List Your Equipment For Free  /  Seller Login

South Coast Rail Program Reaches Phase 1 Milestones

Thu May 09, 2019 - Northeast Edition #10
MassDOT


“Providing rail service between the South Coast and Boston will increase access to economic opportunities in both regions,” said Gov. Charlie Baker.
“Providing rail service between the South Coast and Boston will increase access to economic opportunities in both regions,” said Gov. Charlie Baker.

MassDOT and the MBTA are announcing that the South Coast Rail Program has reached two critical Phase 1 milestones: a finance plan is complete and will be fully funded in the Commonwealth's Capital Investment Plan and the U.S. Army Corps of Engineers (USACE) has approved the final federal permit required for the program to advance. Meanwhile, early action steps are underway including infrastructure work and the acquisition of land for stations.

"Providing rail service between the South Coast and Boston will increase access to economic opportunities in both regions," said Gov. Charlie Baker. "After decades of promised service, today's announcement moves the project further than it's ever been before, and our administration is proud to continue advancing South Coast Rail."

"Residents in southeastern Massachusetts deserve reliable and affordable commuter rail access to Boston, and MassDOT and the MBTA have completed critical steps to make this a reality," said Lt. Gov. Karyn Polito. "The administration will continue to work with local partners throughout the project."

"The last major hurdle with Phase 1 proceeding was the Finance Plan and now that hurdle is gone — funding has been identified," said Transportation Secretary and CEO Stephanie Pollack. "Phase 1 of South Coast Rail will be funded one hundred percent by the Commonwealth and the MBTA will not be required to provide any capital funding or issue any revenue bonds that might otherwise impact the MBTA's future operating budget. We are now well on our way to offering passenger rail service to the South Coast in a few short years with the financing secure, major permits in hand and infrastructure being built."

"Today, restoration of passenger rail to the South Coast takes a major step forward thanks to the efforts of MassDOT, the MBTA, and the Executive Office for Administration and Finance to develop the Finance Plan," said Steve Poftak, MBTA general manager.

The South Coast Rail Phase 1 Finance Plan was created after independent cost and schedule reviews were conducted by three firms — the existing project manager, the existing owner's representative and an outside firm hired by the MBTA. A workshop was held to review the three submissions on cost and schedule and a consensus was achieved on the program cost of $1.047 billion. In consultation with the Executive Office for Administration and Finance, the decision was made that Phase 1 would be funded 100 percent by the Commonwealth through a combination of general obligation bonds and special obligation bonds to be issued under existing authorization for the Rail Enhancement Program.

The MBTA will not be required to issue any revenue bonds that might otherwise impact the MBTA's future operating budgets. All bond cap provided to the South Coast Rail Program will be in addition to the bond cap that MassDOT currently receives to fund its capital plan and there will be no reduction in bond cap allocated to MassDOT as part of the South Coast Rail Finance Plan.

While a previous estimate projected that Phase 1 would allow for passenger rail service between Boston and Taunton, New Bedford and Fall River to begin in late 2022, based on the consensus of the three independent reviews, the date for start of service is now projected to be in late 2023.

Several permitting milestones which have been achieved this year include this month's final USACE approval and the issuance of the Chapter 91 License, MassDEP 401 Permit and the Mass Coastal Zone Management Consistency Review.

The elements of Phase 1 of the South Coast Rail Program include:

  • Extending the existing Middleborough Line service using diesel-powered trains to New Bedford and Fall River;
  • reconstructing 17.3 mi. of the New Bedford Main Line and 11.7 mi. of the Fall River Secondary;
  • upgrading the existing Middleborough Secondary track from Pilgrim Junction to Cotley Junction, (a distance of 7.1 mi.);
  • constructing two new layover facilities; and
  • constructing six new stations.

For more information, visit mass.gov/south-coast-rail.




Today's top stories

Eight I-15 Bridges Open in Idaho, Project Still Ongoing

Next Generation Cat D8 Dozer Provides Next-Level Technology

BPC, Fay Lead Part of $1.5B PennDOT Project

CNH Designs Special Edition Case Compact Track Loader Inspired by Metallica Frontman James Hetfield

TxDOT's $802M I-30 Project in Dallas Area Makes Strides

Lane Construction Wins $152M Contract for I-77 Interchange in South Carolina

DEVELON to Showcase Three Machines at World of Concrete

Sacramento Airport Builds $140M Walkway


 







39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085