List Your Equipment For Free  /  Seller Login

Phase I of SLC Airport's $3.6B Expansion Nears Completion

Tue July 30, 2019 - West Edition #16
Katherine Devlin – CEG Editorial Assistant


TRP aerial looking northwest June 29, 2019
TRP aerial looking northwest June 29, 2019
TRP aerial looking northwest June 29, 2019 Tower crane dismantling July 15, 2019 A worker dismantles the tower crane on July 15, 2019 The final concrete pour for the elevated roadway. Crews pour the final concrete for the elevated roadway on July 11, 2019 North Concourse looking northeast June 29, 2019 Garage roof steel erection June 4, 2019 Crane teardown May 17, 2019

Construction on Phase 1 of the new $3.6B Salt Lake City Airport has made significant progress in the past few months. Concrete pours, paving and steel erection have been highlights. Ground was broken for the new facilities in July 2014.

According to the airport's website, prior to the above-ground work, underground stone columns were installed to provide seismic stability and steel piles were installed to support the weight of the building.

A worker dismantles the tower crane on July 15, 2019

In May, scaffolding came down on The New SLC plaza, featuring a 45-ft. tall window curtain wall. Paving began at the arrivals terminal and concrete pours for the east pedestrian bridge were completed.

June saw steel erection completed for the Terminal building's expansion; the beginning of concrete pours for the sidewalks; and concrete being poured for the pedestrian walkway from the parking garage to the Gateway.

In July, crews poured the final section of the elevated roadway. This road is expected to ease congestion and will be used for dropping off passengers. Crews also began dismantling tower cranes over the complex's parking garage.

The project has had an impact on the local community to the tune of $5.5 billion. Approximately 2,000 jobs have been created. The first phase is due to open in 2020, with the overall project complete by 2025. CEG




Today's top stories

Progress Continues On $250M Columbus LOT Project

Work Continues On Largest Project in NYSDOT History

OSHA Puts PPE for Women, Hard Hats On Its Radar

Case Introduces Limited Signature Edition Backhoe Loader for Iconic Presence On Job Site

Consider These Comfort, Performance Features When Selecting Your Next Compact Track Loader

Aerospace Hub Construction Starts

VIDEO: PennDOT to Make $50M Upgrade to U.S. 119, Plans to Replace Old Bridge in Fayette County

Ohio University Announces Investment From Kokosing


 







39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085