List Your Equipment For Free  /  Seller Login

Lehigh Cement Expands, Replaces Union Bridge Quarry

Major equipment used on the job includes six 40-ton (36 t) articulated trucks, eight track excavators sized 50,000 to 200,000 lbs.

Tue January 12, 2016 - Northeast Edition
Brenda Ruggiero


The Joseph B. Fay concrete crew places concrete in a traveling form.
The Joseph B. Fay concrete crew places concrete in a traveling form.
The Joseph B. Fay concrete crew places concrete in a traveling form. An example of deep excavation with a 36 in. (91 cm) steel stream diversion pipe in foreground. This Cat 349 excavator and Komatsu PC300 with 8,000 lb. (3,629 kg) hydraulic hammer downsize shot rock. This excavation is one of two deep cuts on the project and will be sloped in soil and near vertical in rock. The stream is flowing through a 36 in. (91 cm) steel casing and saved the contractor from establishing temporary channels to cross the stream. The crane servicing rebar and carpenter crews is an 85-ton (77 t) Kobelco CK850G. A Komatsu 650 excavator loads out soil and rock onto a Komatsu HM 400 40-ton (36.28 t) articulated truck. The completed tunnel with traveling concrete formwork is headed towards a road and stream crossing. The project covers 5 mi. (8 km), with work being simultaneously performed at multiple locations. A quarry replacement project in Carroll County, Md., involves the installation of the longest continuous curved conveyor ever to be installed in the state.

A quarry replacement project in Carroll County, Md., involves the installation of the longest continuous curved conveyor ever to be installed in the state. Large lengths of the conveyor must be below grade due to permit and community restrictions.

The Lehigh Cement Company LLC is currently replacing its Union Bridge Quarry with a greenfield quarry expansion in the neighboring town of New Windsor. The project began in May 2015 and is scheduled to be complete and commissioned by Nov. 2017.

The contract, which is for an undisclosed amount, was awarded to Joseph B. Fay Company, an i+iconUSA Company, with Scott Wilson as project manager. Fay recently received a separate contract for opening a portion of the new quarry across the street.

The quarry is a greenfield site requiring development to begin mining and processing operations including office and maintenance facilities. Work includes excavation, installation of box culverts, and several foundations for the ultimate installation of a 4.7-mi. (7.56 km) conveyor system to enable the client to transport crushed limestone from the quarry to its existing Union Bridge cement plant.

Fay is using EFCO traveling form system to place 250 lf. (76.2 m) of tunnel every two weeks. This project includes 9,600 ft. (2,926 m) of tunnels, up to 60 ft. (18 m) deep in some locations, and 11,300 ft. (3,444 m) at grade under a jumbo cover on concrete slab, which is 12 ft. (3.6 m) wide and 9 ft. (2.7 m) high.

The project covers 5 mi. (8 km), with work being simultaneously performed at multiple locations. This requires extensive planning and coordination of equipment and personnel, and Fay is using BlueBeam Review and ipads to have the most recent drawings and documentation available at all locations.

The conveyor which is being installed is made in China for a German company. This required inspection in China before shipping to the United States and then eventually to the location. This will be done in 40-ft. (12.2 m) sea containers which then will be trucked to the site.

“Throughout the length of this conveyor system, there are seven road crossings, six of which require tunnels to be built under the roadways, which ultimately require road closings to complete the work,” explained Wilson. “Carroll County wants only one road closing at a time. For each tunnel, the area needs to be open cut, back filled, and then have the roadway restored.”

There is a very narrow right of way on the project. Lehigh owns half of the property on which the conveyor is being built, and the remainder is a dairy farm for which Lehigh has easement. Fay is also required to tunnel through the farmland and restore it to its previous conditions.

“To pass clean across the fields, the water flowing from the fields and ditches is passed through clear water diversion pipes,” said Wilson. “Berms on the high side collect the water and funnel it into a pipe through the job site. It then exits the low side onto the field on the other side. Construction must be contained inside of sediment control using silt fence and berms.”

Tunneling is required under three stream crossings, and Fay came up with an innovative approach to have the steams run into a 36-in. (91 cm) metal culvert in the same geographical location and across the tunnel. The original plan diverted the stream to a new geographical location during construction and then back to the original location once completed. The new innovation saves time and has less impact on the environment.

Much of the terrain of the project has limestone with an irregular rock surface. This can vary up and down by 15 ft. (4.5 m) in a span of 10 ft. (3 m) due to pinnacles of rock making it difficult to dig.

The project includes 526,000 total cu. yds. (402,155 cu m) of earth and rock excavation, 26,155 total cu. yds. (19,999 cu m) of concrete placement, and 5.3 million total lbs. (2,408.5 t) of reinforcing steel.

Major subcontractors working on job include Taggart, conveyor and electrical installer; Senex, blaster; McCrossin, drilled piers; Interlock, rebar installer; Franco's Liberty Bridge, slab installer; Tom Brown Waterproofing, waterproofing; Plum Contracting, underdrain; Hawkins Erosion Control, silt fence and seed; Victory Steel, rebar supplier; and Buemer Group, supplier of the conveyor.

Major equipment used on the job includes six 40-ton (36 t) articulated trucks, eight track excavators sized 50,000 to 200,000 lbs. (22,679 to 90,718 kg), five dozers (D8 to D5-sized), four rollers, three 60- to 120-ton (54 to 109 t) cranes and various other smaller equipment.

Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Progress Continues On $250M Columbus LOT Project

Work Continues On Largest Project in NYSDOT History

OSHA Puts PPE for Women, Hard Hats On Its Radar

Case Introduces Limited Signature Edition Backhoe Loader for Iconic Presence On Job Site

Consider These Comfort, Performance Features When Selecting Your Next Compact Track Loader

Aerospace Hub Construction Starts

Vantage Selects Turner Construction Corp. for $2B Expansion Project

AES Ohio Powers Economic Development With Major Upgrades


 







39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085