Forward momentum continued for the Hudson Tunnel Project during the fourth week of January as the Gateway Development Commission (GDC), which is managing what has been described as the nation's most critical infrastructure project, announced a major next step.
GDC identified its shortlist of qualified construction teams who will receive an invitation to submit plans in response to a Request for Proposals (RFP) for a design-build contractor to perform final design, construction and other related work for the tunnel on Manhattan's West Side.
NJBIZ noted Jan. 23 that the trio of joint ventures were among those that submitted a Statement of Qualifications (SOQ) in December in response to a Request for Qualifications (RFQ) issued by GDC.
The teams are:
The Hudson Tunnel Project has three major components, according to the GDC:
These three components will improve reliability, resiliency, and redundancy for hundreds of thousands of daily passengers who travel across the Hudson River and allow for much-needed repairs on an essential stretch of the Northeast Corridor.
Upon completion of the Hudson Tunnel Project, four tracks (two in the new Hudson River Tunnel and two in the North River Tunnel) will be available between New Jersey and New York under the Hudson River and allow for operational flexibility and redundancy for Amtrak and NJ TRANSIT rail operations to maintain current capacity levels.
NJBIZ learned that construction on the Hudson Tunnel project is expected to get under way later this year and continue through mid- to late 2029.
When that occurs, the first phase of the effort will include two parallel tunnels extending from just west of Manhattan Bulkhead, below 12th Avenue and to the 12th Avenue shaft. In addition, the proposal also calls for a second pair of parallel tunnels running from the that tunnel shaft to the Hudson Yards concrete casing below 30th Street.
According to the GDC, the tunnel will then continue through the foundation of the Manhattan bulkhead below the river bottom and continue about 45 ft. below the surface and underneath Hudson River Park and 12th Avenue, beneath the block between West 29th and West 30th streets on the west side of 12th Avenue, and beneath West 30th Street.
On the north side of West 30th Street, the alignment meets the concrete casing, before continuing beneath 10th Avenue to a tunnel portal to the east, before finally connecting to Penn Station.
By constructing the Hudson Tunnel Project, rail users also will be provided with a resilient regional and national rail network, and in doing so, substantial social, economic and environmental benefits will come to the New York-New Jersey metropolitan area. They will likely include:
This latest development builds on other previous ones, which NJBIZ reported on, such as the start of construction on both the New Jersey and New York sides of the Hudson River as well as a recap of 2023 and a look at what is in store for the project in 2024 from GDC Chief Executive Officer Kris Kolluri.
"All of us at GDC are working day in, day out to keep the momentum going on this project," he told NJBIZ. "We are thrilled to have a strong slate of shortlisted firms who will bring that energy to this critical and challenging phase of work on the Hudson Tunnel Project."