List Your Equipment For Free  /  Seller Login

Major Project Aims to Improve Travel in Wichita

Wed May 02, 2018 - Midwest Edition #9
Cindy Riley – CEG Correspondent


In an effort  to reduce congestion, increase capacity and improve travel in east Wichita, the Kansas Department of Transportation (KDOT),  Kansas Turnpike Authority (KTA) and the city of Wichita have partnered to provide improvements at the Webb Road intersection and the Greenwich to K-96 corridor. 
(KDOT photo)
In an effort to reduce congestion, increase capacity and improve travel in east Wichita, the Kansas Department of Transportation (KDOT), Kansas Turnpike Authority (KTA) and the city of Wichita have partnered to provide improvements at the Webb Road intersection and the Greenwich to K-96 corridor. (KDOT photo)
In an effort  to reduce congestion, increase capacity and improve travel in east Wichita, the Kansas Department of Transportation (KDOT),  Kansas Turnpike Authority (KTA) and the city of Wichita have partnered to provide improvements at the Webb Road intersection and the Greenwich to K-96 corridor. 
(KDOT photo)
 The more than $300 million East Kellogg expansion includes new intersection designs at Webb and Greenwich and better access to the turnpike.
(KDOT photo)
 To date, crews have moved 410,000 cu. yds. of dirt and anticipate moving an additional 830,000 cu.yds. up to completion. 
(KDOT photo)
 The Kellogg & Webb project, which stretches from the East Wichita Turnpike access to just shy of Greenwich, will upgrade Kellogg to a six-lane freeway, with an interchange at Webb Road, frontage roads and modified access to the KTA at Exit 50.
(KDOT photo)

In an effort to reduce congestion, increase capacity and improve travel in east Wichita, the Kansas Department of Transportation (KDOT), Kansas Turnpike Authority (KTA) and the city of Wichita have partnered to provide improvements at the Webb Road intersection and the Greenwich to K-96 corridor. The more than $300 million East Kellogg expansion includes new intersection designs at Webb and Greenwich and better access to the turnpike.

“Projects like this reconstruction of an expressway into a freeway with multiple interchanges is a huge undertaking,” said Don Snyder, KDOT Wichita Metro engineer.

“It takes many years of planning, designing, gathering public feedback, acquiring right-of-way, moving and improving utilities, locating adequate funding and many other steps before construction can begin. Luckily, we have great partners in the city of Wichita and the Kansas Turnpike Authority. Without them, KDOT would have a difficult time moving these projects forward, because we're working on a major interchange replacement on the other side of Wichita. We are also wrangling a number of other large infrastructure projects on an aging interstate and local highway system.”

Gary Janzen, city engineer of the city of Wichita, said a great deal of thought and effort went into mapping out construction.

“The projects were originally planned as two separate projects to improve Kellogg to a freeway one mile at a time,” he said. “But because of changes to the design of the first project that impacted direct access to the KTA, the second, which re-establishes those direct connections, was expedited and managed by the KTA, due to the high level of coordination required with their infrastructure.

“The project scope includes city, state and the KTA infrastructure, so the teaming of the three agencies made sense, in order to ensure proper coordination during design and effective use of funding. It also allowed construction of the second project — Greenwich to K-96 — to begin several years sooner than it otherwise would have.”

The Kellogg & Webb project, which stretches from the East Wichita Turnpike access to just shy of Greenwich, will upgrade Kellogg to a six-lane freeway, with an interchange at Webb Road, frontage roads and modified access to the KTA at Exit 50. Construction plans also call for aesthetic enhancements, waterline, sanitary sewer, and stormwater improvements, along with landscaping.

The Kellogg, Greenwich to K-96 project will improve the next portion of Kellogg east of the Webb project to a six-lane freeway with an interchange at Greenwich, bridge over Zelta, new connections to the KTA and frontage roads.

Officials broke ground on the expansion in August 2015. Attendees at the event included state, local and project leaders, along with Mike King, who at the time served as Kansas transportation secretary and KTA director.

“All three agencies were excited to break ground on this project, and the ceremony went extremely well,” said Janzen, who added that construction began not a moment too soon.

“Kellogg traffic, which is around 40 to 50,000 vehicles a day, has to stop at the side roads — Webb, Greenwich and Zelta. And those side roads have to wait on Kellogg traffic. Upon completion of the project, Kellogg will be improved to six lanes and will go over or under the side roads, changing it to a freeway that no longer has to wait on side-road traffic. This will significantly reduce congestion both on Kellogg and the side roads.

“This also mitigates safety concerns. The Kellogg and Webb intersection was the location of the highest accident rate in the entire city. By grade separating [making the Kellogg traffic separate from the Webb traffic], the majority of vehicles no longer cross paths, which thereby significantly reduces the likelihood for incidents.”

The cost of the massive East Kellogg corridor improvements includes design, right-of-way, utility relocation, construction and construction engineering. A large portion of the price tag will be paid with T-WORKS funding of $162 million. The remaining Kellogg & Webb segment costs are being paid by the city, while remaining Kellogg, Greenwich to K-96 segment expenses will be funded by the city, KDOT and KTA.

The Kellogg & Webb project is being managed by the city of Wichita. The Kellogg, Greenwich to K-96 project is overseen by KTA. For the latter, the three agencies joined together, with KTA managing and bidding the project. Engineers for each organization have experience in breaking out costs to attribute the correct expenses to the appropriate partner.

Kellogg & Webb construction should take about four years, with anticipated completion in late 2019. The Kellogg,Greenwich to K-96 project construction should take about five years, and is expected to be finished by late 2021.

