List Your Equipment For Free  /  Seller Login

Saying Goodbye to Bertha

The tunneling machine was used to carve a 1.7-mi. tunnel beneath the city of Seattle, a task that was begun in April 2013.

Wed July 05, 2017 - West Edition #14
Lori Tobias


In this April 2017 photo, tunnel workers pose with the SR 99 tunneling machine after Bertha moved into the disassembly pit near Seattle Center.
(WSDOT photo)
In this April 2017 photo, tunnel workers pose with the SR 99 tunneling machine after Bertha moved into the disassembly pit near Seattle Center. (WSDOT photo)
In this April 2017 photo, tunnel workers pose with the SR 99 tunneling machine after Bertha moved into the disassembly pit near Seattle Center.
(WSDOT photo) In this May 2017 photo, a piece of the SR 99 tunneling machine’s cutterhead, weighing 99,000 lbs., awaits a trip to a metal recycling yard. Crews working for Seattle Tunnel Partners are removing the cutterhead one piece at a time inside the disassembly pit near Seattle Center.
(WSDOT photo)
 Crews use cutting torches to disassemble a section of the SR 99 tunneling machine’s trailing gear inside the tunnel in Seattle.
(WSDOT photo)
 In this June 2017 photo, disassembly is revealing the complex inner workings of the machine that completed a 9,270-ft. tunnel beneath Seattle this spring.
(WSDOT photo) Crews clean the face of Bertha, the SR 99 tunneling machine, a few days after the five-story-tall machine completed its 9,270-foot journey beneath Seattle.
Crews clean the face of Bertha, the SR 99 tunneling machine, a few days after the five-story-tall machine completed its 9,270-foot journey beneath Seattle.
(WSDOT photo)
 A look at Bertha, the SR 99 tunneling machine, in the pit near the Space Needle where she ended her 9,270-ft. journey beneath Seattle. Crews can be seen cleaning the massive machine’s cutterhead.
(WSDOT photo) Crews working for Seattle Tunnel Partners have started taking apart the conveyor system that moved tunnel spoils from Bertha, the SR 99 tunneling machine, to barges docked on Terminal 46 on the Seattle waterfront. 
(WSDOT photo) These spools, sitting on Terminal 46 in Seattle, are part of the conveyor belt used to carry spoils out of Bertha, the SR 99 tunneling machine. 
(WSDOT photo) This April 2017 photo shows Bertha, the SR 99 tunneling machine, parked in her final resting spot within the disassembly pit near Seattle Center.
(WSDOT photo)
 In this May 2017 photo, welders working for Seattle Tunnel Partner cut a section of the SR 99 tunneling machine’s cutterhead in preparation for its removal from the disassembly pit near Seattle Center.
(WSDOT photo) Inside the SR 99 tunnel, welders working for Seattle Tunnel Partner disassemble the SR 99 tunneling machine’s trailing gear.
Inside the SR 99 tunnel, welders working for Seattle Tunnel Partner disassemble the SR 99 tunneling machine’s trailing gear.
Inside the SR 99 tunnel, welders working for Seattle Tunnel Partner disassemble the SR 99 tunneling machine’s trailing gear.
(WSDOT photo)
 This May 2017 photo shows crews’ progress on removing the SR 99 tunneling machine’s cylindrical steel shield inside the disassembly pit near Seattle Center. This view looks north, with the cutterhead at the machine’s far end, beneath the small rain canopy.
(WSDOT photo)

Efforts in Seattle to dismantle the custom-made tunneling machine fondly dubbed “Bertha” are proceeding as planned with completion on schedule for September.

The tunneling machine was used to carve a 1.7-mi. tunnel beneath the city of Seattle, a task that was begun in April 2013. Four years later, on April 4, the 8,000 ton, five-story-tall machine broke into daylight 64 years to the day after the Alaskan Way Viaduct first opened to traffic. The tunnel project will move a 2-mi. section of SR 99 underground when it wraps up in early 2019. Crews will then demolish the viaduct, clearing the way for the city's new waterfront.

Work to dismantle Bertha began in May after crews moved it into place in the disassembly pit.

“Frontier-Kemper is dismantling the machine from two locations,” said Chris Dixon, project manager of tunnel contractor Seattle Tunnel Partners.

“The most visible is inside the north retrieval or disassembly pit, where they used powerful torches to slice and lift most of the 950-ton cutterhead. As of [mid-June], almost all of the shield protecting the front third of the machine has been cut and lifted. A 400-ton crawler crane has proven more than capable of lifting the heaviest pieces, which weighed more than 100 tons.

