List Your Equipment For Free  /  Seller Login

Speed Vital to Completion of Louisiana's French Branch Project

Thu August 20, 2020 - Southeast Edition #18
Chuck MacDonald – CEG CORRESPONDENT


Barriere Construction, headquartered in Metairie, La., completed the French Branch paving project in less than one year.
Barriere Construction, headquartered in Metairie, La., completed the French Branch paving project in less than one year.
Barriere Construction, headquartered in Metairie, La., completed the French Branch paving project in less than one year. The aggressive schedule required a great deal of night paving operations. The project in Slidell, La., required work on I-10, I-12, I-59 and six on ramps. The paving teams used 176,000 tons of Superpave for the job.

For years, the confluence of I-10, I-12 and I-59, the French Branch Bridge and West Pearl River Bridge has enabled drivers to get where they needed to go in the New Orleans metro area. Motorists and residents alike were wary about the announcement of extensive reconstruction coming on these essential roads.

Most viewed it as a "good news, bad news" situation. The crumbling roadways was in dire need of repairs, but the three highways and six on ramps, known as the French Branch Project, would probably take a long time to fix.

Many locals — including construction industry experts — were shocked that the winning bid from Barriere Construction committed it to complete the massive project in less than one year. The next two lowest bids were commitments of 675 and 699 days respectively.

How could one firm complete a job in nearly half the time of its competitors? Barriere chose an asphalt alternative for the reconstruction. The asphalt bid, though slightly higher in construction costs, had user delay costs of $5.4 million ($15,000 per day), nearly half the cost of the other bids. The final bid of $45.3 million beat the nearest competitor by $2.3 million.

"When we first submitted our bid to the state, others challenged it and didn't think it was possible," said Ricky Quigley, Barriere's general superintendent on the French Branch project. "But we brought together a lot of resources, including the right equipment to work with and the people to make the project happen. We had multiple teams working the job and they put in a lot of hours to bring it in on time."

The Asphalt Advantage

Dave Newcomb and Jon Epps analyzed the project in the TTI Report: "Considerations and Case Studies in Rapid Highway Construction Using Asphalt Pavement"

"Barriere Construction does both asphalt and concrete pavement construction in Louisiana. Their choice of bidding the asphalt alternative was based on the flexibility and speed of construction that asphalt offered. Furthermore, asphalt allowed the construction in the critical ‘fast' zones to take place quickly allowing the remaining construction to take place behind barriers, thereby making the work safer for motorists and workers."

Barriere's construction team benefitted from having two asphalt plants in the area. This enabled it to keep a constant flow of material to the workers. Barriere also hired a quality control manager to ensure the road met the Louisiana Department of Transportation and Development (LADOTD) specifications and enabled the team to constantly communicate with the owner and owner's agent.

The LADOTD designed both asphalt and concrete versions of the French Branch rebuild. The asphalt version selected by Barriere required a 5-in. base course over the existing subgrade with a 10-in. Superpave binder course and a 2-inch Superpave wearing course. The road was topped by 0.75-in. open-graded friction course (OGFC), which helps to drain rain off the roadway and gives motorists increased stopping power when needed. In all, the paving teams installed 230,000 sq. yds. of asphalt base course, 176,000 tons of Superpave, and 6,000 tons of OGFC.

Excavation

A key requirement of the job called for the removal of the old concrete roadway before paving could begin. The construction team used excavator breakers and impact breakers to shatter the concrete into pieces small enough to be hauled away. In all, the Barriere team removed 93,800 tons of concrete.

Of course, the excavation was not without obstacles.

"Some of the more challenging subgrade was where I-10 passes over I-59," said Quigley. "The soil was so soft there that we had to excavate it 6 feet deep to find solid ground. We still got it done in time to open up for traffic Monday morning."

A vital component of the project's success was due to its skillful equipment management.

"On a project like this, we had to make sure that the right piece of equipment was at the right place at the right time," said Ben Tucker, director of equipment and facilities. "We were constantly asking, ‘Is there a way to get the job done faster?'"

"Over the last 15 years, Barriere has partnered with Caterpillar on our projects," said Tucker. "Probably 90 percent of our equipment is Cat, including our excavators, pavers and rollers. On a complicated job like the French Branch project, we needed to have absolute reliability for our equipment. Their partnership was crucial in getting the job done on time."

Tight Schedule

To adhere to its rigorous schedule, Barriere maintained a strong "bench" during the job.

"We had back-up crews in case someone had a family emergency or couldn't complete the shift," said Quigley. "Our schedule wouldn't allow us to drop behind. At the same time, our teams developed a great rhythm during their shifts and were extremely productive."

When a lane opened for work the team had to operate at peak proficiency. Quigley described the handoffs from one team to another.

"The lanes were turned over to us at 8 p.m. on a Friday night, so we would start demolition and then bring in a second crew about 1.5 hours later. The removal was scheduled from Friday night into Saturday morning. Then, we would bring in the milling machine to remove the soil-cement and help create a strong subgrade. The first paving crew would start around midnight and work for about 10 hours before the next paving crew would take over for their shift. Then, the lanes would be opened up for traffic on Monday morning at 5 a.m."

The weather presented other scheduling challenges, as the area's typical pop-up rain showers halted paving.

"We studied the weather maps carefully before turning our crews loose on the job," said Quigley.

Because of the French Branch Projects' proximity to the Gulf of Mexico and the possibility of severe storms, the construction team was required to be ready to reopen the road within 48 hours' notice.

Confined Spaces

Barriere faced numerous obstacles and restrictions if it were to complete its ambitious reconstruction plan. Detouring traffic would enable workers more space and time for the rebuild. However, because of high traffic volume and lack of frontage roads, this was impossible. Barriere approached this problem by narrowing traffic to one lane during night paving operations.

Quigley recalled some of the difficulties of working in laterally confined spaces.

"Sometimes we had a narrow stretch of about 1,800 linear feet to work in, then we would have to switch and work about the same length in another lane."

Because of the tight spaces, workers were not always able to work behind concrete barriers that provided maximum protection.

"We had cones to alert the drivers of our presence," said Quigley. "And we had electronic warning systems to tell us if any vehicle crossed into the work zone."

Bringing It Home

Once the confined spaces work was complete, the Barriere team could shift into high gear. While the DOTD plan allowed for road closures on 27 weekends, the Barriere team got it done in just nine.

By rehabbing the shoulders along the I-10 section, traffic could be safely redirected to make way for paving crews — at times, three simultaneously.

"This strategy enabled us to spend more time working on the main lanes," said Quigley. "After the work was complete, we milled the rehabbed shoulders and saved the paving material to use on other parts of the project or for future jobs."

With the job fully complete in 2016, Quigley now drives the French Branch project and reflects. "Our people invested a lot of time and effort in it. They performed admirably. This was a once-in-a-lifetime project." CEG


Chuck MacDonald

Chuck MacDonald is an editor, blogger and freelance feature writer whose writing adventures have taken him to 48 states and 10 countries. He has been the editor for magazines on pavement construction, chemicals, insurance and missions. Chuck enjoys bicycling, kayaking and reading. He graduated from the University of Missouri with a degree in journalism. Chuck lives in Annapolis, Md. with his wife Kristen. They have seven grandchildren.


Read more from Chuck MacDonald here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

MassDOT Plans to Replace Cape Cod's Sagamore Bridge With Two, Three-Lane Spans

HIPOWER Unveils T4F Mobile Power Models

Illinois DOT Celebrates Completion of I-55 Interchange Near Joliet, Shorewood


 







39.96118 \\ -82.99879 \\ Columbus \\ OH