List Your Equipment For Free  /  Seller Login

Pittsburgh's New Fern Hollow Bridge Nears Opening

Thu November 17, 2022 - Northeast Edition #24
Brenda Ruggiero – CEG Correspondent


Plans are to open the bridge before the end of the year and fully complete the 
project later in 2023.
(Photo courtesy of Robert M. Byrnes, PennDOT)
Plans are to open the bridge before the end of the year and fully complete the project later in 2023. (Photo courtesy of Robert M. Byrnes, PennDOT)
Plans are to open the bridge before the end of the year and fully complete the 
project later in 2023.
(Photo courtesy of Robert M. Byrnes, PennDOT) Another challenge was the protection of what is referred to as “the gatehouse,” a historic pavilion structure made of stone right at the corner of the bridge.
(Photo courtesy of Robert M. Byrnes, PennDOT) Based on cost and availability, pre-stressed concrete I-beams were chosen.
(Photo courtesy of Robert M. Byrnes, PennDOT) On the design side, PennDOT design project managers went through the process on a very accelerated schedule.
(Photo courtesy of Robert M. Byrnes, PennDOT) As the beams were being constructed, the designers were finalizing the columns and pier caps on top of the caisson foundations and designing the abutments.
(Photo courtesy of Robert M. Byrnes, PennDOT) The Pennsylvania Department of Transportation (PennDOT) continues to move to open a new bridge at the site of the Fern Hollow Bridge in Pittsburgh, Pa., less than a year after its collapse.
(Photo courtesy of Robert M. Byrnes, PennDOT) The contractor arranged for the rental of two large track cranes to erect the beams. The largest came in on more than 50 tractor trailer loads and the other one was on 25 tractor trailer loads.(Photo courtesy of Robert M. Byrnes, PennDOT) One of the biggest challenges was just the high-profile nature of the project.
(Photo courtesy of Robert M. Byrnes, PennDOT)

The Pennsylvania Department of Transportation (PennDOT) continues to move to open a new bridge at the site of the Fern Hollow Bridge in Pittsburgh, Pa., less than a year after its collapse.

The bridge on Forbes Avenue between Squirrel Hill and Point Breeze collapsed on Jan. 28, 2022. Under an emergency grant of $25.3 million from the federal Department of Transportation, PennDOT began work on Feb. 3. The contract was awarded to Swank Construction under the direction of Pete Douglas. Plans are to open the bridge before the end of the year and fully complete the project later in 2023.

The contract includes the bridge collapse demolition and new bridge design and construction.

Doug Thompson, principal assistant construction engineer, PennDOT District 11, said that early on, PennDOT offered to help the city and provide expertise.

"I guess they entered into a legal agreement in the first few days with the city so that PennDOT could take over the design and construction responsibilities for the project, to replace the bridge," he said.

Jason Zang, assistant district executive, construction, PennDOT District 11, said that they were also talking closely with FHWA in regard to how they could proceed as quickly as possible.

"They basically said what you want to do is pick a contractor and that's how we did it," he said. "So, we picked a contractor and we picked a consulting firm right out of the gate and that was I think day one or day two. That was right there after the collapse. In all PennDOT districts, the primary function is putting projects out to bid, so it is kind of our specialty of getting projects out to contract and to bid. None of us want to see that in our career and I hope we never have to see it again, but that bridge carries like 20,000 vehicles a day, I think. The goal was to get the bridge replaced as quickly as possible. That's always been the goal."

Thompson reported in late September that the collapse was first cleaned up, restored and wasted, and a concurrent design and construction was begun.

"Actually, the design started about a month before we could start construction because we had to have some plans for the foundations prepared, so right out of the gate they did core borings and started on their foundation design," he said. "Pretty quickly out of the gate, we narrowed down the construction type. We basically determined the width of the bridge — the bridge needed to be the same that was out there now due to the right of way that the city had through a park and everything."

Once the span configuration was determined, the contractor worked quickly to determine the most quickly available structure type: steel or concrete. Based on cost and availability, pre-stressed concrete I-beams were chosen.

"The big driving factor in the schedule was when could the beams be delivered," Zang said. "We took that date based on when the beams could be delivered and we backed into April … so we weren't out there just pitter-pattering around. We wanted to be efficient, so there was some time there where there wasn't much going on on site, but there was a lot of the design work going on. But we based the groundbreaking on when we started our foundation. It was all based on when the beams would show up."

As the beams were being constructed, the designers were finalizing the columns and pier caps on top of the caisson foundations and designing the abutments. The beams started arriving in on July 25.

