List Your Equipment For Free  /  Seller Login

MDOT Begins M-30 Flooding Repairs in Midland, Gladwin

Tue July 07, 2020 - Midwest Edition #14
Michigan Department of Transportation


Debris removal at M-30 over the Tittabawassee River began June 29, and will allow crews to begin necessary repairs of the existing bridge piers currently blocked by trees and other debris.
Debris removal at M-30 over the Tittabawassee River began June 29, and will allow crews to begin necessary repairs of the existing bridge piers currently blocked by trees and other debris.
Debris removal at M-30 over the Tittabawassee River began June 29, and will allow crews to begin necessary repairs of the existing bridge piers currently blocked by trees and other debris.
 M-30 at the Tittabawassee River will require inspection of the existing bridge approach, which will be rebuilt following inspections. M-30 over the Tobacco River washed away in the flooding. Following debris removal, crews will begin construction of a temporary bridge.

The Michigan Department of Transportation (MDOT) has awarded an emergency contract to begin debris removal at two bridge locations on M-30 in Midland and Gladwin counties, following a historic flooding event in May.

M-30 structures over the Tittabawassee River in northern Midland County and over the Tobacco River in Gladwin County were both impacted by flooding. Midland-based Fisher Contracting was awarded the bid at $1.2 million and began work June 29. Debris removal is expected to finish by July 22.

M-30 Over Tittabawassee River
  • The contractor will use a barge to remove existing debris and trees blocking the bridge piers.
  • Following debris removal, inspection of the existing piers will be completed and a maintenance plan established.
  • MDOT plans to administer an emergency contract to address required maintenance for the bridge and bridge approach, following complete review of the existing structure and determining repair options.
M-30 Over Tobacco River
  • The contractor will remove existing debris, including remaining pieces of the original causeway bridge washed away during the flood.
  • Following debris removal, inspection of the existing channel will begin and soil borings collected.
  • MDOT is currently working with temporary bridging solution vendors to determine an appropriate temporary bridge structure that will remain in place for several years while permanent bridge plans are established.
  • Following debris removal, MDOT will administer an emergency contract to begin construction of a temporary bridge at M-30 over the Tobacco River.



Today's top stories

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

'Machinery Pete' Interviews Jack Lyon On RFD TV

VIDEO: Two Major Roadway Project Contracts Awarded by State Officials in West Virginia

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete

John Deere Construction Introduces Flexible Customer Training Options

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer


 







39.96118 \\ -82.99879 \\ Columbus \\ OH