List Your Equipment For Free  /  Seller Login

Pennsylvania Turnpike's $425M Interchange Project on Schedule

Wed December 14, 2016 - Northeast Edition #25
Irwin Rapoport – CEG Correspondent


Crews placed concrete for the new Mill Creek Bridge foundations; excavated; and demolished existing mainline bridges at Durham Road and Route 413.
(Pennsylvania Turnpike Commission photo)
Crews placed concrete for the new Mill Creek Bridge foundations; excavated; and demolished existing mainline bridges at Durham Road and Route 413. (Pennsylvania Turnpike Commission photo)
Crews placed concrete for the new Mill Creek Bridge foundations; excavated; and demolished existing mainline bridges at Durham Road and Route 413.
(Pennsylvania Turnpike Commission photo) New bridge beams were installed for the Mill Creek structure and retaining walls were added to support future widening.
(Pennsylvania Turnpike Commission photo) There are three construction projects left to complete for Stage 1 of the Pennsylvania Turnpike Commission’s $425 million I-95 Interchange project.
(Pennsylvania Turnpike Commission photo) The TPC expects to have the work completed in late 2018.
(Pennsylvania Turnpike Commission photo) The project is the last piece of the Interstate network to be completed as defined under the Federal-Aid Highway Act of 1956.
(Pennsylvania Turnpike Commission photo) The work, which began in 2010, includes the construction of environmental mitigation sites; the replacement of five overhead bridges; new toll plaza facilities; flyover ramps; and highway widening.
(Pennsylvania Turnpike Commission photo) The projects completed are four bridges at Bensalem Boulevard, Richlieu Road, Ford Road, Galloway Road, and Bristol-Oxford Valley Road; I-95 Interchange stream mitigation; and the I-95 wetland mitigation site.
(Pennsylvania Turnpike Commission photo) The project includes the construction of sound barrier and retaining walls along both the eastbound and westbound turnpike.
(Pennsylvania Turnpike Commission photo) The goal is to have the western area of the project complete by July 2017.
(Pennsylvania Turnpike Commission photo) Pier substructures for the southbound I-95 flyover bridge are built and temporary paving was done on the northbound and southbound I-95 roadway.
(Pennsylvania Turnpike Commission photo) Crews placed concrete for the new Mill Creek Bridge foundations; excavated; and demolished existing mainline bridges at Durham Road and Route 413.
(Pennsylvania Turnpike Commission photo)

There are three construction projects left to complete for Stage 1 of the Pennsylvania Turnpike Commission's $425 million I-95 Interchange project in Bensalem and Bristol Townships in Bucks County. The TPC expects to have the work completed in late 2018.

The work, which began in 2010, includes the construction of environmental mitigation sites; the replacement of five overhead bridges; new toll plaza facilities — Neshaminy Falls toll plaza in Bensalem and a new Cashless Tolling Point (Delaware River Bridge toll plaza westbound); flyover ramps from I-95 North to the Eastbound Turnpike; highway widening (I-95 and I-276 movements); the Delaware Valley Interchange Connector Ramp reconstruction; and new at-grade intersection with Route 13 mainline.

The projects completed are four bridges at Bensalem Boulevard, Richlieu Road, Ford Road, Galloway Road, and Bristol-Oxford Valley Road; I-95 interchange stream mitigation; and the I-95 wetland mitigation site.

The project is the last piece of the interstate network to be completed as defined under the Federal-Aid Highway Act of 1956 and the first transportation project in Pennsylvania to be funded through the EB-5 visa program.

The work on Section D10 is being done by PKF Mark III Inc. Crews began in October 2014 and this section should be completed in the late fall of 2017. Gannett Fleming, Pennoni Associates and Rummel Klepper & Kahl were responsible for the design.

Crews from James D. Morrissey Inc. (JDM) started work on Section D20 last September. This portion of the interchange connection ($119 million) involves widening the existing I-95 between Neshaminy Creek and existing I-276. The work on this section is expected to be complete by 2019. Gannett Fleming, consultants and Rummel Klepper & Kahl designed the infrastructure.

The Turnpike is being widened from two lanes in each direction to three — a 2.5 mi. (4 km) stretch — between I-95 and the Delaware River Bridge. This includes components of the new Northbound I-95 "flyover" structure, which will connect I-95 northbound to I-276 eastbound and widens the road from three lanes in each direction to four.

The existing I-95 north of the Turnpike will be re-designated as I-295 in Pennsylvania and New Jersey with new signing installed as part of this project. Section D20 consists of widening and reconstruction of approximately 2 mi. (3.2 km) of existing I-95.

"The additional lanes are provided not only to safely connect the interstates," said Mark F. Raup, P.E., senior engineer project manager, "but to accommodate future traffic growth in the study area and the region. The primary goal of the overall project is to complete I-95 but there was no interchange between the I-95 and the Pa. Turnpike to make that connection, and we're doing that by using two existing highways the Pa. and New Jersey Turnpikes.