“Inside the tunnel, another team of workers is cutting and removing several hundred feet of trailing gear — all of which supported the tunnel operations. These pieces are then lifted with a smaller crane inside the tunnel and trucked out through the south end, near Seattle's stadiums. Frontier-Kemper is working six days/week, 20 hours a day with 50 workers.”

Hitachi Zosen, the manufacturer and owner of the tunneling machine, decides which parts will be recycled, refurbished and/or reused. The cutterhead could not be reused as it had to be cut into much smaller pieces and lifted, Dixon said, noting that Hitachi Zosen sent most of the cutterhead to Seattle Iron and Metals for recycling. The firm also gave the Port of Seattle two pieces of the cutterhead for the Port to use for display purposes later.

The work has gone largely as expected, Dixon said, with workers adjusting the dismantling process as needed.

“The dedication and commitment of everyone on the Seattle Tunnel Partners team has been exceptional, and we wouldn't be at this milestone without the hard work of our crews,” Dixon said earlier this year when Bertha emerged into daylight. “We look forward to continuing this outstanding progress through project completion.”

The project has not always gone so smoothly. In December 2013, work on the tunnel came to halt after high temperatures were registered on the tunneling machine. A little over 1,000 ft. had been excavated at the time. It was determined there was damage to the seal system on the machine. The manufacturer, Hitachi Zosen, chose to repair the machine from the surface, requiring construction of an 80-ft. wide, 120-ft.-deep access pit in a work zone west of the Alaskan Way Viaduct. Between March and August 2015, Hitachi Zosen installed a re-designed seal system and made additional repairs to the machine, then lowered the front end back into the ground. In December 2015, STP refilled the access pit and again began tunneling.

It remains unclear how the machine was damaged.

“It is the contractor's claim that a hollow, 8-inch steel well casing caused the damage to the tunneling machine,” said Laura Newborn, spokeswoman of the Washington Department of Transportation. “WSDOT disagrees with the contractor's assertion that the pipe caused the damage. The contractor paid for the repairs and has requested reimbursement.

What caused the damage is a matter of litigation.”

STP still has significant work to complete before the tunnel opens, said Newborn.

“Crews must finish building the double-deck highway within the circular walls that were built by crews inside the tunneling machine. Mechanical and electrical systems, plumbing and safety features also must be installed.

“Even as workers are installing these systems, crews will begin the extensive task of testing and commissioning the tunnel to ensure it's ready for traffic,” Newborn said.

Inspectors will individually test more than 8,500 separate components before testing each of the tunnel's various systems as a whole.

Over the next several years, the city of Seattle's Waterfront Seattle project will build new public space and a surface boulevard in the place of the double-deck viaduct, which is scheduled for demolition in 2019.

Bertha's Journey

  • Breakthrough date: April 4, 2017
  • Distance tunneled: 9,270 ft.
  • Tunnel rings built: 1,426
  • Soil extracted from beneath Seattle: 850,000 cu. yds.
  • Lowest point relative to surface: 215 ft. (near First Avenue and Virginia Street)
  • Lowest point relative to sea level: 155 ft. (near First Avenue and Madison Street)

CEG


Lori Tobias

Lori Tobias is a journalist of more years than she cares to count, most recently as a staff writer for The Oregonian and previously as a columnist and features writer for the Rocky Mountain News. She is the author of the memoir, Storm Beat - A Journalist Reports from the Oregon Coast, and the novel Wander, winner of the Nancy Pearl Literary Award in 2017. She has freelanced for numerous publications, including The New York Times, The Denver Post, Alaska Airlines in-flight, Natural Home, Spotlight Germany, Vegetarian Times and the Miami Herald. She is an avid reader, enjoys kayaking, traveling and exploring the Oregon Coast where she lives with her husband Chan and rescue pups, Gus and Lily.


Read more from Lori Tobias here.





Today's top stories

Florida's Sarasota Bradenton International Airport Sees $105M Terminal Expansion

Louisville Pump Station Receives $230M Update

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

SISO Air, InTerra Form Strategic Reseller Agreement

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Balfour Beatty's Carolinas Operations Selected for Over $36M in Special Project Works

Caterpillar to Spotlight 'Next 100 Years' at CES 2025

Liebherr to Exhibit at World of Concrete 2025


 







\\ \\ \\