List Your Equipment For Free  /  Seller Login

Walsh Construction Performs Bridge Slide on I-70 Project

Wed January 10, 2018 - Midwest Edition #1
Irwin Rapoport – CEG Correspondent


The $5.6 million project was awarded to Walsh Construction Company in 2017.
The $5.6 million project was awarded to Walsh Construction Company in 2017.
The $5.6 million project was awarded to Walsh Construction Company in 2017. For the second time in its history, the Indiana Department of Transportation (INDOT) is using a slide-in-bridge method to replace the twin bridges on Interstate 70 (I-70) at State Route 121/New Paris Pike (SR 121) in Wayne County.

For the second time in its history, the Indiana Department of Transportation (INDOT) is using a slide-in-bridge method to replace the twin bridges on Interstate 70 (I-70) at State Route 121/New Paris Pike (SR 121) in Wayne County. The $5.6 million project was awarded to Walsh Construction Company in 2017.

The work began last June and should be completed before June 2018. The first bridge slide was successfully executed on Sept. 10. The bridges, located between New Paris and Richmond, were built in 1959, are 131 ft. long and have two lanes in each direction. The new 71 ft. long bridges (single span) will be two lanes and have 10 and 6 ft. shoulders

The other roadwork includes building temporary pavement crossovers for maintaining traffic, shoulder strengthening, rebuilding and lowering State Road 121 below the bridges to increase vertical clearance.

"After nearly 60 years," said Nathan Riggs, information director, INDOT East Central District, "the bridges have reached the end of their useful service life and need to be completely replaced."

The new bridges and road infrastructure were designed by Beam Longest & Neff, with the project being financed by Federal and State funds. Daily traffic on the current bridges is 34,560 cars and trucks daily, which is expected to increase to 36,950 vehicles daily in 2037.

The construction work has led to recurring overnight lane closures on eastbound and westbound I-70 between 9 p.m. and 6 a.m. between State Road 227 (Exit 153) and U.S. 40 (Exit 156).

SR 121 may be closed under the I-70 bridges for a maximum of 60 days while SR 121 pavement and the I-70 bridges are rebuilt, according to the project web page. "Specific closure dates will be announced. During the closure of SR 121, highway traffic will be detoured south to U.S. 40 via Indiana Route 227, U.S. 27 and Ohio Route 320.

The first bridge slide and approach pavement tie-in was projected to take 13 days, but Walsh crews were able to complete the process in eight days. The second bridge slide took place on Oct. 13.

INDOT, after lengthy studies, favored a slide-in bridge construction method. For the slide, the new bridge decks are built on temporary supports adjacent to the existing bridge.

After the new bridge is built, according to the project web page, that direction of traffic will be reduced to one lane and temporarily shifted across the median to share the other side of the interstate with the opposing direction of traffic separated by concrete barriers. The existing bridge will be demolished and the new bridge will slide laterally into place. The approaches to the new bridge will be rebuilt, and traffic will be returned to its normal configuration. This sequencing will occur twice, once for each bridge and direction of traffic.

Walsh crews are still determining the amount of materials that will be removed with the demolition of the bridges.

The new bridges and roads are expected to use 2,400 cu. yds. of concrete and 80 tons of structural steel. Walsh established a staging area on the east side of the bridges in May 2017, complete with temporary offices, materials storage, and parking for its equipment.

On an average day there are about 10 Walsh and subcontractor personnel on-site. During the first slide, there were about 20 people on site. The subcontractors hired for the project are: Illini Drilled Foundations for 54-in. drilled shafts, Harmon Steel for structural steel erection, rebar, shear stud and stay-in-place formwork installation, Milestone Contractors LP for asphalt paving, Crackers Demo for existing bridge demolition and Roadsafe Traffic Systems for maintenance of traffic.

On this project, Walsh is using Cat 314, 315, and 321 excavators; a Cat D4 dozer; an Xtreme XR1255 telescoping forklift; an Enerpac RRH-603 hollow core cylinders (for pulling bridge); and a Cat 279 skid steer loader.

Equipment is being rented from Herc Rentals in Indianapolis and MacAllister Rentals in Richmond, Indiana.

The company's closest yard/shop is approximately 75 miles away from the work site.

CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Louisville Pump Station Receives $230M Update

Amtrak Secures $112M in Federal Funds to Upgrade 13 Projects in Northeast Corridor

Hitachi Construction Machinery Wins Silver in 2024 Anthem Award

Turner Construction Leads $675M Concourse Project

Bobcat Celebrates Season of Giving With Volunteerism, Hurricane Relief, Philanthropic Support

Thompson Tractor Hosts Caterpillar Demo in Oxford, Alabama

Rokbak Haul Track Telematics Boost Uptime With Proactive Maintenance

RIDOT Officials Mark Completion of Key $8.9M Road Resurfacing in Middletown, R.I.


 







39.96118 \\ -82.99879 \\ Columbus \\ OH