List Your Equipment For Free  /  Seller Login

U.S. Nuke Waste Repository in New Mexico Will Expand

Wed October 25, 2017 - West Edition #22
Susan Montoya Bryan - ASSOCIATED PRESS


Workers are expected to begin mining operations at the U.S. nuclear waste dump in New Mexico for the first time in three years following a radiation release that contaminated part of the underground repository.
(U.S. Department of Energy photo)
Workers are expected to begin mining operations at the U.S. nuclear waste dump in New Mexico for the first time in three years following a radiation release that contaminated part of the underground repository. (U.S. Department of Energy photo)
Workers are expected to begin mining operations at the U.S. nuclear waste dump in New Mexico for the first time in three years following a radiation release that contaminated part of the underground repository.
(U.S. Department of Energy photo) The U.S. Energy Department announced that the work to carve out more disposal space from the ancient salt formation will begin later this fall. The work is scheduled to be complete by 2020.
(U.S. Department of Energy photo)

ALBUQUERQUE, N.M. (AP) Workers are expected to begin mining operations at the U.S. nuclear waste dump in New Mexico for the first time in three years following a radiation release that contaminated part of the underground repository, the Energy Department said on Oct. 17.

The work to carve out more disposal space from the ancient salt formation where the repository is located will begin later this fall and should be completed by 2020, the department said in a statement.

Workers will remove more than 112,000 tons (101,605 t) of salt, making way for seven disposal rooms. Each will have space for more than 10,000 drums containing up to 55 gal. (208 L) of waste.

The repository, named the Waste Isolation Pilot Plant, began accepting shipments of radioactive waste from defense sites and national laboratories earlier this year after being closed for nearly three years.

It's working to catch up with the nation's multibillion-dollar program for cleaning up tons of waste left behind by decades of bomb-making and nuclear research. The waste includes radioactive tools, gloves, clothing and other debris.

The pace of shipments is increasing slowly, but federal auditors recently raised concerns that the repository could run out of space. The U.S. Government Accountability Office also found that the Energy Department has no plans for securing regulatory approvals and expanding the Waste Isolation Pilot Plant before it reaches capacity in less than a decade.

Mining for the new disposal area first began in 2013 but was halted after the radiation release in February 2014.

A chemical reaction inside a barrel of waste that was inappropriately packed at Los Alamos National Laboratory before being shipped to the southern New Mexico repository was blamed for the radiation release.

Twenty-two workers at the repository were exposed, and monitors at the surface recorded low levels of radiological contamination. Officials maintained that nearby communities were not at risk.

The incident resulted in a $74 million settlement with the state of New Mexico for numerous permit violations at both the lab and the repository. Investigators said the misstep could have been avoided if existing policies and procedures had been followed.

The settlement, signed in early 2016, was at the time the largest ever negotiated between a state and the Energy Department.

Since then, some areas of the repository have remained off-limits, making it impossible for crews to do maintenance to prevent its ever-shifting salt ceilings and walls from collapsing.

In one area, monitors recently picked up on increased movement, indicating some instability. A rock fall last November forced a brief evacuation of workers but there were no injuries or contamination.

As the mining work resumes, officials said crews will install rock bolts to provide stability inside the new disposal vault.

A machine called a continuous miner removes the salt. It's loaded into a large truck and then a hoist that carries the material nearly a half-mile (0.8 km) to the surface.




Today's top stories

Turner Construction Leads $675M Concourse Project

Prioritize Planned Maintenance to Get the Most Out of Your Machines

Depreciation Bonus Begins Phase-Out

National Attachments Celebrates Its 35th Anniversary

California's I-80 Pavement Rehab Project Moving Along

CEG Speaks With New President of Chadwick-BaRoss, Thompson Equipment

Boston, MBTA Officials Reveal New Designs for Future Blue Hill Avenue Transit Project

Ole Miss Progressing Toward Construction of $125M Accountancy School


 







\\ \\ \\