List Your Equipment For Free  /  Seller Login

MDU to Build Pipeline to Doosan Bobcat Factory

Wed October 04, 2017 - Midwest Edition #20
Construction Equipment Guide


Bismarck-based Montana Dakota Utilities is building a $13.8 million pipeline to provide natural gas to a South Korea-owned manufacturing facility in southeastern North Dakota.
Bismarck-based Montana Dakota Utilities is building a $13.8 million pipeline to provide natural gas to a South Korea-owned manufacturing facility in southeastern North Dakota.

BISMARCK, N.D. (AP) Bismarck-based Montana Dakota Utilities is building a $13.8 million pipeline to provide natural gas to a South Korea-owned manufacturing facility in southeastern North Dakota.

MDU said construction of the 12-in., 21-mi. long pipeline to the Doosan Bobcat Inc.'s factory in Gwinner will be complete in September 2018.

The North Dakota Industrial Commission earlier approved $10.5 million in financing through the state-owned Bank of North Dakota. Regulators also granted the project a certificate of public convenience and necessity, which means traditional permits aren't necessary.

Doosan Bobcat signed a 15-year contract with MDU to get gas from the pipeline, which is fed from Alliance Pipeline's system that extends from western Canada to a Chicago hub.

North Dakota natural gas helps feed that pipeline at two points in the western part of the state.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\