List Your Equipment For Free  /  Seller Login

Gomaco Takes I-670 to New Heights

Mon March 14, 2005 - Midwest Edition
Construction Equipment Guide


Complete General Construction in Columbus, OH, has owned Gomaco machines since 1970. Its tackled several challenging projects and completed them all. And last summer, the company started work on a project that would take them to new heights on I-670 through downtown Columbus.

The contract called for approximately 16,000 ft. (4,877 m) of barrier and parapet walls, including 420 ft. (128 m) of 93-in. (236 cm) tall wall with no caged-steel reinforcing.

It could be the tallest barrier wall ever slipformed without steel reinforcement.

“The most difficult aspect of the project had to be just trying to decide to slip the wall or handform it,” explained Jeff Thompson, concrete division manager of Complete General. “It was a gamble for us. The wall design was a modified Ohio Department of Transportation 50 inch single-slope, center-line barrier wall. In this tall section, it grew from 73 to 93 inches and we determined that it was actually more cost effective to slipform it than to handform and pour it.”

The company had experience slipforming wall, just nothing this tall. In fact, very few companies have experience with extremely tall walls.

Complete General went to Indiana to consult with CRI Construction. The Indiana contractor successfully slipformed a 104-in. (264 cm) tall wall over steel reinforcing with its Commander III.

Complete General would be using the company’s old work horse, its Commander IV, to slipform the wall.

“The Commander IV is the oldest paving machine we have right now and we just love it,” said Joe Kuhn, concrete superintendent. “It’s just been so versatile for us and you wouldn’t believe how many different operations we’ve been able to use it for. I knew it was the machine for this wall.

“The biggest thing on a project like this is the concrete,” he added. “You have to communicate with your supplier and make sure everyone’s on the same page about the low slump, the consistency of the slump and the timely arrival of the trucks. You have to take into consideration that the machine and mold are a gimme. They’re going to work, so the concrete is the only variable.”

Complete General used an old-fashioned concrete mix design with no chemical additives, just a consistent low slump of 0.5 inches (1.3 cm). Ready-mix trucks were limited to 8-cu.-yd. (6.1 cu m) loads, too.

“It helped with slump control,” Thompson said. “Unloading the trucks took 15 to 20 minutes and it took a truck and a half to go through the mold, so you basically had one-half hour that the concrete was sitting in the mold before it came out the back. The smaller loads could be controlled a lot better.”

A total of 10 vibrators worked to consolidate the low-slump concrete inside the mold. Complete General had all of the vibrators rebuilt before the pour, just to eliminate any potential problems on the pour.

The tall wall section of the project was slipformed in two days, moving at a production rate of only four in. (10.2 cm) per minute.

“We didn’t set any land-speed records on this pour,” Thompson said. “It just took so much concrete to go 12 inches and we figured 12 inches of the new wall had to weigh two tons. It was slow, but we couldn’t have handformed and poured it in two days.”

“It moved at a snail’s pace but we sure got a good product out of our Gomaco machine,” added Kuhn. “When you’re standing next to a 93 inch piece of fresh concrete slipped out, it’s something to see. It really is.”

Complete General finished the entire wall project successfully and have since moved on to other challenges. This year it will be slipforming a 102-in. (259 cm) wall, this time over steel reinforcing.

“The Commander IV is just a nice machine and we’ll probably own ours forever,” Thompson said. “We’ve had great success with all our Gomaco products. On this wall, everything went off without a hitch and we had no problems slipforming any of the wall. In fact, I think we could add another 10 to 12 inches to the tall wall.”

(This story appears courtesy of Gomaco World.)




Today's top stories

VIDEO: $4.7B Gordie Howe International Bridge Project Nears Completion

Volvo CE Upgrades Straight Boom Demolition Excavators

Construction Market Boosts Economy

Bobcat Company Donates $885,000 in Equipment to Support Salvation Army's Disaster Relief Efforts

VIDEO: KEMROC Expands; Plans to Increase Nationwide Presence

INFRA Grant Moves Ohio's N. Coast Connector Project Steps Closer

John Deere Construction Introduces Flexible Customer Training Options

VIDEO: First of Two Sections of NYC's $1.45B East Side Coastal Resiliency Project Is Complete


 







39.96118 \\ -82.99879 \\ Columbus \\ OH