List Your Equipment For Free  /  Seller Login

ODOT Devises Plan to Keep Rock, Mud Slides at Bay

Tue February 13, 2018 - West Edition #4
Lori Tobias – CEG Correspondent


Crews first used excavators, loaders and dozers to clear out the slide debris, and hauled out 150 truckloads of soil. Then they lined the excavated site with drain rock.
Crews first used excavators, loaders and dozers to clear out the slide debris, and hauled out 150 truckloads of soil. Then they lined the excavated site with drain rock.
Crews first used excavators, loaders and dozers to clear out the slide debris, and hauled out 150 truckloads of soil. Then they lined the excavated site with drain rock.
 The blocks were one part of a two-prong approach that also included installing a large trench drain just north of the geofoam to divert water away from the slide area.

Engineers with Oregon's Department of Transportation have come up with a new fix for a pesky problem that has plagued a much-traveled highway since the 1950s.

The recent problems on U.S. 20 — a highway 2.5 mi. from Newport that links the central Oregon coast to the I-5 corridor — began in the winter of 2015 after heavy rains triggered a landslide. ODOT spent $100,000 to fix the problem, finishing the work in October 2016. Just one month later, record rainfalls caused the road to slide again.

The state has been working on the problem for decades. In the 1960s, ODOT placed a culvert beneath the roadway and was able to keep the slope stable with only ongoing minor repairs — until the recent slides.

But this time ODOT engineers looked a little deeper. A geotechnical investigation revealed that the original culvert had failed and that the slide area beneath the highway stretched south all the way to Yaquina Bay. With that knowledge, they decided to take a different approach to the repair. This one with a $1 million price tag.

“With landslides, basically you can either drain them, buttress them or unload them,” said Steve Schultz, ODOT project manager. “We can't get down and get a buttress in because the end of the slide is clear to the bay. So, we unloaded it.”

And they did that by installing 567 geofoam blocks.

“It's new to us,” said Schultz. “The blocks are 1.8 pounds per cubic foot. The native soil weighs 120 to 140 pounds per cubic foot. The blocks are light and the soil is really heavy. The weight pushes on the slide. We have 40,797 cubic feet replaced with Styrofoam. The Styrofoam weighs 73,435 pounds and the native fill, at 130 pounds per cubic foot, is 5,303,610 pounds. We dug out the dirt and put in the blocks and reduced 5.2 million pounds.”

Crews first used excavators, loaders and dozers to clear out the slide debris, and hauled out 150 truckloads of soil. Then they lined the excavated site with drain rock. Next, laborers put the blocks – each one 2 ft. tall by 3 ft. wide by 12 ft. long and weighing 130 pounds — in place.

“They are pretty big blocks,” said Markus Schaas, ODOT assistant project manager. “Two laborers moved them into place and then they stacked them, and every 16 square feet, they put in a galvanized steel plate that has spikes on each side and locked all the blocks together.”

Schultz described it as looking like a truss plate.

“It works much better if you have a really flat starting foundation,” Schultz said. “All must be square vertically and horizontally. If one gets out of place, it can cascade. When they placed them, they stacked them like a haystack. The rows run in alternate directions.”

Once the blocks were in place, crews covered them with a gasoline resistant membrane to prevent the foam from melting. After that, the blocks were covered with 4 ft. of crushed rock and paved with asphalt.

The blocks were one part of a two-prong approach that also included installing a large trench drain just north of the geofoam to divert water away from the slide area.

“The Styrofoam is under the east bound land and under the fill slope,” Schaas said. “The subsurface drain runs underneath the westbound lane and that is to intercept ground water before it gets to the slide.”

Because the road is narrow, flaggers were used to keep the highway restricted to one lane. When traffic was heavy in both directions, 100 vehicles were released in each direction at a time, acting much like a traffic signal, said ODOT spokeswoman Angela Beers-Seydel. When traffic was heavy in only one direction, 100 vehicles were released from the heavy direction and then the light direction was cleared. ODOT tried different scenarios and found that plan worked best, she said.

The project, which began in mid-October, was completed in December.

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\