Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Massdot takes on massive bridge reconstruction project along the I-95 in Massachusetts.
Wed January 11, 2017 - Northeast Edition #1
The Massachusetts Department of Transportation (MassDOT) is currently working on a project to replace several bridges in Attleboro, Mass. The construction bid price was $19.97 million and the project is planned to be funded through the 2016 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
The project consists of demolition and replacement of the substructure and superstructure of the I-95 northbound and southbound bridges over North Avenue in Attleboro. It also calls for the building of a temporary highway in the median of I-95 and over North Avenue to shift the traffic during two accelerated windows for the replacement of the bridges. Other scope of work includes the installation of a noise barrier including drilled shafts, widening of the southbound highway and utility relocations.
MassDOT District 5 awarded J.F. White Contracting's civil division the contract for the Attleboro Bridge Replacement project in July 2016. Work is expected to be complete by the spring of 2018.
Challenges with the project include maintaining three lanes of highway traffic in both directions of travel, coordinating work with adjacent contracts, demolishing and replacing the existing bridges within the time limits set in the contract, and maintaining traffic along North Avenue during the construction of the bridges.
One unique aspect of the job is that the contractor will be using an earth backfilled arch bridge as their choice for a temporary bridge. The contract uses accelerated bridge techniques during the construction of the bridges. By moving one direction of traffic into the median there is little disruption to highway traffic.
Major subcontractors for the job include Walsh Construction for earth work, J. R. Vinagro Corp. for clearing and grubbing and demolition, and Highway Safety Solutions Inc. for signage, traffic barriers, and pavement markings.
The length of the project with the temporary median road is just less than 1 mi. A total of 85,000 cu. yds. (64,987 cu m) of fill will be placed for the temporary median road, and the job will include 8,400 sq. ft. (780.4 sq m) of prefabricated bridge units and 37,740 sq. ft. (3,506 sq m) of noise barrier.
According to MassDOT, the proposed work for both bridges will consist of removing the existing bridge superstructures and substructure and replacing with new superstructures and substructure complete with new decks and barriers. The new superstructures will accommodate three lanes of traffic in their respective directions. The new structures will not feature sidewalks.
Four highway guardrail transitions will be located at the corners of each bridge, and approximately 100 ft. (30.5 m) of the existing approach roadways will be milled and paved on both sides of the bridges. CEG
Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.
Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.
Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.