"Currently, people need to get off the highway and travel along signalized arterials to get from one highway to the other. Once the flyovers are in place, motorists from Philadelphia going over to New Jersey and making the return trip, will be able to stay on I-95.

"This is a benefit to the local community as there is a lot of traffic that uses the arterial roads that doesn't have to be there," he added. "It will be removed and hopefully the community will be able to regain the roads for economic development and easier local traffic."

The Turnpike mainline was constructed in the mid-1950s and the I-95 section was built in the mid-1960s.

"The highway lanes and bridges that we are reconstructing has pretty much reached the end of its service life," said Raup.

The lifespan of the new roads and bridges is more than 50 years.

The design did have to take into account environmental considerations based on an Environmental Impact Statement and Federal Record of Decision prepared between 1992-2003.

"There were a lot of commitments made with respect to mitigate the impact on the socio-economic community and natural and cultural resources in the area," said Raup. "The project is taking place in a first ring suburb of Philadelphia, but this area is right at the edge of the coastal plain and there are some sensitive environmental features that the agencies wound up being concerned about because many are some of the last remaining features of their kind in southeastern Pennsylvania."

Section D10

The project includes the replacement or construction of wider bridges over Durham Road, Route 413 and Mill Creek and replacement/reconstruction of the existing roadways; construction of sound barrier and retaining walls along both the eastbound and westbound turnpike due to widening of the existing roadway; new drainage systems; construction of basins for erosion control and storm water management; and Intelligent Transportation System facilities.

Following the completion of the prep work, the installation of erosion and sedimentation controls and sandbag cofferdam and relocation of Mill Creek began, along with the construction of basin M1 on the eastbound Pa. Turnpike.

Foundation piles for the northbound flyover bridge have been installed and trees were cleared at the east end for construction of new eastbound off ramp at Route 13. The rock embankment was constructed on the eastbound Turnpike, just east of Route 413.

Crews placed concrete for the new Mill Creek Bridge foundations; excavated; and demolished existing mainline bridges at Durham Road and Route 413. New bridge beams were installed for the Mill Creek structure and retaining walls were added to support future widening.

"Working adjacent to wetlands and the soils encountered in the area requiring additional undercutting and backfilling with stable embankment material," said Raup. "The project is essentially one two-mile long work area."

The goal is to have the western area of the project complete by July 2017.

Crews have removed about 225,000 cu. yds. (172,025 cu m) of material from the site. New materials include 124,000 tons (112,491 t) of bituminous pavement; 36,000 cu. yds. (27,524 cu m) of structural concrete; and 4.7 million lbs. (2.1 million kg) of structural steel.

"The contractor is recycling existing concrete and bituminous pavement," said Raup, "and using in certain areas for embankment widening."

Section D20

The work area ranges from the turnpike/I-95 interchange/I-95 south to PA 413. Construction includes a new 15-span bridge that will connect the newly designated I-95 into Philadelphia; retaining walls along I-95; sound barrier walls; installation of new drainage systems, construction of basins for erosion control and storm water management; replacement of signing and guide rail; installation of ITS facilities; and re-designation signing from Scudder Falls to Center City Philadelphia.

A main challenge for the design team dealt with a sanitary sewer that crosses I-95, which needs to be extended in both directions.

"This requires a substantial design in terms of a pumping effort," said Raup, who noted that the work on the sewer has been completed. "It was nothing extraordinary, but it was definitely something that had to be done as it was pumping up to seven million gallons per-day."

Pier substructures for the southbound I-95 flyover bridge are built and temporary paving was done on the northbound and southbound I-95 roadway. Crews cleared along southbound I-95 to provide for widening work zone; started the placement of new storm water drainage pipe along southbound Route 413 on ramp; and completed the jack/bore of 72 in. (183 cm) and 54 in. (137 cm) drainage pipe under I-95.

"The challenge of dealing with large volume of traffic on I-95 and the maintenance of an aged roadway surface during construction," said Raup, "and constantly monitoring the roadway surface and addressing issues as soon as noticed to avoid a more significant impact."

The major goals for the upcoming construction season are switch traffic to the next traffic stage to open the southbound collector distributor road by spring of 2017.

Crews removed 390,000 cu. yds. (298,176 cu m) of material. New materials include 168,000 sq. yds. (140,469 sq m) of concrete pavement; 18,000 cu. yds. (13,762 cu m) of structural concrete; and 4.4 million lbs. (2 million kg) of structural steel.

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Progress Continues On $250M Columbus LOT Project

Work Continues On Largest Project in NYSDOT History

OSHA Puts PPE for Women, Hard Hats On Its Radar

Case Introduces Limited Signature Edition Backhoe Loader for Iconic Presence On Job Site

Consider These Comfort, Performance Features When Selecting Your Next Compact Track Loader

Aerospace Hub Construction Starts

Vantage Selects Turner Construction Corp. for $2B Expansion Project

AES Ohio Powers Economic Development With Major Upgrades


 







39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085