List Your Equipment For Free  /  Seller Login

Leaking Expansion Joints Spur Two Bridge Rehabilitation Efforts in N.H.

Thu November 21, 2019 - Northeast Edition #24
Ken Liebeskind -CEG Correspondent


The rehabilitation of two bridges in Bedford and Manchester, N.H., is underway, with much of the work completed on one section of them.
The rehabilitation of two bridges in Bedford and Manchester, N.H., is underway, with much of the work completed on one section of them.
The rehabilitation of two bridges in Bedford and Manchester, N.H., is underway, with much of the work completed on one section of them. The work is being done on the Route I-293 northbound and southbound bridges over the Merrimack River in Bedford and Manchester. The pier work on the southbound bridge is complete and the northbound bridge should be completed by Thanksgiving. The water leak from the expansion joints caused cracking along the lower piers. To extend the life of the bridges, the expansion joints needed be replaced, the concrete deck improved and proper bridge piers installed. R.S. Audley of Bow, N.H., is the contractor on the $4.7 million project. The company also is using a Grove RT760E rough-terrain crane and a Blast It All Mfg. Workhorse Skid Steer Scraper. The old joints had been leaking for some time with substantial decay in the concrete.

The rehabilitation of two bridges in Bedford and Manchester, N.H., is under way, with much of the work completed on one section of them.

R.S. Audley of Bow, N.H., is the contractor on the $4.7 million project that is being directed by NH Department of Transportation.

The work is being done on the Route I-293 northbound and southbound bridges over the Merrimack River in Bedford and Manchester. Each bridge is 914 ft. long and 55 ft. wide and carries three 12-ft. travel lanes.

Tyler Vaughan, a civil engineer of NHDOT, said, "The project included removing the bridge deck pavement and membrane checking the deck for concrete repairs and also piers 2 and 5 for concrete repairs. These two piers had bridge joints that needed to be replaced. The old joints had been leaking for some time with substantial decay in the concrete. With the excess decay, the amount of chipping was limited to small areas to keep structural integrity of the bridge while maintaining traffic above."

"The job was challenging because of the volume of traffic and limited access for pier rehabilitation work," said Scott Stevens, R.S. Audley bridge engineer. "We used an Anderson Hydra Platform under bridge access device, which was more flexible than a crane-mounted man basket, which we've used before."

The company also is using a Grove RT760E rough-terrain crane and a Blast It All Mfg. Workhorse Skid Steer Scraper.

Vaughan said the pier work on the southbound bridge is complete and the northbound bridge should be completed by Thanksgiving. The top decks of both bridges will be started in April, 2020 and should be completed by September.

The bridges were built in 1958 and widened and re-decked in 1991, according to Jason Tremblay, senior project engineer of NHDOT's Bureau of Bridge Design. He said an inspection of the bridges showed that expansion joints were failing, which set up the current job.

"We chipped away to replace sections piece by piece so as not to degrade the extension joints," Vaughan said. "The piers have safety devices built in, so there is no danger to traffic."

The water leak from the expansion joints caused cracking along the lower piers. To extend the life of the bridges, the expansion joints needed be replaced, the concrete deck improved and proper bridge piers installed.

"It should be 20-plus years before we have to preserve the bridge again," Tremblay said. CEG




Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: Two Major Roadway Project Contracts Awarded by State Officials in West Virginia

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer


 







\\ \\ \\