"There were some challenges associated with that," Zang said. "They could deliver two beams a day. Once they came into Pittsburgh, the city coordinated and escorted the beams through the congested areas of Oakland. Oakland's a pretty busy area, so they escorted the beams through Oakland, we got them in and erected two a day for the first two spans. So, we had the first 14 beams erected, two a day, and then they brought in span three from a different direction, not through Pittsburgh but from the eastern side of Pittsburgh through Monroeville and they backed them up the street. That drew a lot of attention when they closed the street and backed them up Braddock Avenue and onto the site."

Next, the contractor arranged for the rental of two large track cranes to erect the beams. The largest came in on more than 50 tractor trailer loads and the other one was on 25 tractor trailer loads.

"They erected the Span 2 beams with the large crane that was sitting up on the abutment," Thompson said. "They erected those Span 2 beams onto Span One and then the next day they had a smaller crane, although it was a very large crane. And they had a smaller crane sitting down in the valley. Then they did a two-crane lift — a dual lift — and one crane picked either end of it while it was sitting on Span One. Then, they both lifted it into position in Span 2 because there just wasn't a crane available with the radius and capacity to lift the beam from behind the abutment clear out to the center span."

Concerning challenges, Thompson spoke about the effort involved to quickly, concurrently design and construct a bridge and literally start construction when you only have the foundation plan to prove.

"Another big challenge I personally have dealt with, like Jason [Zang] said earlier, we're really good at developing designs and preparing a bid package and putting projects out to bid and contractors bid on a project and give us a price for a bridge," he said. "But [with] this one, there was nothing to bid."

Instead, the contractor and designer were selected and then prices were negotiated. As the bridge was being designed, the foundation plans were approved, so that cost was negotiated.

"We were negotiating the cost piece by piece, which is pretty challenging, but we're getting through it," Thompson said.

On the design side, he noted that PennDOT design project managers went through the process on a very accelerated schedule.

"Hats off to the designers," Thompson said. "We still have to follow all the design processes even though there's emergency procedures in place. So, they've done a great job with doing what they can to still have the public involvement for all the environmental processes and getting some public involvement on the art aspects of the bridge. That's challenging just to expeditiously get public involvement while at the same time hurry up and build the bridge."

Working with utilities also has been a process, including relocation and a 16-in. gas line that was severed during the collapse.

Another challenge noted by Thompson was the protection of what is referred to as "the gatehouse," a historic pavilion structure made of stone right at the corner of the bridge.

"We had to figure out how to protect that while we excavated down," he said. "That gatehouse was a challenge that we worked through."

The structure was 2 ft. from vertical construction and a temporary shoring wall was built in front of it.

Thompson reported that plans call for a polyester polymer concrete overlay to be incorporated into the project to protect the concrete. This is something new to Pennsylvania.

He also noted that the columns on the bridge will have form liners to make them look similar to the cut sandstone on the original bridge foundations. They will be stained to match some of the existing sandstone abutments that were maintained on the bridge.

"We looked around to see what aspects of the old bridge did we want to try to leave around, such as the old abutments just to maybe tell the story of what was there in the past," Thompson said. "We decided to leave the old foundations from the K frames in place as well and it was thought that possibly somebody might want to try to put a plaque up or something and tell the story of the bridge collapse and have those old foundations there potentially for that use."

According to Zang, one of the biggest challenges was just the high-profile nature of the project.

"Because the bridge collapsed and it had national attention; it was the day President Biden happened to be in Pittsburgh," he said. "So …everyone's looking at it and we've been very careful and very cautious with what we're telling the public. We're keeping a close eye on the schedule and the team has really been working hard. Everything's overlapping. This is completely different than what we're typically doing in Pennsylvania and it is allowing the project to go a lot quicker because you have construction happening while design is happening. It's not linear like every other project.

Smaller equipment such as excavators, dozers and small cranes are owned by the contractor, but large cranes were rented.

Major subcontractors for the project include PENNSTRESS of Roaring Springs, Pa.; Weatherspoon and Williams LLC of Coraopolis, Pa., for beams; Hall Industries, Elwood City, Pa., for bridge railing; and HDR of Pittsburgh, Pa., for the design.

The new bridge includes 21 beams, 150 ft. long and approximately 8 ft. tall and more than 1,000 cu. yds. of concrete on the deck. The bridge is 100 ft. high over the trail.

Traffic was detoured on the day of the collapse and has remained so throughout the project. This also includes pedestrians in the area. CEG


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.96118 \\ -82.99879 \\ Columbus \\ OH