List Your Equipment For Free  /  Seller Login

MDT Changes Course of $25M Road Project Due to Old Olive Branch Mine

Wed December 19, 2018 - West Edition #26
Lori Tobias – CEG Correspondent


Engineers knew it was possible that at least a portion of the mine shaft was close to the surface. So, they designed the new bridges around the old mine to minimize the risk.
Engineers knew it was possible that at least a portion of the mine shaft was close to the surface. So, they designed the new bridges around the old mine to minimize the risk.
Engineers knew it was possible that at least a portion of the mine shaft was close to the surface. So, they designed the new bridges around the old mine to minimize the risk. The $25 million project between Rocker and Butte is expected to take about three years to complete.

When the Montana Department of Transportation set out to reroute some outdated stretches of Interstates 15-90, it encountered an unexpected landmark. Located between the westbound and eastbound bridges, both built in the 1960s and considered "functionally obsolete" was an old, abandoned mine, dubbed the Olive Branch mine.

Engineers knew it was possible that at least a portion of the mine shaft was close to the surface. So, they designed the new bridges around the old mine to minimize the risk.

MDT will not do anything with the former mine, said Jeff Ebert, Butte district manager for MDT. The mine produced silver, as well as some gold, zinc and lead around the late 1800s and early 1900s.

"The timbers inside the mine that miners used to help hold the mine up when it was built are now in disrepair," Ebert said. "The mine also branched into horizontal tunnels that are throughout the whole area there, spiking out in various directions. In our opinion, it could have raised concerns with whether it was stable or not," he said. "It was a hazard."

The new road will change slightly from the original design. The eastbound bridge had been built into a curve, but will now be straight and located away from the old mine shaft.

Not having a curve in the bridge "increases the safety of the bridge," Ebert said. The new bridges also will be wider.

The $25 million project between Rocker and Butte is expected to take about three years to complete.

Phase one, which includes dirt work, guardrail installation and a bridge, is expected to be completed by the end of the year, said Geno Liva, Butte district construction operation engineer.

The schedule calls for traffic to be switched onto the new structures in the spring with phase two, removal of the old structures, also to get under way. Completion of the project will be in 2020 with chip sealing and final striping.

There have been some minor budget changes, driving the original $24.3 million project by up about $700,000, Liva said. Those costs included increased traffic control costs and an overrun of mine waste removal by about 700 percent of the original plan.

Crews have encountered numerous challenges, Liva said. The mine, however, was not one of them.

"One of the challenges has been the schedule," he said. "We are replacing two structures in each construction season of 2018 and 2019. This is significant because of the short construction seasons here in Montana. The contractor did experience some delay in acquiring steel for the project, as well, which compounded the short season issue. Moving the traveling public through the project site was another challenge on the project. This section of interstate carries traffic from both I-90 and I-15. While replacing the structures we have traffic in a two-lane configuration with the use of crossovers and have closed an interstate exit in one direction.

"Working around the mine has not caused many issues for construction of the project. Changes were made with the discovery of the abandoned mine shaft in the preconstruction phase. We included the work to cap the mine shaft in the plans and that work also is near completion. The public will benefit from the project in many ways including having improved structures on the roadway and a reconstructed roadway to travel on. The new structure is significantly wider than the old ones."

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Des Moines Airport Works With Weitz/Turner On Expansion

ROMCO Equipment Co., SMT Acquire Bee Equipment Sales

San Francisco County Transportation Authority Bridges Retrofit Addresses Seismic Safety

Year in Review: Bobcat's Major Moments of 2024

MassDOT to Use Drones for Infrastructure Projects; Amherst Exploring New Downtown Designs

Iowa DOT's I-35 Project Includes New Bridges

JM Wood Holds December Auction in Montgomery, Alabama

DEVELON Set to Exhibit at ARA Show 2025