Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
Thu August 12, 2021 - Northeast Edition #17
Some highway construction projects extend beyond the horizon, with right-of-way and paving crews transforming a whole countryside. In Philadelphia, the major reconstruction of an urban segment of Interstate 95 is measured in linear feet. Yet, the relatively short stretch of roadway encompasses a wide range of construction tasks. These include demolishing old viaducts, replacement of city streets and off-and-on ramps, drilling micropiles and laying cobblestone walkways.
"There are all different kinds of work on this job," said Rick Foster, executive vice president of heavy highway civil contractor James J. Anderson Construction Company. "It pretty much has a little bit of everything. Actually due to the size of the project, a lot of everything. It has been a challenge."
The project is the $312 million fifth phase of a two-decades-long project to upgrade I-95 from the city's Allegheny Avenue south to Frankford Avenue The current work area —called GR4 — is adjacent to Delaware River frontage and principally involves completely redoing the interstate's southbound lanes, viaduct and interchanges.
Even before starting demolition of the old southbound lanes and structures serving them, pier foundation work for the new traffic ways proceeded.
"We began installing micropiles while the GR3 stage of the work was still being constructed," Foster said. "Why micropiles? The GR3 phase used a lot of H-beam piles and nearby residents were telling us, ‘I hope you're not going to do that on the southbound lanes.'"
The Pennsylvania Department of Transportation (PennDOT) had anticipated such concerns and designed micropiles for southbound lanes nearer residential areas. H-beam piles were driven into the ground by repeated blows from a pile-driving hammer, of course, whereas micropiles are drilled through the waterfront-area subsoil into bedrock. It is a slower but quieter and a nearly vibration-free operation.
But in addition to being slower, the micropile installation posed other challenges, too, which the executive vice president described this way: "How do you efficiently drill 70-foot-deep piles under an existing structure with low-overhead clearance?"
That challenge was handed to Nicholson Construction Company. The subcontractor's crews met the challenge by drilling 10-in.-in-diameter micropiles both vertical and battered using a combination of low overhead track drills and excavator-mounted drills. The drilled depth ranged from 40 to 80 ft. In all, some 115,000 linear ft. of micropiles were installed. In non-residential GR4 areas, another 22,000 ft. of H-piles were driven into the ground.
As the foundation work progressed, work started happening above ground, too. A 1.5-mi. viaduct carrying traffic over local streets is being entirely reconstructed and an interchange with Girard Avenue realigned and constructed. The scale of the project is evident in the volume of materials consumed: 6,750 tons of structural steel and another 5,650 tons of reinforcing steel, 23,500 linear feet of precast beams and almost 50,000 cu. yds. of concrete.
The final mainline pour of a bridge section approaching the Girard Avenue off ramp shows the complexity of some of the work. As explained by Bob Crawford, Anderson's chief engineer and project manager, the bridge taxed the company's engineering expertise. The bridge deck varied in width from 120 to 150 ft. and incorporated different slopes.
"The problem was that the width was about the limit the GOMACO bridge deck finishers can go," Crawford said. "We decided on a second mid-rail and poured with two different machines. We had five GOMACO bridge deck pavers on the project, so we had access to them."
It was a 400-cu.-yd. concrete pour with SJA Construction supplying the concrete. Conveniently, SJA's concrete plant is very near the work area. Just as conveniently, less than a mile away from I-95 on Allegheny Avenue is Anderson-owned Riverside Materials, which supplied the project with new asphalt and recycled products. The proximity of the two plants worked out well for everyone. "We were in a very good spot to do the job," Foster said.
The site has been a construction beehive, with machinery rumbling and rolling. A new off-ramp and a bridge serving Aramingo Avenue are nearing completion. Elsewhere, transparent sound wall panels are going up to lessen traffic noises for nearby residential neighborhoods. James J. Anderson Construction Company's equipment on site includes small Komatsu dozers and Volvo 235 and Cat 330 excavators. Sound walls are being erected with Grove 60 to 90 ton hydraulic cranes. 37 meter, 49 meter and 58 meter Schwing truck-mounted pumps provided by B. Pietrini & Sons, deliver concrete in hard-to-reach applications situations. GOMACO pavers are laying down new traffic lanes.
Subcontractors are numerous and include High Steel Structures doing steel fabrication and erection with Structural Services Inc. erecting the precast beams manufactured by Northeast Precast Products, installing stay-in-place forms and shooting studs. Re-Steel supplied the reinforcing steel, with L&R Construction placing the reinforcing steel, J. Fletcher Creamer & Son erecting sign structures, Penhall Company performing concrete grinding work, Roma Concrete building curbs and sidewalks and Menard constructing continuous modular columns.