In early December 2016, crews marked a milestone with completion of the KTA bridge demolition. The tear down took a total of 17.5 hours, and completed 36 hours ahead of schedule. Pearson Construction served as the demo contractor.

“US-54 was closed and detoured beginning Friday evening of the planned demolition,” said Janzen. “Demolition occurred Friday night into Saturday. The contractor was allowed full closure of US-54 until Monday morning at 5:00 a.m., however, it was cleaned and reopened to the public by Saturday afternoon.”

Workers completed as much preparation work as possible in advance of the closure, including removal of the approach slabs and embankments, leaving the freestanding bridge structure only for demolition. Crews had a considerable amount of heavy equipment, including a crane with wrecking ball, front end loaders, dozers and excavators available to pad the road, demolish the bridge and clean the road to reopen.

Another milestone was reached in late 2017 for both projects, when the newly opened frontage roads began carrying US-54 traffic. This achievement allowed for the grading and bridge work to begin on the freeway portion between the frontage roads. The west half of the Webb Road bridge is anticipated to be completed this summer. The bridge is a steel tub-girder structure with the outermost girders being curved.

According to Roger McClellan, president of general contractor Wildcat Construction, “Communication is the key to the project success, and we work tirelessly to establish and maintain positive relationships with the city of Wichita, KDOT, Kansas Turnpike Authority, subcontractors and suppliers. It is a challenging and ongoing process, but as general contractor, it is our responsibility to foster an environment where communication leads to collaboration.

“Technically, the biggest challenge we have faced is the development and implementation of the aesthetic finishes for vertical concrete elements. We worked closely with project partners to develop artwork that met the intent of the plans, while remaining constructible during placements in excess of 20 feet tall and 70 feet wide. After 18 months of analysis, we developed a concrete mix that would meet all KDOT specifications and provide a crisp finish for relief ranging from ¼” to 3 ½” deep.”

Significant earthwork movements, retaining walls, and a total of seven bridges are in progress, as traffic has been moved to the outer limits of the Kellogg corridor from Cypress to Zelta. Utility relocation has been completed for the entire corridor, along with the frontage roads built and opened to carry traffic during mainline construction.

The work has not been without its share of challenges. In early 2017, a 20-in. water line providing service to customers along Webb Road, from Orme to Lincoln, was damaged due to construction work in the area. The interruption affected four area businesses and a 124-unit apartment complex.

Dealing with changing weather also is an issue, although there have been no major setbacks because of the elements.

“We have been able to work during the mild winters since the project began, which has allowed us to mitigate the impact of significant spring rains in the last two years,” said McClellan. “We continually evaluate weather forecasts with our planned activities to minimize the impact that Kansas weather can have on the progress of the projects.”

As for key tasks yet to be carried out, “Greenwich Road will be reconstructed, the westbound US-54 bridge will be removed and replaced over the Kansas Turnpike, and the KTA ramps at US-54 will be graded and paved,” said McClellan. “Lighting, ITS and aesthetic finishes like decorative steel panels and landscaping also remain for later phases of construction.”

The condition of the job site prior to construction was less than ideal.

“During right-of-way acquisition, the city of Wichita, KDOT, Kansas Turnpike Authority and their consultants identified underground utilities, buildings, on-grade pavement, and signals that were to be removed to make way for new construction. However, during the course of utility relocation, the project team identified additional underground conflicts with new construction, and provided cost-effective solutions to benefit the public and later phases of construction.”

To date, crews have moved 410,000 cu. yds. of dirt and anticipate moving an additional 830,000 cu. yds. up to completion. Cranes and other material handling equipment will be used for the retaining wall and bridge construction. Excavators, trucks, loaders and dozers will be used for earthwork and remaining storm drainage systems.

Some of the main materials that will be permanently incorporated into the projects include structural steel, concrete, reinforcing steel, reinforced concrete pipe, precast wall panels and aggregates. Custom formliners also are being used to create a unique pattern on the bridges and retaining walls, in an effort to pull the two projects together.

McClellan noted that mainline construction will be the most time-consuming portion of the project, as an underpass at Webb Road and overpasses at Greenwich Road and Zelta Road are constructed. These drastic changes to the profile of Kellogg will eventually allow Kellogg traffic to flow above or below arterial traffic.

A number of precautions also have been taken during the ongoing work.

“All on-site employees, supervisors, inspectors and project team personnel are required to follow OSHA's construction standards during work activities,” said McClellan. “Work days begin with stretch & flex for Wildcat crews, and job safety analysis forms are completed by foremen for the work day's activities. For sensitive activities, targeted pre-work meetings are held between field and project team personnel to communicate and implement a work plan that addresses all needs and concerns.

“To protect the public, we use concrete safety barrier, temporary fencing and handrails to minimize exposure to fall risks or collision risks while traveling through the site. We inspect traffic control daily, and promptly correct deficiencies to ensure routes and detours are clear and easy to navigate.”

As a general rule, two lanes of traffic are open in each direction and left turns are prohibited during construction. There have been some expected traffic delays and some congestion, but officials are working to be proactive in communicating to the public through various social media networks provided by the partners. Although the ongoing work can be disruptive at times, including challenging traffic changes, feedback from the community has been positive, overall.

“We continue to hear from drivers how easy and relatively quick it is to travel through such a major project,” said Glen Scott, KTA design and construction engineer. “Most find alternate routes when needed, and look forward to the improvements when construction is completed.”

CEG




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\