Construction Equipment Guide
470 Maryland Drive
Fort Washington, PA 19034
800-523-2200
The project involves the installation of the longest continuous curved conveyor ever to be installed in the state of Maryland.
Wed November 16, 2016 - Northeast Edition #23
The second phase of a quarry replacement project in Carroll County, Md., which involves the installation of the longest continuous curved conveyor ever to be installed in the state, is nearing completion.
The private project for an undisclosed dollar amount is for Lehigh Cement Company LLC. The company is currently replacing its Union Bridge Quarry with a greenfield quarry expansion in the neighboring town of New Windsor.
The Phase 2 contract was awarded to Fay, an i+iconUSA Company, with Scott Wilson serving as senior project manager.
Work on this phase began in October of 2015, and was originally scheduled for completion on Jan. 31, 2017. However, crews currently forecast completion in late 2016.
Phase 2 includes site development services for the development of an initial pit, crusher pad, building pad, and transfer tower pad. Extra work added once the project started included the installation of a haul road and erection of a Mechanically Stabilized Earth (MSE) retaining wall and foundations associated with the new crusher system.
Earthwork includes 1.6 million cu. yds. (1.2 million cu m) of total excavation; 685,000 cu. yds. (523,720 cu m) of overburden removal; and 936,000 cu. yds. (715,623 cu m) of blasting and rock excavation. A total of 1.1 million cu. yds. (841,010 cu m) was placed in controlled fill embankments for the building pad, perimeter berm, and haul road. The haul road connects the initial pit, crusher dump area and building pad, and will allow the owner to begin production mining operations at the completion of the contract.
The building pad is the site for a 13,000 sq. ft. (1,208 sq m) shop/office for quarry administration and equipment maintenance. The shop/office is being constructed under Fay's other Lehigh contract, along with a 4.7-mi. (7.6 km) overland conveyor.
Concrete work on the project includes construction of eight concrete footings for a crusher installed by others, as well as a truck unloading pad at the top of the retaining wall to allow 100-ton (91 t) mining trucks to dump directly into the crusher.
The MSE retaining wall constructed inside the crusher pit created grade separation and access for mining trucks to dump into the crusher. The wall is 50 ft. (15.24 m) high and 400 ft. (122 m) long, with tapered ends. Reinforcement of the wall was much heavier than a standard highway wall due to the height and extreme 294,000 lbs. (133,356 kg) surcharge imparted by loaded 100-ton mining trucks. Up to 11 40-ft. (12-m) long galvanized steel straps per 24 sq. ft. (2.2 sq m) panel were used to reinforce the retained fill. Reinforced fill passing a 3 in. (7.6 cm) sieve was crushed on site from limestone in the quarry.
Fay is concurrently working on Phase 1 of this project, which includes excavation, installation of 9,600 ft. (2,926 m) of box culverts, 11,000 ft. (3,353 m) of slab-on grade, and several foundations for the ultimate installation of a 4.7-mi. conveyor system to enable the client to transport crushed limestone from the quarry to its Union Bridge cement plant. This will be the largest curved conveyor in the state of Maryland.
“The karst geology of this limestone deposit presented significant challenges to the excavation and blasting crews,” Wilson said. “The depth of bedrock was extremely variable due to dissolved limestone and faults. Limestone pinnacles up to 20 feet high were overlain and surrounded by soft, wet clays. A high water table compounded the difficulties, since the crusher pit was excavated 30 feet below an active stream. The fill material in the early portion of the project was excavated from above and in between the limestone pinnacles and consisted of clays and poor quality soil, which made it challenging to build haul roads.”
According to Wilson, the limestone mined in the New Windsor Quarry is more than 900 million years old and will supply the Lehigh Cement plant with more than 70 years' worth of raw materials. The Lehigh Union Bridge plant is the second largest cement producing facility in North America and supplies cement from New York to Indiana. At completion, the New Windsor quarry pit will be more than 400 acres and 700 ft. (213 m) deep.
“The initial stripping and working through the karst layer has been a major challenge that Fay has safely accomplished while maintaining their development schedule. Fay has placed safety as their top priority, meeting Lehigh's high expectation and requirements as well as appropriately addressing community concerns. Fay has been a professional and competent company that will be asked to bid on future projects,” commented Kevin Cove, director of project engineering, Lehigh Cement.
The safety regulations on the project are per the Mine Safety and Health Administration (MSHA), not OSHA. Notable differences in MSHA regulations are: vehicle parking brakes, equipment inspection reports, wheel chocks, and task-specific training. The project included 90 acres of clearing and grubbing and the excavation of 1.6 million cu. yds. of overburden, bedrock, karst, limestone and phyllite material.
In addition, crews excavated a 100 by 100 by 15 ft. (30 by 30 by 4.5 m) sump and constructed a 117,000 cu. yd. (89,453 cu m) berm, a 425,000 cu. yd. (324,936 cu m) building pad and a 345,000 cu. yd. (263,771 cu m) haul road. They also installed a 15,500 sq. ft. (1,440 sq m) mechanically stabilized earth retaining wall and 7,000 linear ft. (2,133.6 m) of 12 in. (30.5 cm) HDPE dewatering line, along with continuous dewatering with 6 to 12 in. (15 to 30.5 cm) pumps.
Major subcontracted jobs include blasting by M&J Explosives of Carlisle, Pa.; clearing and grubbing by Deamer Land Clearing of Mifflintown, Pa.; survey and layout by Johnson Bernat Associates (JBA) of Gaithersburg, Md.; erosion control by Hawkins Erosion Control LLC of Mount Airy, Md.; and photogrammetry (aerial mapping) by Identified Technologies, Pittsburgh, Pa.
Major equipment used on the job includes Caterpillar 740B and Komatsu HM400 40-ton (36 t) articulated trucks; Caterpillar 385 and 349 and Komatsu 490 and 650 production excavators; Komatsu PC200, PC300, and PC360 utility excavators; 65-ton (59 t) Link-Belt rough terrain cranes; Ingersoll Rand rollers; a Caterpillar 825H compactor; and Caterpillar D8T, D10N, D9T, and D6N dozers.
Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.
Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.
Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.