List Your Equipment For Free  /  Seller Login

Years After Hurricane Harvey, Dam Still Under Repair

Wed March 25, 2020 - Southeast Edition #7
Irwin Rapoport – CEG Correspondent


Pumping water out of the spillway approach channel scour hole
Pumping water out of the spillway approach channel scour hole
Pumping water out of the spillway approach channel scour hole Hauling excavated material to fill in scour hole left by damage incurred by the Vernon Lake dam and spillway during Hurricane Harvey in 2017. A Komatsu dozer helps fortify the embankmen A Komatsu excavator places an armor stone barrier for retention purposes.
 Nearing finished grade…

Hurricane Harvey caused extensive damage in Texas and Louisiana during August 2017, including major devastation to the Vernon Lake dam and spillway in Vernon, La., which is the subject of a $1 million Louisiana Department of Transportation and Development (LADOTD) repair project.

The contract was awarded to Merrick Construction LCC in February 2019 and work began last July. The earthen dam, spillway approach channel and the spillway itself were all damaged by Harvey, and crews from Merrick have completed all of the major benchmarks (with work ongoing to complete the patching on spillway).

"When delivered, the management gate will be completely closed again, allowing Vernon Lake to refill at the maximum rate nature allows," explained Erin Buchanan, LADOTD's public information officer. "LADOTD initiated the process of allowing the lake to refill by closing the management gate several months ago. We recently slowed the rate of rise of the water level in the lake by slightly opening the management gate to ensure the last few items of work within the spillway can be completed."

The damage to the infrastructure was considerable, with the embankment being affected by major cracks — between 75 and 100 ft. on the lake side and approximately 200 ft. on the downstream side. This led to the embankment sliding into the water between 5 and 10 ft.

The dam consists of a 5,275-ft. earthen embankment with a 300-ft.-wide concrete chute spillway and approach channel. It also has a management control structure that consists of a 6x6-ft. concrete conduit penetration of the embankment with an inlet tower and sluice gates.

"The damages were precipitated by rainfall associated with Harvey that produced approximately 20 inches of rain over a fourday period," Buchanan said. "The embankment experienced a slide on the downstream slope near the east abutment that extended from the downstream crown to near the downstream toe of the embankment. There was an existing minor surficial slide on the lake side of the embankment near the location of the newly developed downstream slide.

"Additionally, during the high flow event, significant scouring occurred within the earthen spillway approach channel that was approaching the concrete chute spillway," she added. "The spillway approach channel scour was caused by modifications [cutting a boat channel into the approach channel] that had occurred many years earlier. Also due to the high flows in the concrete spillway, some areas that had previously been patched were damaged."

Due to the damage, the lake water surface elevation was lowered approximately 17 ft. and maintained that level as much as possible in order to prevent loading on the embankment in area of the slide, as well as providing storage to prevent any spillway flows for rainfall events.

"The initial concerns during the event were loss of the earthen embankment and a breach of the dam," Erickson said. "Had the dam breached, analysis indicates that multiple structures would have been flooded, as well as significant flooding and potential damage to numerous state and parish [county] roads."

Authorities had to develop a repair plan, and the first item was to lower the water surface in order to adequately assess all of the damage.

"Surveys of the entire structure were taken," Erickson said. "A geotechnical investigation was performed in the area of the embankment slides. Stability analysis was performed on various embankment configurations and a downstream stability berm was selected as the final embankment configuration. A complete assessment of all damages was made, with plans and specifications developed to repair the damages. Concurrent with the damage assessment and design process, funding sources for the project were secured."

The repair project was designed by LADOTD personnel. The stability analysis was performed by Fred Young P.E., dam safety engineer, and the plans were developed by Bradley Sticker P.E., water resources engineer.

"Near the completion of the plans for repairs, over 15 inches of precipitation occurred in three weeks," Erickson said. "This saturated the embankment and resulted in the downstream slide lengthening. This required the embankment to be resurveyed and new plans developed."

The expected lifespan of the infrastructure, with the repairs, is 50 years. The dam was originally constructed in 1961. For work to proceed safely, the water surface had to be lowered 20 ft. below pool stage (elevation 225 ft.), at a minimum. Alsey Lachney, Merrick Construction's project manager, has overseen similar projects and put a considerable effort into planning the schedule and benchmarks. "The material was excavated by tractors with scrapers and excavators," Lachney said. "The depth of the cut was a challenge — it was a big levee and it was steep getting in and out. The rain also affected work for a couple of days."

The approach channel repairs dealt with filling in holes.

"There was a fairly large hole that had been scoured out from the high water, and the hole was full of water that had to be pumped out," Lachney explained. "We filled it up with embankment material that was removed from the slide. It was a challenge because the channel had a lot of seepage coming up from the sand. The material was saturated, you could barely walk on there, and the equipment had a tough time getting in and out, but we did fix it."

The spillway work went according to plan, finishing up in early February. Much of this work involved concrete patching and dealing with spalls.

"There were a lot of spalls, which was flaking the concrete spillway," Lachney said. "We sawcut out sections — 2 to 3 inches deep, chipped them down and poured material back in."

The only subcontractor was Coastal Highway Erosion Control, which was brought in for the final seeding of the matting.

Peak days saw close to 15 Merrick employees on site, including excavator, dozer and truck operators, and several laborers. Five people were engaged in the excavation/dirt work and 10 for the spillway repairs.

Approximately 17,000 cu. yds. of material was excavated from the levee and 27,000 cu. yds. was brought in, and 82 sq. yds. of concrete was brought in for the patching.

Equipment utilized by crewmembers included a large Komatsu excavator, a large Komatsu dozer, a John Deere tractor and scraper, a Case tractor and scraper, a Cat pad roller and a John Deere tractor with discs.

"When you work in the bottom of the channel scour area, there's a lot of sand and it grinds the metal — this was one of the biggest wear and tear issues," Lachney stated. "We have a good maintenance program, and no major repairs occurred during the construction process."

The firm purchases and rents equipment from Louisiana Cat, H&E Equipment Services, Scott Equipment and Bottom Line Equipment.

For more information, visit www.bottomlineequipment.com, https://he-equipment.com/, www.louisianacat.com, and www.scottcompanies.com. CEG


Irwin Rapoport

A journalist who started his career at a weekly community newspaper, Irwin Rapoport has written about construction and architecture for more than 15 years, as well as a variety of other subjects, such as recycling, environmental issues, business supply chains, property development, pulp and paper, agriculture, solar power and energy, and education. Getting the story right and illustrating the hard work and professionalism that goes into completing road, bridge, and building projects is important to him. A key element of his construction articles is to provide readers with an opportunity to see how general contractors and departments of transportation complete their projects and address challenges so that lessons learned can be shared with a wider audience.

Rapoport has a BA in History and a Minor in Political Science from Concordia University. His hobbies include hiking, birding, cycling, reading, going to concerts and plays, hanging out with friends and family, and architecture. He is keen to one day write an MA thesis on military and economic planning by the Great Powers prior to the start of the First World War.


Read more from Irwin Rapoport here.





Today's top stories

Progress Continues On $250M Columbus LOT Project

Work Continues On Largest Project in NYSDOT History

OSHA Puts PPE for Women, Hard Hats On Its Radar

Case Introduces Limited Signature Edition Backhoe Loader for Iconic Presence On Job Site

Consider These Comfort, Performance Features When Selecting Your Next Compact Track Loader

Aerospace Hub Construction Starts

Vantage Selects Turner Construction Corp. for $2B Expansion Project

AES Ohio Powers Economic Development With Major Upgrades


 







39.96118 \\ -82.99879 \\ Columbus \\ OH \\ 43085