List Your Equipment For Free  /  Seller Login

RedStone Uses Slide Rail System to Install Wet Well

Fri July 14, 2017 - Southeast Edition #15
James McRay


“We only had about a 25 ft. radius of space around where the wet-well was going to go, so we didn’t have any room for sloping or benching,” said RedStone’s Kurt Cosse. “Riggs happened to have a Slide Rail System that we needed and everything kind of fell into place.”
“We only had about a 25 ft. radius of space around where the wet-well was going to go, so we didn’t have any room for sloping or benching,” said RedStone’s Kurt Cosse. “Riggs happened to have a Slide Rail System that we needed and everything kind of fell into place.”
“We only had about a 25 ft. radius of space around where the wet-well was going to go, so we didn’t have any room for sloping or benching,” said RedStone’s Kurt Cosse. “Riggs happened to have a Slide Rail System that we needed and everything kind of fell into place.” “When I arrived out on the Red Stone job site I was very impressed from the get-go,” said Riggs CAT’s Josh Clark. “Everything was neat and organized, all the Slide Rail components were set out ready to install.”

Recently, contractor RedStone Construction Group was low-bidder to install a sanitary sewer wet well for North Little Rock (Arkansas) Wastewater. The 25 ft. tall, 8 ft. diameter fiberglass wet well was installed along 10th Street in North Little Rock.

The installation of a pre-cast structure with sewer tie-in was really nothing new for RedStone. However, the depth of the excavation and its proximity to the Arkansas River presented a new wrinkle for the veteran underground utility crew. Plus, the excavation site was packed into a very small working area.

“We only had about a 25 foot radius of space around where the wet-well was going to go, so we didn't have any room for sloping or benching,” said Kurt Cosse, RedStone's project supervisor. “We knew we needed some type of non-traditional shoring system that would allow us to minimize the impact of the excavation area,” he said.

Contractor Calls on Little Rock's Riggs CAT for Shoring Equipment

RedStone turned to local heavy equipment dealer Riggs CAT for possible solutions to its unique shoring challenge.

“RedStone came to us and we looked at their project parameters and saw that they had a really tight confined area that they were going to put the lift station in,” said Josh Clark, Riggs' rental operations coordinator. “So they asked us, what options do you have for shoring and we were able to show them an Efficiency Production slide rail system.”

“We've worked with Riggs pretty much since we've been in business, they've always been there for us,” said Cosse. “Just recently, Riggs has got into the trench safety rental business and they happened to have this shoring system that we needed and everything kind of fell into place from there. It's just a good match.”

Efficiency Production Slide Rail System Makes Debut in Arkansas

Efficiency Production's universal slide rail system is a component shoring system comprised of steel panels — similar to trench shield sidewalls — and vertical steel posts. When installed, the versatile system creates a safe, obstruction-free shored excavation, according to the manufacturer.

“From the get-go, all the parts were right and what we needed,” Cosse said. “On previous jobs we've had problems with shoring material not being the correct one, or not showing up at all. But from day one when we got the slide rail system, everything came that was required to install it.”

Efficiency Production's On-Site Shoring Specialist Impresses All

Both Cosse and Clark were very impressed with Efficiency's Shoring Specialist, Dan Meredith, who provided factory-direct installation assistance.

“Dan was competent and knew exactly what he was doing,” said Cosse. “He had very good patience and was a very good teacher. By the end of just one day, our crew could install the slide rail system by themselves.”

Meredith is part of Efficiency Production's special operations shoring division.

“It was great working with both Riggs CAT and RedStone, three different companies coming together for a common objective,” Meredith said.

Clark said, “I observed how Dan worked with and handled the crew and I was very impressed with him. He interacted with RedStone's crew to make the slide rail go into the ground effectively and efficiently, but he also showed respect to those professionals that were there with Red Stone. It takes a special person to blend into a crew like that and Dan did that seamlessly,” Clark concluded.

Installation Takes Half the Time With Efficiency Slide Rail System and Installer

Slide Rail is installed by sliding the steel panels into integrated rails on vertical posts and then pushing the panels and posts incrementally down to grade as the pit is dug.

“It took about a day to install the system which was half the time we thought it would take,” said Cosse. “I think that if we'd used another type of shoring or didn't have Dan on site, it could have taken twice as long.”

RedStone rented from Riggs the slide rail equipment to shore a 14 by 14 ft. excavation, 20 ft. deep. It installed the system with a Cat 330F and Cat 323F excavators, plus a Cat frontloader.

RedStone Construction Group has been serving Arkansas for more than 35 years, offering a wide range of services including excavation and earthwork, underground utilities, concrete and asphalt paving and repairs. For more information, visit www.redstone-cg.com.

For more information about Riggs CAT, visit www.riggscat.com.

For more information about Efficiency Production, visit www.efficiencyproduction.com.

James McRay is the director of marketing and media of Efficiency Production Inc. He can be reached at 800/552-8800; [email protected]




Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\