Column cap forms were erected with a Grove 275 hydraulic crane and steel and concrete girders were erected utilizing two Liebherr 200-ton crawler hydraulic cranes working in tandem.
Underneath the northbound and southbound viaduct and ramps is a whole other world of labor. The area is being transformed with cobblestone and blue-dyed-concrete, public parking lots, a shared use path interconnecting roadways, rock-lined stormwater retention ponds and green spaces. Kuharchik Construction installed LED lighting that will illuminate it all at night. Olivieri and Associates has a significant portion of the hardscaping subcontract and Green Valley is performing the landscape work.
"Between now and June of next year, there will be a lot of workers on their knees working cobblestones and pavers and colored concrete," Foster said of the finish work.
But before any of that occurs, the whole area had to be brought to grade.
"We try to use a lot of GPS in grading," Foster said. "A lot of this area is under structures, so it was not your typical satellite GPS."
Numerous GPS stations were involved. A team of engineers coordinated placement of transits and fitted every structural column of the viaduct with a control point.
"The transit operator can move 50 feet and hit another control and start transmitting from it to the paver in the midst of paving. It's pretty wild," Foster said.
The area underneath the viaduct has height clearances ranging from 30 ft. to barely high enough to walk under. Foster said working around so many pier caps and columns is "tedious" and challenging. Some $40 million of the contract is expended on just the underneath part of the work. "It's a whole job in itself," he said.
A 12-in.-by-12-in. concrete edger curb separates different sections of the area beneath the viaduct.
"We took on the challenge of slipforming them using a GOMACO Xtreme Slipform machine configured in 3 track mode," Crawford said. "It was a 100 percent localized GPS job."
The whole project area has been bedeviled by problems associated with working in an urban environment including "a very large homeless population. But working together with an excellent PennDOT resident engineer and his staff, we've managed to keep things moving."Foster said.
Other contemporary issues affecting the multi-year project were the pandemic, which affected workday and labor force issues, and imposition of steel tariffs that sent material prices "through the roof." All in all, however, the I-95 project has progressed without a hitch for the Philadelphia contractor.
The company was founded in 1981 by Jim Anderson, a milling superintendent who decided to go out on his own. The company added asphalt paving and in 1990 acquired Riverside Materials, which today is a 500-ton high-production drum asphalt plant and recycling operation. To complete its vertical business structure, Anderson acquired Dyer Quarry, which supplies aggregates to both Riverside and other customers. Anderson employs in excess of 400.
In 2008, the company formed its structure division.
"Bob [Crawford] was the first person hired," Foster said of his chief engineer. The formation of the structure division completed Anderson's vision of a vertically integrated large heavy highway contractor capable of reconstructing Philadelphia's highways through self-supply of construction materials and self-performance of all civil and bridge work in-house.
The GR4 contract will be completed next June. Everything atop the viaduct will be finished by year's end, according to Foster, including median work that will proceed after southbound lanes are opened. "Hardscaping underneath will take the extra time."
The SR95 GR4 project was a joint effort between JJA, PennDOT, Construction Manager Hill International, lead designer AECOM as well as Gannett Fleming and Dawood Engineering.
Two final phases of the 20-year overhaul of the Girard portion of the interstate urban interstate will extend I-95 reconstruction work South of the highway's intersection with Interstate 676. Those culminating stages of the project are scheduled to be finished by 2029. CEG
Craig Mongeau has been Construction Equipment Guide’s editor in chief for the past 21-plus years. He directly manages CEG’s Northeast and Southeast editions (which includes New England, Georgia and Alabama state supplements); Superintendent’s Profile; Crane Guide; Northeast and Southeast-based anniversary magazines; and special event publications. He also oversees CEG’s Midwest and Western Editions as well as all CEG website content.
A Hofstra University graduate, Craig began his publishing career as a staff writer for local Southeast Pennsylvania newspapers. He then became an associate editor and book editor of Springhouse Corporation, a Pennsylvania-based medical publishing house and then worked as a managing editor of Rockhill Communications, based in Bala Cynwyd, Pa., where he created and managed content for a national Voluntary Hospital Association website.
Originally from Pittsfield, Mass., Craig has lived in North Wales, Pa., for the past 27 years. He has been married to his wife, Hillary, whom he met in college, since 1998 and together, they have two daughters, Jolie and Aubrie.