List Your Equipment For Free  /  Seller Login

New Bridge Debuts as 'Off Broadway' Work Continues

Wed April 11, 2018 - West Edition #8
Construction Equipment Guide


American Bridge crews carefully maneuver the second bridge span into place over southbound I-235 in preparation for attaching the truss structure to the center pier. It took more than six hours to move and secure the span in place.
(ODOT photo)
American Bridge crews carefully maneuver the second bridge span into place over southbound I-235 in preparation for attaching the truss structure to the center pier. It took more than six hours to move and secure the span in place. (ODOT photo)
American Bridge crews carefully maneuver the second bridge span into place over southbound I-235 in preparation for attaching the truss structure to the center pier. It took more than six hours to move and secure the span in place.
(ODOT photo) Southbound I-235 reopened to traffic just after 6:30 a.m. Jan. 29 in time for morning rush-hour. The old BNSF railroad bridge can be seen adjacent to the new, 550-ft.-long railroad bridge. The older bridge is expected to be removed sometime later this spring, which will allow for the widening of I-235 to six lanes plus auxiliary lanes.
(ODOT photo)

The curtain is up and I-235 in Oklahoma City is now open following the first bridge move of its kind in state history by the Oklahoma Department of Transportation. The interstate was closed for nearly 60 hours to move two giant bridge spans into place and now the new BNSF railroad bridge is taking center stage in its new home above the interstate.

This historic bridge move began Jan. 26, as all lanes of I-235 were closed between N. 36th Street and I-44 to prepare for the big show. On the morning of Jan. 27, self-propelled mobile transporters began inching the first of two 45-ft. tall truss bridge spans weighing a total of 4-million lbs. from their assembly site in the work zone to their final location about a quarter of a mile to the south, just south of N. 50th Street The second span began moving mid-morning on Jan. 28 and was fully installed by early evening. Northbound I-235 reopened to traffic that night and southbound lanes opened early Jan. 29, in time for the morning commute.

“We know this closure placed a tremendous burden on traffic in the area, and we can't thank drivers enough for their patience,” said Casey Shell, ODOT chief engineer. “The amazing teamwork between the project designers, Allen Contracting and American Bridge and ODOT workers to get all this in place over a weekend was truly a modern engineering marvel and something Oklahomans will long remember.

“Specifically, we want to thank Allen Contracting for working tirelessly through Sunday night to beat expectations and reopen the interstate to traffic Monday for morning commuters — a full day earlier than the time allowed within their contract.”

This marks the first time this type of bridge movement and installation has taken place in Oklahoma. Building the bridge truss structures near the highway and moving the fully assembled spans into place over the weekend greatly reduced the impact to traffic, requiring the interstate to be closed for a few days rather than several months if traditional bridge construction methods had been used.

“This innovative bridge construction and installation method is a first for Oklahoma and saved drivers the inconvenience of several months of closures on I-235,” Steve Jacobi, ODOT bridge engineer said. “Everyone involved with this effort did an excellent job executing the bridge move, which was a major milestone in this project.”

This work is part of the nearly $88 million reconstruction and widening project on I-235 between N. 36th Street and I-44. While completion of this bridge move is a major accomplishment to celebrate, there is still a year left in this more than two-year-long project on I-235. Motorists can expect I-235 to be open with two lanes in each direction with reduced speed limits in the work zone through 2019. Drivers are encouraged to continue using their Off Broadway alternate routes such as I-35, I-44, SH-74/Lake Hefner Parkway and I-40.

Once complete, I-235 will be widened to six lanes plus auxiliary lanes and receive ramp improvements and a significantly improved drainage system for the highway. This project is one of several phases to completely reconfigure the I-235/I-44/ U.S.-77 (Broadway Ext.) interchange in Oklahoma City.

In the coming weeks BNSF crews will begin laying track to connect the existing railroad line to the new structure, allowing for later removal of the old railroad bridge by ODOT's contractor.

For more information, visit odot.org.




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\