40-ft. median, a new drainage system and a guardrail throughout the project limits; and constructing a new multi-use trail for walking and biking.

Odebrecht Construction USA is less than two months away from completing the Florida Department of Transportation's (FDOT) $59 million project to widen and improve a segment of State Road (SR) 977/Krome Avenue from SR 94/SW 88 Street/Kendall Drive to north of SR 90/SW 8 Street/Tamiami Trail in western Miami-Dade County.

The work started in February 2015 and is estimated to be completed in September 2018.

The Krome Avenue section is widening the road from two lanes to four lanes; installing a 40-ft. median, a new drainage system and a guardrail throughout the project limits; and constructing a new multi-use trail for walking and biking. The SW 88 Street/Kendall Drive section is realigning the intersection; reconstructing the roadway and shoulders; and upgrading signage, lighting and traffic signals. The SW 8 Street/Tamiami Trail section is realigning the intersection; widening the bridge over the C-4 Tamiami Canal; and upgrading signage, lighting and traffic signals.

“This project is part of the overall plan for Krome Avenue,” said Ossie Larrazabal, FDOT's senior project engineer with Solid Consultant Engineers Inc. “The enhancements to Krome Avenue will increase safety along the corridor and provide a better commute to residents in south Miami-Dade County.”

The new infrastructure was designed by Marlin Engineering.

“Access to important stakeholders such as the Miccosukee Resort and Gaming Facility, Krome Detention Center, Dade Corners gas station and CEMEX plant had to be maintained at all times,” Larrazabal said. “The team worked hand-in-hand with the stakeholders to schedule the work during low impact hours to minimize disruptions.”

The existing roadway had cracks and other pavement issues at certain locations.

As the work has wound down, so have the traffic impacts. Permanent work zones were established along the corridor to maintain one lane of traffic open in both directions. The contractor recently opened both northbound and southbound travel lanes. Temporary daytime and nighttime lane closures will continue through the remainder of the project during off peak hours to minimize impacts to the community.

“Maintaining traffic flow is critical,” Larrazabal said. “This is an important route for commuters and the trucking community. There's been a lot of coordination between the team, contractor and county to keep the traffic moving.”

In terms of remaining work, Odebrecht has to finish placing the final layer of asphalt and complete lighting and signalization items throughout the corridor.

“It's such a long corridor, so staying organized and on top of the sequence of work has been key,” said Rogers Cruz, Odebrecht's project manager. “We've had to coordinate well in advance with our subcontractors to make sure everyone has work to do to stay on schedule. There's been lots of meetings.”

“The team meets daily to discuss ongoing work and upcoming milestones, so we've really gotten to know each other well,” said Larrazabal. “We are also fortunate to have had numerous opportunities for the crew to participate in on-the-job training programs to learn new skills.”

Peak days saw close to 30 construction workers on-site. Major subcontractors include: General Asphalt for pavement; Florida Sol for signal and lighting; Jones-Benitez for bridge construction, Barreiro Construction for concrete placement; Agland for sod placement; AMROADS for pavement markings; and Bob's Barricades for maintenance of traffic devices.

Materials excavated and removed from the site include: 7 mi. of the old roadway; 700 linear ft. of the old bulkhead canal wall; and 270,000 cu. yd. of earthwork.

New materials include more than 65,000 tons of asphalt; two million cu. yd. of earth work; 2,000 cu. yd. of concrete; and 150,000 lb. of steel.

For the project, Odebrecht has been using: three cranes, six excavators, four dozers, four loaders, five rollers and two pavers, which includes Cat, John Deere and Kenworh equipment. Odebrecht purchases and rents equipment from dealerships such as Kelly Tractor, Nortrax, Herc Rentals, United Rental, Neff, Synergy Rents, Action Rentals, Meco Miami and Trekker.

“We've observed most wear and tear issues with moving parts,” said Cruz, “such as bucket teeth and blades that break down all the time. It is also very common to get flat tires on equipment. It usually takes a day to repair these minor issues. All the equipment is under warranty or a service contract. The mechanics come to the jobsite on an as needed basis.”

The work on Krome Avenue, once the current project is completed, will resume in early 2019 and be completed in the summer of 2020. The $42.7 million project will cover the area between SW 136 Street and SW 232 Street.

The work includes: rebuilding and widening of Krome from a two-lane roadway to a four-lane roadway divided by a 40-ft. grassed median; providing a drainage system and lighting along the length of the project; installing guardrail in the median along the length of the project; providing adequate access management and improving traffic operations throughout the corridor; installing guardrail in the median along the length of the project; and building a new bridge over the C-102 canal.

The general contractor for the project is Halley Engineering Contractors Inc., with construction engineering and inspection services to be provided by The Corradino Group.

“The upcoming project is a continuation of the 36-mile corridor improvements,” said Heather Leslie, community outreach specialist of the project, who helps FDOT with communications on road projects. “These projects have been in the works since 1999 and will continue to address safety, flooding, water quality, economic competitiveness and preservation of the existing roadway. The Department wants to ensure a safe and reliable road for the residents and commuters in this area.”

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.96118 \\ -82.99879 \\ Columbus \\ OH