List Your Equipment For Free  /  Seller Login

Population Growth Sparks $340M Treasure Valley Project

Tue August 27, 2019 - West Edition #18
Lori Tobias – CEG Correspondent


The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state.
The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state.
The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state. The primary work will involve widening the Interstate, adding or modifying existing bridges, overpasses and interchanges. More than 31 million trips occur on I-84, with two-thirds of those taking place between Ada and Canyon Counties. The project is a continuation of an expansion project that got underway a decade ago, but was halted during the recession. Work was able to resume after the state legislature gave IDT the go-ahead to pursue bonding against future federal government funding through the Grant Anticipation Revenue Vehicle (GARV). The Interstate is the primary commuter route, and also an important freight route and the lifeblood of Idaho’s agriculture community.  The work is happening over 11 miles of I-84 in Ada and Canyon Counties, an area known as the Treasure Valley, the population hub of the state. The overall project is expected to continue through 2021 and 2022.

The Idaho Transportation Department (ITD) has kicked off a $340 million project on the largest highway in the state. The work is happening over 11 miles of I-84 in Ada and Canyon Counties, an area known as the Treasure Valley, the population hub of the state. It is the fastest growing area in Idaho, which is the largest growing state in the United States.

More than 31 million trips occur on I-84, with two-thirds of those taking place between Ada and Canyon Counties.

"It's all about size," said Jake Melder, ITD spokesman. "I-84 is just not big enough. Idaho is experiencing unprecedented growth and we're now finding this Interstate is insufficient to carry the demands we have."

The Interstate is the primary commuter route, and also an important freight route and the lifeblood of Idaho's agriculture community. The primary work will involve widening the Interstate, adding or modifying existing bridges, overpasses and interchanges.

"There is going to be one at Northside that is kind of a superstructure," Melder said. "That's going to be the biggest construction package we put out, and it should be going out in the coming weeks.

The overall project includes:

Karcher Overpass Specs

  • 276-ft., 7-in. long bridge
  • 43-ft. wide
  • 17-ft. minimum clearance of I-84 below

Four interchanges:

  • Franklin Boulevard Interchange (IC) (Nampa) — minor ramp modifications
  • Northside Blvd IC — complete rebuild from diamond configuration to single point urban interchange (SPUI)
  • Karcher/Midland IC — ramp modifications and add a SB lane on bridge
  • Franklin Road IC (Caldwell) — minor ramp modifications

Major bridges over I-84:

  • Karcher Road Overpass — complete replacement to allow additional I-84 lanes
  • Middleton Road Overpass — complete replacement to allow additional I-84 lanes
  • Ustick Road Overpass — complete replacement to allow additional I-84 lanes

Major Bridges on I-84 (referenced facilities run under the Interstate):

  • Union Pacific Railroad (east of Northside IC)
  • Mason Creek (west of Franklin Blvd IC)
  • Linden Street (east of Franklin Road IC)

The project is a continuation of an expansion project that got underway a decade ago, but was halted during the recession. Work was able to resume after the state legislature gave IDT the go-ahead to pursue bonding against future federal government funding through the Grant Anticipation Revenue Vehicle (GARV).

"That mechanism, we think, is going to be a wiser use of taxpayer funds because construction costs are on the rise," Melder said. "We've been able to get an excellent rate on our bonds and that means getting the work done sooner and getting the work done cheaper. Improved transportation means an improved economy. It's an excellent way of utilizing taxpayer funds."

One of the big challenges facing work crews is that the Interstate is already congested and at capacity. But ITD has made a commitment to not close lanes during commuting hours. To that end, crews worked last year to create extra wide shoulders where traffic can be shifted during construction.

"A lot of these bridges were built in the ‘60s and most don't accommodate the additional lanes underneath them, so we're going to be adding an additional travel lane and an auxiliary lane," Melder said. "Right now, with the bridge work that is being done and, again why we have these expanded shoulders, we're able to shift the lanes of travels. The abutment work on ends of bridges is not impactful on traffic. But we do have to have overnight closures, and when we're setting the bridge deck, we will have to close traffic because we don't want to be setting over traffic."

The overall project is expected to continue through 2021 and 2022. CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\